Interim Management Statement

19 May 2010 07:00

RNS Number : 1523M
Melrose Resources PLC
19 May 2010
 



FOR IMMEDIATE RELEASE

19 May 2010

    MELROSE RESOURCES PLC

 

Interim Management Statement

 

 

Melrose Resources plc (LSE: MRS) ("Melrose" or "the Company"), the oil and gas exploration, development and production company, today issues its Interim Management Statement to cover the period 1 January 2010 to 31 March 2010 ("the first quarter") and an operations update. This information is provisional and unaudited and may be subject to further review.

 

Exploration

 

During the first quarter Melrose has drilled two exploration wells in Egypt in the onshore Nile Delta and commenced 2D seismic data acquisition programmes in two frontier areas, namely, the Mesaha concession in southern Egypt and the South Mardin concessions in Turkey.

 

In Egypt, the South Damas-1 exploration well was drilled to test a prospect in the Sidi Salim formation close to the Damas field in the South East Mansoura concession. The well encountered the top reservoir at a depth of 4,345 feet and penetrated 76 feet of net gas pay with good reservoir properties. The preliminary estimate of the discovered reserves is 30 Bcfe, which is in line with the pre-drill analysis. During the first quarter the Tall Rak-1 exploration well was also drilled to test a Sidi Salim prospect but no hydrocarbon indications were found and the well was plugged and abandoned. Two further wells Sakr-1 and South East Dikirnis-1 are planned to be drilled in the second half of the year targeting combined unrisked reserves of 53 Bcfe with an average chance of success of 51%.

 

The Mesaha 2D seismic survey has been completed with 1,047 kilometres of data being acquired over the western side of the concession, which contains an undrilled Palaeozoic sedimentary basin. The seismic data indicates the presence of a strong shallow reflector and this is now interpreted as being the top of the Palaeozoic section. The data quality below the reflector is variable but ongoing processing studies indicate the presence of stratigraphic layering beneath the reflector and the overall basin architecture is consistent with the findings of earlier gravity and aeromagnetic surveys. The technical analysis of the data is still ongoing and, depending upon the results, further 2D seismic may be acquired prior to drilling an exploration well in the block.

 

Melrose has also commenced a 2D seismic acquisition programme over the large Kanun oil lead in the South Mardin concessions in Turkey. To date 210 kilometres of data have been acquired out of a planned total of 245 kilometres and the initial results should be available by mid year. Assuming that the Kanun lead is confirmed as a good quality prospect, it will be scheduled for drilling as early as practicable in 2011. Alternatively, the Company will acquire a second phase of seismic data in late 2010 over other oil leads which have been identified in the concession area.

 

In Bulgaria, Melrose has contracted the GSP Jupiter jack-up rig to drill the Kavarna East prospect in July 2010. This prospect is located between the existing Kavarna and Kaliakra discoveries and contains unrisked reserves of 12 Bcf with a high chance of success of 80%. An option has been negotiated in the rig contract to the drill the Kaliakra East prospect as part of the same drilling programme assuming that this is operationally feasible. This prospect has unrisked reserves of 59 Bcf and a chance of success of 34%, however, the water depth at the selected location is close to the operating limit of the jack-up unit. 

 

Field Developments

 

In Egypt, the South Damas development is progressing well and the construction of the 6.5 kilometre tie-back line to the existing Damas facilities is nearing completion. The field is expected to be on stream by late June, approximately six weeks ahead of schedule, and should produce at gas rates of around 12 MMcfpd. The existing Salaka-1 production well has also been successfully recompleted into an untapped reservoir interval in the Kafr El Sheik formation and is producing at 5.5 MMcfpd. During the first quarter, Melrose completed its West Dikirnis Phase II development programme in Egypt through the installation of the Liquid Petroleum Gas ("LPG") and Gas Re-injection ("GRI") facilities.

 

In Bulgaria, Melrose has now received Certificates of Commerciality for both the Kavarna and Kaliakra fields from the Bulgarian Government and the development plans for both fields are well advanced. The Jupiter jack-up rig is due on location to install the Kaliakra subsea tree at the end of June (before drilling the Kavarna East exploration well) and the Bigfoot lay barge will simultaneously commence work on the flow lines. The Kavarna first gas date is now expected to be in August with Kaliakra to follow in early October.

 

The Bulgarian authorities have requested additional independent feasibility studies to be carried out on the proposed conversion of the Galata gas field into a storage facility. Melrose is supporting these studies whilst maintaining a clear focus on delivery of the Kavarna and Kaliakra developments which are viewed as the Company's key 2010 projects.

 

Business Development

 

Melrose is in the final stages of receiving the regulatory approvals necessary to complete the farm-in transaction to acquire a 32.5% interest in the Midia and Pelican concessions, offshore Romania. The development plans for the two existing gas discoveries, Ana and Doina, are being finalised and approvals are being sought from the authorities to drill the Eugenia South exploration well in the fourth quarter of the year.

 

Production and Product Prices

 

Melrose's production in the first quarter totalled 16.6 Bcf of gas and 668 Mbbls of oil and condensate on a working interest basis, which represents a 17% increase compared with the same period in 2009. The increase is primarily due to a strong contribution from new discoveries brought on stream during the course of 2009. Average daily production in the first quarter was 38,131 boepd on a working interest basis. On a net entitlement basis, first quarter production totalled 6.9 Bcf of gas and 302 Mbbls of oil and condensate giving an average daily rate of 16,043 boepd.

 

A summary of the Company's working interest and net entitlement production by country in the first quarter is as follows:

 

Working Interest

 

Egypt

Bulgaria

US

Total

Total Volume

 

 

 

Gas (Bcf)

16.36

-

0.23

16.58

Liquids (MMbbl)

0.62

-

0.05

0.67

Average Daily Rate

 

 

 

 

Gas (MMcfpd)

181.73

-

2.53

184.27

Liquids (bpd)

6,877

-

543

7,420

Oil equivalent (boepd)

37,165

-

966

38,131

 

Net Entitlement

 

Egypt

Bulgaria

US

Total

Total Volume

 

 

 

 

Gas (Bcf)

6.63

-

0.23

6.85

Liquids (MMbbl)

0.25

-

0.05

0.30

Average Daily Rate

 

 

 

 

Gas (MMcfpd)

73.61

-

2.53

76.14

Liquids (bpd)

2,810

-

543

3,353

Oil equivalent (boepd)

15,077

-

966

16,043

 

The average product prices realised by the Company in the first quarter were as follows:

 

 

Egypt

Bulgaria

US

Group

Gas ($ per Mcf)

2.81

-

5.35

2.90

Oil and condensate ($ per bbl)

74.06

-

73.36

73.95

 

Financial Position

 

Total capital expenditure in the first quarter amounted to $29.8 million, of which $22.9 million was on development and $6.9 million on exploration activities.

 

There have been no major changes in the Company's balance sheet since 31 December 2009 and the net debt at 31 March was $483.5 million. The Company has a senior debt facility of $450 million and a subordinated debt facility of $70 million. Both facilities are committed until 2014. The margin on the facilities is competitive and would equate to 3.3% above US$ LIBOR assuming the loans were to be fully drawn.

 

During the first quarter, the Company proposed that a final dividend for 2009 of 3.1 pence per share would be paid to Shareholders. Assuming that this dividend is approved at the Annual General Meeting scheduled to be held on 10 June 2010 it will be paid on 20 July 2010.

 

Business Outlook

 

In light of the first quarter performance and ongoing development activities, the Company is maintaining its current 2010 production guidance at 40.0 Mboepd on a working interest basis. This equates to 17.5 Mboepd on a net entitlement basis assuming a Brent oil price of $70 per barrel. 

 

The 2010 capital expenditure forecast remains at $142 million of which 62% is dedicated to field development activity and the remainder to exploration and new business initiatives. Approximately 40% will be spent in Bulgaria, 33% in Egypt and the remainder split between Romania, USA and Turkey. 

 

The main components of the Company's short to medium work plans include: in Bulgaria, implementing the Kavarna and Kaliakra field developments and continuing the exploration drilling programme on the Galata/Kaliakra trend; in Egypt, drilling two exploration wells in the Nile Delta and completing the new Mesaha seismic data processing; in the USA, continuing the secondary recovery programme in the Permian Basin; in Turkey, completing the first phase of the seismic acquisition and processing programme over the South Mardin blocks and in Romania, completing the formal regulatory process to acquire the Midia and Pelican block interests prior to proceeding with the Ana and Doina field developments and the exploration drilling programme.

 

Commenting on this report, David Thomas, Chief Executive, said:

 

"Melrose's strong production performance has continued in the first quarter of the year, helping to underpin our exploration and development programmes. We are also pleased with the progress being made on our new field developments both in Egypt and the Western Black Sea, where the Kavarna and Kaliakra fields are expected to make a significant contribution to group revenues later this year. We also remain hopeful that our Romanian farm-in transaction will receive regulatory approval in the near future." 

 

 

For further information please contact:

 

Melrose Resources plc

David Thomas, Chief Executive

Robert Adair, Executive Chairman

Diane Fraser, Finance Director

 

 

0131 221 3360

Buchanan Communications

Tim Thompson

Ben Romney

 

0207 466 5000

 

 

or visit www.melroseresources.com

 

 

 

Glossary:

bbl - barrel of oil or condensate or natural gas liquids

Bcf - billion cubic feet of gas

Bcfe - billion cubic feet of gas equivalent

boepd - barrels of oil equivalent per day

bpd - barrels of oil or condensate per day

Mboepd - thousand barrels of oil equivalent per day

Mcf - thousand cubic feet

MMbbl - million barrels of oil or condensate or natural gas liquids

MMcfpd - million cubic feet per day

 

Disclaimer

This announcement contains certain forward-looking statements that are subject to the usual risk factors and uncertainties associated with the oil and gas exploration and production business. While Melrose believes the expectations reflected herein to be reasonable, the actual outcome may be materially different owing to factors either within or beyond Melrose's control, and accordingly no reliance may be placed on the figures contained in such forward looking statements. 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
IMSQVLFFBEFBBBZ
Date   Source Headline
20th May 20083:36 pmRNSArticles of Association
15th May 200812:14 pmRNSAnnual Report and Accounts
13th May 20088:30 amRNSInterim Management Statement
24th Apr 200811:04 amRNSOperations Update
11th Apr 20083:20 pmRNSDirector/PDMR Shareholding
31st Mar 20089:56 amRNSDirector/PDMR Shareholding
31st Mar 20089:35 amRNSTotal Voting Rights
27th Mar 20083:21 pmRNSBlock Listing Return
27th Mar 20083:13 pmRNSMajor Interests in Shares
27th Mar 200810:33 amRNSDirector/PDMR Shareholding
25th Mar 200811:30 amRNSTR-1-Notification of Interest
18th Mar 20087:01 amRNSPreliminary Results
25th Feb 200810:15 amRNSAnalyst Site Visit
19th Feb 200811:30 amRNSNotice of Results
19th Feb 20089:30 amRNS2007 Production Report
31st Jan 20084:40 pmRNSSecond Price Monitoring Extn
31st Jan 20084:35 pmRNSPrice Monitoring Extension
21st Jan 20087:01 amRNSDrilling Update
18th Jan 20084:40 pmRNSSecond Price Monitoring Extn
18th Jan 20084:35 pmRNSPrice Monitoring Extension
17th Jan 200811:19 amRNSEgypt Update
14th Jan 20084:25 pmRNSAnnual Information Update
4th Jan 200811:15 amRNSUnited States Update
7th Dec 200711:19 amRNSDirector's Shareholding
7th Dec 200711:16 amRNSBulgaria Update
4th Dec 20074:35 pmRNSPrice Monitoring Extension
30th Nov 200710:59 amRNSOperations Update
28th Nov 200710:20 amRNSIndependent Non Exec Director
13th Nov 20073:01 pmRNSDirectorate Change
8th Nov 20074:40 pmRNSSecond Price Monitoring Extn
8th Nov 20074:35 pmRNSPrice Monitoring Extension
7th Nov 20079:55 amRNSBulgarian Operations Update
2nd Nov 200711:00 amRNSBond Offering Update
18th Oct 200710:22 amRNSE250m Bond Offering
10th Oct 20077:01 amRNSOperations Update
21st Sep 20077:01 amRNSInterim Report
4th Sep 200711:03 amRNSHolding(s) in Company
3rd Sep 20074:35 pmRNSDirector/PDMR Shareholding
30th Aug 20071:51 pmRNSHolding(s) in Company
29th Aug 20077:00 amRNSInterim results
24th Aug 20072:58 pmRNSChange of Company Secretary
24th Aug 20072:21 pmRNSChange of Company Sectretary
9th Aug 20079:30 amRNSNotice of Results
8th Aug 200711:57 amRNSDirectors' Share Plan
12th Jul 20073:42 pmRNSDirector's Shareholding
12th Jul 20073:42 pmRNSBlock Listing Return
11th Jul 200711:00 amRNSEgypt Drilling Update
28th Jun 20075:04 pmRNSDirectors' Shareholdings
28th Jun 20071:28 pmRNSPerformance Share Plan
21st Jun 200710:31 amRNSDirectors' Shareholdings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.