Roundtable Discussion; The Future of Mineral Sands. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksKsk Power Regulatory News (KSK)

  • This share is currently suspended. It was suspended at a price of 1.50

Share Price Information for Ksk Power (KSK)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 1.50
Bid: 0.00
Ask: 0.00
Change: 0.00 (0.00%)
Spread: 0.00 (0.00%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 1.50
KSK Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Indian Subsidiary Results and Trading Update

31 May 2016 13:44

RNS Number : 7620Z
KSK Power Ventur PLC
31 May 2016
 

 

 

 

 

 

KSK Power Ventur PLC

31 May 2016

 

KSK Power Ventur plc("KSK" or the "Group" or the "Company")

 

Indian Subsidiary Financial Results and Trading Update

KSK Power Ventur plc (KSK.L), the power project company listed on the London Stock Exchange, with interests in multiple power plants and businesses across India, is pleased to announce that its Indian subsidiary, KSK Energy Ventures Limited ("KSKEV"), the equity shares of which are listed and traded on the National Stock Exchange of India Limited ("NSE") and the BSE Limited ("BSE") has filed its financial results for year ending 31 March 2016 under Indian GAAP with the NSE and BSE.

Full details of the KSKEV results are available at: http://www.bseindia.com/xmldata/corpfiling/AttachLive/853543E0_07F8_4F94_9D62_ED21811D3259_120237.pdf

In addition, the Company is able to give the following trading update up to 31 March 2016.

During the twelve month period operating assets generated 9,987 GWh with an average portfolio plant load factor of 55%, as against 6,158 GWh (34%) for FY 2015, and 5,757 GWh (32%) for FY 2014.

 

 

31 March 2016

31 March 2015

31 March 2014

 

 

KSK Mahanadi ( 1200 MW)

6,368 GWh

(60%)*

3,203 GWh

(30%)*

1,088 GWh

(10%)*

 

Sai Wardha (540 MW)

 1856 GWh

(39%)

1,174 GWh

(25%)

2,586 GWh

(55%)

 

VS Lignite (135 MW)

792 GWh

(67%)

851 GWh

(72%)

902 GWh

(76%)

 

Sai Regency (58 MW)

459 GWh

(90%)

423 GWh

(83%)

445 GWh

(88%)

 Sai Lilagarh (86 MW)

172 GWh

(23%)

148 GWh

(20%)

341 GWh

(45%)

 

Sitapuram Power (43 MW)

324 GWh

(86%)

343 GWh

(91%)

342 GWh

(91%)

 

Solar Project (10 MW)

17 GWh

(19%)

16 GWh

(18%)

19 GWh

(21%)

 

 

TOTAL

9,987 GWh

(55%)

6,158 GWh

(34%)

5,757 GWh

(32%)

 

*KSK Mahanadi's PLF is calculated across the periods on the installed capacity base of 1200 MW although actual operations of this capacity only commenced substantially during the second half of FY 2016 (upon grant of the necessary transmission corridor access for supplying through the National Grid).

The near 10 TWh of generation has resulted in a significant uplift in gross revenue, supported by increased supply tariffs, as well as additional tariff entitlement under change in law provisions of the underlying Power Purchase Agreements (PPAs) with state owned distribution companies. With current generation at KSK Mahanadi supported by a combination of coal linkage from South East Coalfields Limited, as well as higher priced e-auctions of domestic coal periodically being conducted by SECL, the Board expect EBITDA to be in line with market expectations and further improvements to EBITDA are anticipated upon coal linkage stabilisation.

With capitalisation of the entire common infrastructure setup at KSK Mahanadi and associated debt being charged to operations, higher interest charges were incurred during FY 2016. Together with finance costs at other projects, higher finance costs are therefore expected for the period ending 31 March 2016. However, going forwards, the Board have initiated debt refinancing discussions for a number of assets, such as at VS Lignite and Sai Wardha, with the potential for interest savings coupled with a longer repayment profile.

Total project cost for the 3,600 MW KSK Mahanadi power station, along with the integration of the rail and water support infrastructure projects, is estimated at US$ 4.181 billion (at exchange rate of INR 68 / US$). Of this, US$ 2.561 billion has already been incurred with a contribution of US$ 522 million of Sponsor Equity and US$ 2.039 billion of project debt. As regards the balance of US$1.62 billion yet to be incurred:

· Next 1200 MW - an amount of US$ 962 million is expected to be incurred

· Last 1200 MW - an amount of US$ 658 million is to be incurred

The consortium of project lenders have now committed to fund the entire expenditure required for the next 1200 MW and construction progress is being fully accelerated currently in coordination with the EPC Contractor. As regards funding the additional project equity including the last 1200 MW, the Group is also engaged in discussion with multiple strategic investors for appropriate equity participation at the KSK Mahanadi subsidiary level and the Group is committed to raise the necessary incremental equity required at the earliest opportunity. While this would result in the Group diluting its effective equity interest in KSK Mahanadi this would enable a completely funded and secure 3.6 GW power project.

For further information, please contact:

 

KSK Power Ventur plc

Mr. S. Kishore, Executive Director

 

+91 40 2355 9922

 

Arden Partners plc

James Felix/Jonathan Keeling

 

+44 (0)20 7614 5900

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLLFSFELILVIR
Date   Source Headline
24th Feb 20117:00 amRNSChange of Registered Office
15th Feb 20117:00 amRNSInterim Management Statement
14th Feb 20117:00 amRNSIndian Subsidiary Financial Results
26th Jan 20117:54 amRNSAcquisition of shares in Indian Subsidiary
5th Jan 20117:26 amRNSWardha Unit -III
3rd Dec 20101:59 pmRNSHolding(s) in Company
22nd Nov 20107:00 amRNSInterim Results
17th Nov 20101:05 pmRNSNotice of Interim Results
1st Nov 20107:00 amRNSIndian subsidiary financial results
12th Oct 20107:00 amRNSHolding(s) in Company
6th Oct 201012:28 pmRNSHolding(s) in Company
5th Oct 20104:56 pmRNSHolding(s) in Company
5th Oct 20104:52 pmRNSHolding(s) in Company
29th Sep 20104:00 pmRNSResult of AGM
29th Sep 20107:00 amRNS?62.5 million raised through placing of new shares
27th Sep 20109:38 amRNSBusiness Update - Wardha Warora
20th Sep 20107:00 amRNSMahanadi power project business update
27th Aug 20101:10 pmRNSHolding(s) in Company
19th Aug 201012:21 pmRNSAnnual Information Update
16th Aug 20107:00 amRNSInterim Management Statement
9th Aug 20102:08 pmRNSHolding(s) in Company
9th Aug 20107:00 amRNSSubsidiary Quarterly Results
30th Jul 20102:31 pmRNSAnnual Report and Accounts
12th Jul 20107:00 amRNSPreliminary Results
21st Jun 20103:00 pmRNSNotice of Results
8th Jun 20107:00 amRNSSupplementary Development Agreement with Lehman
7th Jun 20108:04 amRNSIndian subsidiary Power Purchase Agreement
1st Jun 20107:00 amRNSIndian Subsidiary Financial Results
17th May 20107:38 amRNSWardha Warora Power Plant - Commencement of Power
31st Mar 20109:36 amRNSCommissioning of VS Lignite Power Plant
31st Mar 20108:07 amRNSFirst Day of Dealings
26th Mar 20102:00 pmRNSPublication of Prospectus
2nd Mar 20107:00 amRNSProposed move to Secondary List of the Main Market
1st Feb 201012:48 pmRNSQuarter 3 Results
4th Jan 20108:56 amRNSResult of AGM
21st Dec 20097:00 amRNSInterim Results
10th Dec 200912:44 pmRNSNotice of AGM
13th Nov 20093:55 pmRNSSubsidiary Closing of QIP
10th Nov 20092:56 pmRNSSubsidiary Opens QIP in India
4th Nov 20094:00 pmRNSNotification of Major Interest in Shares
3rd Nov 20098:55 amRNSReplacement - Quarter 3 Results
30th Oct 20091:38 pmRNSSubsidiary shareholder update
29th Oct 20097:33 amRNSQuarter 3 Results
26th Aug 200910:58 amRNSNon-Executive appointment to the Board
13th Aug 20094:48 pmRNSNotification Of Major Interest In Shares
27th Jul 20093:48 pmRNSIndian Subsidiary Financial Results
15th Jul 20097:59 amRNSPreliminary Results
14th Jul 20097:00 amRNSNotice of Results
15th Jun 20097:00 amRNSNotification Of Major Interest In Shares
12th Jun 200911:16 amRNSNew Corporate Debt facility for Indian Subsidiary

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.