Less Ads, More Data, More Tools Register for FREE

Pin to quick picksKatoro Gold Regulatory News (KAT)

  • There is currently no data for KAT

Imweru Drill Programme Complete

20 Jul 2017 07:00

RNS Number : 5486L
Katoro Gold PLC
20 July 2017
 

Katoro Gold plc (Incorporated in England and Wales)

(Registration Number: 9306219)

Share code on AIM: KAT

ISIN: GB00BSNBL022

("Katoro" or "the Company")

 

 

20 July 2017

 

Imweru Drill Programme Complete: Ahead of Schedule and Below Budget

 

Katoro Gold plc ("Katoro" or the "Company") (AIM: KAT), the Tanzania focused gold exploration and development company, is pleased to announce that the drilling programme for the Imweru resource development programme was completed on 19 July 2017. The expanded drill programme was completed almost a month ahead of the original schedule and well within budget and included 2,000 metres of additional drilling, for a total of 31 drill holes for 3,410 metres (original programme was for 8 to 10 holes for 1,400 metres), that was added after further optimisation of the original programme.

 

The rapid progress and completion of the drill programme will enable the Company to export all geological samples from the drill programme in one batch which will in turn have the added benefit of receiving all the lab results in one report. This will make work on the Pre-Feasibility Study ("PFS") much easier and significantly quicker than planned.

 

Work on the Environmental and Social Impact Assessment ("ESIA") is also progressing well and the ESIA technical team completed their first on-site work session on 18 July 2017.

 

All efforts will now be aimed at getting the geological samples to the laboratory for analysis and to complete the PFS, which will then feed into the Feasibility Study. The Company is currently in the process of exporting the samples to South Africa and after negotiations with the laboratory, they have guaranteed to provide the final results within two weeks from the date of receiving all samples at the laboratory.

 

Louis Coetzee, Executive Chairman of Katoro commented: "Progress on the Imweru resource development programme has been nothing but impressive. Commencing the drill programme ahead of schedule and completing it almost a month ahead on the original schedule, has put the Company in an extremely good position to complete the entire work programme well ahead of schedule but to also deal effectively with the prevailing uncertainty as a result of the changes in mining legislation in as far as process and procedure is concerned. The fact that we were also able to add an additional 2,000 metres to the drill programme, will have a significant impact on the technical quality and integrity of the Feasibility Study."

 

Contacts

Louis Coetzee

+27 (0) 83 2606126

Katoro Gold plc

Executive Chairman

Jon Belliss

+44 (0) 20 7382 8300

Beaufort Securities Limited

Broker

Richard Tulloch

Ritchie Balmer

Frederick Twist

+44 (0) 20 7409 3494

Strand Hanson Limited

Nominated Adviser

Liz Morley

Molly Stewart

+44 (0) 20 3772 2500

Bell Pottinger

Investor and Media Relations

 

Katoro Gold - Notes to editors

 

In May 2017 Katoro acquired the Imweru and Lubando Gold Projects in Tanzania from Kibo Mining plc for a total consideration of £3.66 million and was admitted to trading on AIM.

 

Following the acquisition, Katoro owns 100% of the Imweru and Lubando Projects, which both have Mineral Resources established in accordance with the JORC (2012) Code. The total Mineral Resources stated for Imweru consist of 11.607 Mt at grade of 1.38 g/t for a Mineral Resource of 515,110 oz Au at a resource pay limit of 0.4 g/t for the open pittable material and 1.3 g/t for the underground material, while the Lubando Mineral Resources equate to 6.78 Mt at grade of 1.10 g/t for 239,870 oz Au at a pay limit of 0.4 g/t to a depth of 200 m and 1.3 g/t below the 200 m depth cut-off. The respective projects also include the earlier stage Sheba (within the Imweru Licence Portfolio and Imweru Option Portfolio), Pamba and Busolwa (both within the Lubando Licence Portfolio and Lubando Option Portfolio) projects. The JORC Code compliant Competent Person's Report for each of Imweru and Lubando are available on Katoro's website www.katorogold.com.

 

The Company's primary focus is on advancing and developing Imweru through a work programme which will include, inter alia, a feasibility study and a drilling programme, with the aim, subject to funding, to commence production with an initial target of 50,000 oz gold per annum within 18-24 months from admission to AIM.

 

Updates on the Katoro's activities will be posted on its website www.katorogold.com.

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014 ("MAR").

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLBUGDRBBBBGRC
Date   Source Headline
25th Feb 20207:00 amRNSUpdate re Joint Venture with Blyvoor
14th Feb 202011:15 amRNSExercise of Warrants
14th Feb 20207:00 amRNSUpdate on Tanzanian Assets
11th Feb 202011:05 amRNSSecond Price Monitoring Extn
11th Feb 202011:00 amRNSPrice Monitoring Extension
10th Feb 20202:05 pmRNSSecond Price Monitoring Extn
10th Feb 20202:00 pmRNSPrice Monitoring Extension
10th Feb 202012:30 pmRNSUpdate re Blyvoor JV - Appointment of JV Manager
10th Feb 202011:05 amRNSSecond Price Monitoring Extn
10th Feb 202011:00 amRNSPrice Monitoring Extension
10th Feb 20209:05 amRNSSecond Price Monitoring Extn
10th Feb 20209:00 amRNSPrice Monitoring Extension
4th Feb 202012:50 pmRNSHolding(s) in Company
3rd Feb 202011:15 amRNSUpdate re Joint Venture with Blyvoor
31st Jan 20204:40 pmRNSSecond Price Monitoring Extn
31st Jan 20204:35 pmRNSPrice Monitoring Extension
30th Jan 20202:15 pmRNSStrategic Gold Production Opportunity & Financing
1st Nov 20197:00 amRNSImweru Gold Project Transaction Update
15th Oct 201911:31 amRNSImweru Gold Project Transaction Update
8th Oct 201911:42 amRNSHaneti Nickel Project Update
2nd Oct 20192:49 pmRNSFundraise
30th Sep 20197:00 amRNSImweru Gold Project Transaction Update
13th Sep 20197:00 amRNSInterim Results
22nd Aug 20197:00 amRNSPotential Disposal of Imweru Gold Project
12th Aug 20197:00 amRNSAppointment of Broker
6th Aug 20197:00 amRNSChange of Adviser (broker)
2nd Aug 20194:04 pmRNSHolding(s) in Company
29th Jul 20197:00 amRNSUpdate re Gold Projects
25th Jul 20193:06 pmRNSIssue of Fee Shares and Total Voting Rights
9th Jul 20192:00 pmRNSHaneti Nickel Project Update
26th Jun 20197:00 amRNSHaneti Nickel Project Update
19th Jun 20192:00 pmRNSUpdate re African Battery Metals Agreement
18th Jun 201910:14 amRNSResult of AGM
23rd May 201912:00 pmRNSPosting of Annual Report and Notice of AGM
22nd May 20192:30 pmRNSFinal Results
20th May 201912:35 pmRNSResults of Haneti Sampling Programme
15th May 20193:15 pmRNSUpdate re African Battery Metals Agreement
15th May 20192:30 pmRNSUpdate re Agreement with African Battery Metals
15th Mar 20194:41 pmRNSSecond Price Monitoring Extn
15th Mar 20194:35 pmRNSPrice Monitoring Extension
15th Mar 201910:00 amRNSInvestment and Option Agreement with Katoro Gold
15th Mar 201910:00 amRNSInvestment and Option Agreement
15th Feb 20198:00 amRNSHolding(s) in Company
11th Feb 201911:53 amRNSUpdate to Admission to Trading Date of Fee Shares
8th Feb 20197:00 amRNSCorporate Update
30th Jan 20197:00 amRNSHaneti Nickel Project Update
16th Jan 20199:01 amRNSNew Corporate Website
26th Nov 20182:35 pmRNSAcquisition of High-Grade Nickel Sulphide Project
11th Sep 20181:09 pmRNSUnaudited Interim Results
25th Jul 20188:33 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.