Final Agreement for Surface platinum project

15 Dec 2015 10:30

RNS Number : 1010J
Jubilee Platinum PLC
15 December 2015
 

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

15 December 2015

Jubilee Platinum PLC

("Jubilee" or the "Company")

 

Jubilee executes Final Agreement to process the Hernic surface platinum-bearing chrome tailings

 

Jubilee, the Mine-to-Metals company, is pleased to announce the execution, on 15 December 2015, of a Co-Operation Agreement (the "Final Agreement") with Hernic Ferrochrome Proprietary Limited ("Hernic") on the turning to account ("Processing") of the platinum containing surface chrome tailings ("Hernic Surface Material") currently stockpiled and generated by Hernic, to produce Chromite and Platinum Group Metals ("PGM") concentrate (the "Project").

Highlights

· Jubilee and Hernic conclude Final Agreement for the execution of the Project

· Jubilee's pre-work programme facilitates a fast track programme for early construction and commissioning

· The combined platinum surface projects ("Platinum Projects") targeting an annualised processing capacity in excess of 900 000 tons

· The Platinum Projects enter construction with ASA Metals chrome plant on-line for commissioning February 2016

· Finance offers for the Platinum Projects under agreement

· Company continues in discussions with the acquisition of similar projects and other opportunities currently being presented in the platinum arena

 

Leon Coetzer says:"I am delighted that we have concluded this final agreement and we are honoured to be appointed as exclusive partner in what will be the largest PGM beneficiation plant of surface chrome tailings in South Africa.

"The Jubilee team is looking forward to moving from design into implementation."

 

The Agreement replaces the heads of agreement, as announced on 19 January 2015, in terms of which the Company was selected as the exclusive party to beneficiate the chromite and PGMs contained in the Hernic Surface Material. Hernic is the world's 4th largest integrated ferrochrome producer with an estimated 3 million tons of platinum containing material at surface while Hernic continues to add further material to the surface stock. The Project is the second of the Company's Platinum Projects, the first of which is to be commissioned in early Q1 2016. The Company has targeted a combined processing of platinum containing surface material over the two projects in excess of 900 000 tons per annum.

The Agreement appoints Jubilee as the exclusive party to beneficiate the chromite and PGMs contained in the Hernic Surface Material and addresses the Project execution methodology as well as the operational and financial performance targets. The Hernic Surface Material has been independently fully drilled and assayed for chrome and PGM content. This has resulted in an independent resource statement of 1.7 million tons, of which approximately 90% of the resource is classified in the measured category under the internationally recognised SAMREC code. Hernic also has access to secondary surface stocks, which it has internally identified and could increase the surface stocks to in excess of 3million tons through further drilling programs. The total Project is estimated to contain PGM ounces in excess of 224 000 (3PGM + Au) oz.

The Project will be the largest PGM beneficiation plant of surface chrome tailings in South Africa capable of producing annual revenues of GBP18.2 million (ZAR400 million) at an average metal basket price of USD906 per (3PGM + Au) oz. The financial and operational risks of the Project are significantly mitigated since the material is already at surface and requires neither the cost nor the risk associated with mining. An extensive prefeasibility study has been concluded on the Project, which included both pilot scale and full commercial scale trials to confirm the design and operational parameters.

The Project is to be undertaken in four phases over an 11 month period; namely

· Phase one - Bankable Feasibility Study and Engineering Design. Completed a;

· Phase two - Construction of the chrome and platinum processing plant ("Processing Plant").

· Phase three - Commissioning and Ramp up of Processing Plant to design capacity of 55 000 tons per month 

· Phase Four - Stable operation of the Processing Plant.

 a Announced 11 February 2015.

As previously announced, the Company has received funding terms from a major financial institution which has received credit approval for the debt element of the project financing required to bring its Platinum Projects into operation. The size of the ZAR based debt funding for both surface projects equates to GBP11.5 million (ZAR255 million) before financing costs. The working capital required to bring the Platinum Surface Projects into operation and to achieve positive earnings is estimated at GBP3.4 million (ZAR75 million).

 

 

 

 

Contacts

Jubilee Platinum plc

Colin Bird/Leon Coetzer Tel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913 Andrew SarosiTel +44 (0) 1752 221937

 

Nominated Adviser

SPARK Advisory Partners LimitedSean Wyndham-Quin / Mark BradyTel: +44 (0)203 368 3555

 

Brokers

Beaufort Securities LimitedElliot Hance/Jon BellisTel +44 (0) 20 7382 8416

 

JSE Sponsor

Sasfin Capital, a division of Sasfin Bank Limited Sharon OwensTel +27 (0) 11 809 7500

 

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
AGRLLFFIFTLELIE
Date   Source Headline
5th Nov 20208:00 amRNSExecution of further copper tailings transactions
12th Oct 20207:00 amRNSQuarterly Operations Update Q3 2020
14th Sep 202012:30 pmRNSKabwe Mining Licence Renewed & Board Appointment
24th Aug 20207:00 amRNSNew Processing Agreement: Ore Beneficiation Plant
13th Aug 20207:00 amRNSChrome Operations Update
6th Aug 20207:00 amRNSFurther Copper Tailings Resource Secured in Zambia
13th Jul 20207:00 amRNSSix Month Operations Update
18th Jun 20207:00 amRNSLarge Copper Tailings Resources in Zambia Secured
19th May 202011:30 amRNSRelocation of chrome plant to maximise earnings
7th May 20202:00 pmRNSOperations Update in South Africa and Zambia
17th Apr 20209:15 amRNSUpdate: Operations during lockdown in South Africa
26th Mar 202010:10 amRNSUnaudited interim results
24th Mar 202011:33 amRNSSOUTH AFRICAN 21-DAY LOCKDOWN UPDATE
23rd Mar 20204:41 pmRNSSecond Price Monitoring Extn
23rd Mar 20204:37 pmRNSPrice Monitoring Extension
20th Mar 20204:47 pmRNSSecond Price Monitoring Extn
20th Mar 20204:42 pmRNSPrice Monitoring Extension
20th Mar 20202:05 pmRNSSecond Price Monitoring Extn
20th Mar 20202:00 pmRNSPrice Monitoring Extension
16th Mar 20204:42 pmRNSSecond Price Monitoring Extn
16th Mar 20204:37 pmRNSPrice Monitoring Extension
21st Feb 202010:10 amRNSDirector Dealing
28th Jan 20208:15 amRNSSix Monthly Operations Update
6th Dec 201912:45 pmRNSResults of AGM
3rd Dec 20197:00 amRNSDirector Dealing
25th Nov 20192:24 pmRNSTR-1: notification of major holdings
14th Nov 20191:15 pmRNSEquity Placing to Support Targeted Growth
14th Nov 20197:36 amRNSResults for year ended 30 June 2019 & AGM Notice
5th Nov 20198:30 amRNSAcquisition of all chrome rights at Hernic
24th Oct 20193:11 pmRNSAcquisition at Hernic: Transforming Operations
24th Sep 20197:00 amRNSNew Corporate Presentation
17th Sep 20197:00 amRNSKabwe Multi-Metal Processing Project Update
5th Sep 20198:00 amRNSWindsor PGM Project - Full Operational Status
23rd Aug 201910:15 amRNSCompletion of Acquisition in Kabwe & Joint Broker
5th Aug 20199:00 amRNSSix Monthly Operations Update
11th Jul 20197:00 amRNSProjects Update
5th Jun 20191:45 pmRNSProjects Update
9th May 20197:00 amRNSQuarterly Operations Update Q1 2019
3rd May 201912:30 pmRNSTR-1: notification of major holdings
23rd Apr 20197:00 amRNSPrice Monitoring Extension
5th Apr 20192:05 pmRNSSecond Price Monitoring Extn
5th Apr 20192:00 pmRNSPrice Monitoring Extension
4th Apr 20194:41 pmRNSTR-1: notification of major holdings
3rd Apr 20192:26 pmRNSTR-1 NOTIFICATION OF CHANGE IN MAJOR HOLDINGS
2nd Apr 20194:40 pmRNSSecond Price Monitoring Extn
2nd Apr 20194:35 pmRNSPrice Monitoring Extension
29th Mar 20191:35 pmRNSVoting Rights and Capital
29th Mar 201910:38 amRNSTR-1: Form for notification of major holdings
28th Mar 20197:00 amRNSUnaudited interim results
21st Mar 201910:58 amRNSFunding secured for Kabwe Project and Acquisition

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.