Pipeline Integrity Confirmation & Project Update

25 Sep 2018 07:00

RNS Number : 7709B
Independent Oil & Gas PLC
25 September 2018
 

25 September 2018

 

Independent Oil and Gas plc

 

Pipeline Integrity Confirmation & Project Update

Independent Oil and Gas plc ("IOG" or the "Company"), the development and production focused Oil and Gas Company, is pleased to provide conclusive confirmation of the integrity of the Thames Pipeline and a progress update on its Southern North Sea (SNS) gas project.

Highlights:

· A 150-bar pressure hydrotest has fully confirmed the Thames Pipeline's integrity at pressure well above that required to deliver IOG's gas safely to Bacton terminal. This is a major step towards FDP approval.

· The Thames Pipeline is now conclusively proven for a new economic life over the next two decades as a fully viable, minimal cost, zero tariff export route delivering a maximum annual capacity of 200 BCF directly into the UK market.

· A tethered pig inspection run from the terminal into the line's final section also delivered excellent results, with no internal corrosion nor external defects found.

· These operations demonstrate pipeline capacity of up to 550 MMcfd, creating substantial tariff-free ullage for IOG's existing gas portfolio and future acquisitions, plus third-party gas tariff opportunities. The Company's current SNS development projects will use around half of this available capacity at peak.

· The Company has made significant further technical and financial progress on the SNS gas development project and is now in the final preparatory stages for FID. Front End Engineering and Design ("FEED") studies and bidding processes are substantially complete and contract negotiations with preferred parties well advanced.

· FID is expected during Q4 2018 and funding plans are being finalised accordingly. Construction of key project infrastructure is expected to follow during 2019 with installation scheduled for Q1-2 2020 and first gas in late Q2 2020.

 

Andrew Hockey, CEO of IOG commented:

 

"I am delighted to announce that the internal inspection and high-pressure hydrotest have indisputably confirmed the viability of our pipeline as a very low-cost export route for all of our own substantial gas portfolio, plus a potential extra revenue stream through third party tariffing. Full ownership of this export pipeline with very substantial capacity of 550 MMcfd - acquired for a nominal sum - gives us real competitive advantage to capture consolidation opportunities in the Southern North Sea.

"The recommissioning of the Thames Pipeline will breathe new economic life into a part of the North Sea formerly considered to be in terminal decline and help to maximise economic recovery for the UK. The new gas developments enabled by the re-use of this pipeline will make a significant contribution to providing domestic energy resources to UK homes and industry over the next two decades and provide extended employment opportunities in the region.

"This is an especially exciting time for the Company as we progress ever closer to a transformational FID and also prepare to drill a fully funded appraisal well at Harvey in the coming months which could dramatically increase our proven reserves and company valuation."

 

Pipeline Integrity Confirmation

After detailed consultations with regulatory authorities on the necessary steps to re-commission the Thames Pipeline, on 6 September 2018 IOG ran an internal crawler-based measurement device from the Bacton terminal to 800m offshore to assess the line's internal and external condition. This section was at a higher risk of degradation since decommissioning in 2015. The inspection tool was successfully run and resulting data analysis showed no internal corrosion nor external defects, confirming the excellent condition of that section of the line and removing the potential need for refurbishment work.

This result in turn enabled the Company to determine the safe maximum test pressure (as required under the Pipeline Code) for a 24-hour hydrotest to be 150-bar. The hydrotest was successfully completed on 21-23 September 2018. As the maximum operating pressure required under IOG's Field Development Plan (FDP) is approximately 80-bar, the 150-bar test level translates to a maximum allowable operating pressure of 100-bar, establishing a very substantial capacity margin. This level represents a maximum capacity of approximately 550MMcfd, comfortably encompassing all planned production from IOG's 632 BCF portfolio (303 BCF 2P reserves and 329 BCF mid-case resources) portfolio while leaving extensive tariff-free ullage for any further fields acquired in the future or tariff-paying third-party gas.

Project Update

Alongside the pipeline integrity operations, the Company has been progressing numerous other critical workstreams to reach the required level of project definition for Phase 1 FID. Front End Engineering and Design (FEED) studies have been completed for all key areas, including refurbishment of the Thames Reception facilities at the Bacton terminal. The selection process for major project contracts is concluding, with commercial details agreed and contracts now under negotiation.

In that context, the Company expects to proceed to FID and obtain FDP approval during Q4 2018 and has been finalising funding plans accordingly. The project schedule has been revised to reflect the optimal timing for both fabrication and installation of key infrastructure, including unmanned platforms, connecting pipelines and associated subsea equipment. Safety is paramount in all IOG's operations and as such the delivery of Phase 1 offshore installation is scheduled to commence immediately after the 2019-20 winter season, rather than in Q4 2019, leading to an expected first gas date towards the end of Q2 2020.

-ENDS-

 

Certain information communicated in this announcement was, prior to its publication, inside information for the purposes of Article 7 of Regulation 596/2014.

 

 

 

Enquiries:

Independent Oil and Gas plc

Andrew Hockey (CEO)

James Chance (CFO)

Mark Hughes (COO)

+44 (0) 20 3879 0510

finnCap Ltd

Christopher Raggett

Anthony Adams

(Corporate Finance)

Camille Gochez

(Corporate Broking)

+44 (0) 20 7220 0500

Peel Hunt LLP

Richard Crichton

David McKeown

+44 (0) 20 7418 8900

Camarco

Georgia Edmonds

Tom Huddart

Monique Perks

+44 (0) 20 3757 4980

Notes

About Independent Oil and Gas:

IOG owns substantial low risk, high value gas Reserves in the UK Southern North Sea. The Company is targeting a 2P peak production rate in excess of 200 MMcfd (c. 35,000 Boe/d) from its substantial current portfolio (2P Reserves of 303 BCF) via an efficient hub strategy. Alongside this it continues to pursue value accretive acquisitions, to generate significant shareholder returns. All IOG's licences are owned 100% and operated by IOG.

Further information can be found on www.independentoilandgas.com

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDEAKNLAANPEFF
Date   Source Headline
27th Jun 20177:00 amRNSOGA SNS Tight Gas Strategy and New Presentation
8th Jun 20177:00 amRNSNotice of AGM and Issue of New Shares
31st May 20177:00 amRNSIssue of New Shares
26th May 20177:00 amRNSFinal Results for the Year Ended 31 December 2016
11th Apr 20177:00 amRNSAcquisition of SNS Pipeline
31st Mar 20177:00 amRNSExtension of pipeline MOU
27th Mar 20177:00 amRNSHarvey and Elgood licence Updates
21st Mar 20179:00 amRNSConversion of Salaries & Fees into Share Options
21st Mar 20177:00 amRNSDirectorate Change
1st Mar 201710:55 amRNSAcquisition of SNS Pipeline Update
1st Mar 20178:59 amRNSDirectorate Change
23rd Jan 201712:31 pmRNSConversion of Salaries and Fees into Share Options
16th Jan 20177:00 amRNSAcquisition of SNS Pipeline and Skipper Update
20th Dec 20167:00 amRNSIssue of New Shares
16th Dec 20167:00 amRNSSouthern North Sea Resources Increase
8th Dec 20167:00 amRNSExtension of the Blythe Licence
3rd Nov 20167:00 amRNSIssue of New Shares
1st Nov 20167:00 amRNSInitial Results of Seismic and Update on Cronx
28th Oct 20167:00 amRNSCompletion of Vulcan Satellites Acquisition
3rd Oct 20162:05 pmRNSSecond Price Monitoring Extn
3rd Oct 20162:00 pmRNSPrice Monitoring Extension
30th Sep 20167:00 amRNSInterim Results 2016
30th Sep 20167:00 amRNSInitial Skipper Appraisal Well Results
31st Aug 20167:00 amRNSResignation of Director
19th Aug 20167:00 amRNSCompletion of the Skipper Appraisal Well
17th Aug 20167:00 amRNSSkipper Well Update
29th Jul 20167:00 amRNSDirectorate Change
20th Jul 20162:00 pmRNSSkipper Update
14th Jul 20167:00 amRNSSkipper Update and Issue of New Shares
30th Jun 20167:00 amRNSResult of AGM and Skipper Appraisal Well Update
21st Jun 20167:00 amRNSCompletion of Blythe Acquisition
14th Jun 201610:44 amRNSIssue of New Shares
13th Jun 20167:00 amRNSAcquisition of Vulcan Satellites fields
7th Jun 20167:00 amRNSSkipper Appraisal Well rescheduled for July 2016
27th May 20167:00 amRNSAudited Results for the Year Ended 31 December 15
22nd Apr 20167:00 amRNSHolding(s) in Company
19th Apr 20168:00 amRNSConversion of Salaries and Fees into Share Options
19th Apr 20167:00 amRNSAcquisition of Blythe Discovery
30th Mar 20161:15 pmRNSPotential Acquisition Update
30th Mar 20167:00 amRNSFunding and Strategic Update
7th Mar 20169:23 amRNSIssue of New Shares
22nd Feb 201610:44 amRNSResult of General Meeting
5th Feb 201611:16 amRNSLoan Facility, Corporate Update and Board Changes
28th Jan 20167:00 amRNSExtension of Skipper Licence
18th Jan 20164:35 pmRNSPrice Monitoring Extension
13th Jan 20164:40 pmRNSSecond Price Monitoring Extn
13th Jan 20164:35 pmRNSPrice Monitoring Extension
13th Jan 20167:00 amRNSRescheduling of Skipper Well & Additional Funding
31st Dec 20157:00 amRNSCronx Licence Extension
29th Dec 20156:00 pmRNSResult of GM and Skipper Licence Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.