Dugbe Gold Project Update

8 Feb 2022 07:00

RNS Number : 9525A
Hummingbird Resources PLC
08 February 2022
 

08 February 2022

Hummingbird Resources plc

("Hummingbird" or the "Company")

Dugbe Gold Project Update

Feasibility Study Scheduled for Completion in April

Hummingbird Resources plc (AIM: HUM) is pleased to announce Pasofino Gold Ltd ("Pasofino") (TSXV: VEIN) has released an update for the Dugbe Gold Project ("Dugbe" or "The Project").

For the full Pasofino release, please follow the link here.

Highlights

· Pasofino notes the Dugbe Feasibility Study ("FS") is scheduled for completion in April 2022

· Confidence achieved with the FS confirming gold recoveries of between 85% and 91%, depending on whether a straight carbon-in-leach ("CIL") or CIL with flotation circuit is selected respectively. Current trade-offs are aimed at the selection of the optimal process to achieve the best financial outcomes

· Open pittable resources include 57-million-tonne ("Mt") material, grading 1.58 grams a tonne ("g/t") with 2.88 million ounces ("Moz") gold. Pasofino intends to prioritise the extraction of this higher-grade component of the overall Resource (75Mt at 1.37g/t in Measured and Indicated) in order to support a higher head grade during early years of production

· Favorable results from the on-site geotechnical work should allow steeper pit slopes to be developed, which should translate to lower strip ratios

· Mining dilution has decreased to an average of 8.7% from 10% in the 2021 Preliminary Economic Assessment ("PEA")

· Reduced energy costs from US$0.212 per kWh to US$0.172 per kWh. This anticipated benefit is expected to result in lower energy cost/tonne treated

· All other disciplines are well advanced with the FS over 70% complete

· Environmental and Social Impact Assessment ("ESIA") scope approved by the Liberian Environmental Protection Agency ("EPA"). Exhaustive biodiversity fieldwork has identified areas of lower sensitivity enabling the location of key project infrastructure, reducing environmental impact. Continuous community engagement has been undertaken throughout the development of the project

· Updated results show continual strong progress towards delivering an economically robust FS, as highlighted by the PEA as released on 24 June 2021 as detailed in this link here 

Hummingbird notes that post completion of the FS in April 2022 and, subject to satisfying certain conditions in the Earn-in Agreement, Pasofino is on track to earn in its 49% interest in the Project (prior to the issuance of the Government of Liberia's 10% carried interest). Further, the Company notes that Pasofino has indicated that once the 49% earn-in is completed, it intends to exercise its right under the Earn-in Agreement to acquire 100% ownership of the Project by exchanging Hummingbird's 51% controlling interest in the Project for a 51% controlling interest in Pasofino. This exchange is subject to certain conditions and receipt of all required approvals, including the approval from the TSX Venture Exchange.

Dan Betts, CEO of Hummingbird Resources, commented:

"Yesterday's news from Pasofino that the Dugbe FS is moving rapidly towards completion in April is very encouraging. We look forward to reviewing what promises to be very strong project economics as highlighted by today's update and those as highlighted in the PEA release in June 2021.

The completion of the FS will mark a major milestone for Dugbe and complete its journey from being a pure exploration asset to a viable project, with strong project economic fundamentals. We will provide more details post receiving and analysing the FS from Pasofino in April."

Qualified Persons Statement

Content in this disclosure that relates to the FS was reviewed on behalf of Hummingbird by Dr. Daniel Limpitlaw Pr. Eng, FSAIMM. Dr Limpitlaw is a full-time consultant at Pasofino Gold Ltd.'s wholly-owned subsidiary ARX Resources Limited. By virtue of his education, professional registration and experience, Dr. Limpitlaw is a Qualified Person for the purpose of NI 43-101.

Notes to Editors:

Hummingbird Resources (AIM: HUM) is a multi-asset, multi-jurisdiction gold production, development and exploration Company, a member of the World Gold Council and a founding member of Single Mine Origin ( singlemineorigin.com ). The Company currently has two core gold projects, the operational Yanfolila Gold Mine in Mali, and the Kouroussa Gold Mine in Guinea, which will more than double current gold production when in production, scheduled for first gold pour end of Q2 2023. Further, the Company has a controlling interest in the Dugbe Gold Project in Liberia that is being developed by Pasofino Gold Limited through an earn-in agreement. Our vision is to continue to grow our asset base, producing profitable ounces while placing our Environmental, Social & Governance ('ESG') policies and practices at the heart of all we do.

For further information, please visit   hummingbirdresources.co.uk   or subscribe to our investor releases via  investor email alerts  

Daniel Betts, CEO

Thomas Hill, FD

Anthony Köcken, COO

Edward Montgomery, CSO & ESG

Hummingbird Resources plc

Tel: +44 (0) 20 7409 6660

James Spinney

Ritchie Balmer

Strand Hanson Limited

Nominated Adviser

Tel: +44 (0) 20 7409 3494

James Asensio

Thomas Diehl

Canaccord Genuity Limited

Broker

Tel: +44 (0) 20 7523 8000

Bobby Morse

Ariadna Peretz

James Husband

Buchanan

Financial PR/IR

Tel: +44 (0) 20 7466 5000

Email:  HUM@buchanan.uk.com

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDUBOARURUURUR
Date   Source Headline
20th Aug 20217:00 amRNSInterim Results
5th Aug 20217:00 amRNSKomana East Underground drilling results
20th Jul 20217:00 amRNSQ2 2021 Operational and Trading Update
15th Jul 20213:36 pmRNSTR-1: notification of major holdings
15th Jul 20213:13 pmRNSTR-1: notification of major holdings
7th Jul 20217:00 amRNSSanioumale East drilling results and TVR
24th Jun 20213:50 pmRNSPasofino Gold releases updated PEA for Dugbe
21st Jun 20214:49 pmRNSResult of Annual General Meeting
15th Jun 20213:12 pmRNSHolding(s) in Company
15th Jun 20213:05 pmRNSUpdate on Dugbe Gold Project, Liberia
27th May 20217:00 amRNS2020 Audited Annual Results
25th May 20217:00 amRNSUpdate to Admission of Trading
20th May 20212:36 pmRNSMining Licences granted for Kouroussa Gold Project
18th May 20212:30 pmRNSUpdate on Dugbe Gold Project
11th May 20219:35 amRNSTR-1: Notification of major holdings
21st Apr 20217:00 amRNSQ1 2021 Production Results and Operational Update
6th Apr 20213:54 pmRNSTR-1: Notification of major holdings
1st Apr 20217:00 amRNSSignificant Drill Results Continue at Yanfolila
30th Mar 20217:00 amRNSMineral Resources Estimate Update at Yanfolila
12th Mar 20217:36 amRNSDrilling Update on the Dugbe Gold Project, Liberia
11th Mar 202111:42 amRNSBlock Listing Six Monthly Return
3rd Feb 20217:00 amRNSQ4 2020 production and 2021 outlook
8th Jan 20212:03 pmRNSTR-1: notification of major holdings
23rd Dec 20208:00 amRNSYanfolila exploration and drilling update
17th Dec 20204:53 pmRNSTR-1: Notification of major holdings
2nd Dec 20207:00 amRNSOperational update
11th Nov 20207:00 amRNSUpdate on the Dugbe Gold Project
26th Oct 20207:00 amRNSQ3 2020 Corporate and Operational Update
8th Oct 20207:00 amRNSYanfolila 2020 Drilling Programme Update
24th Sep 20203:16 pmRNSExercise of Options and Total Voting Rights
23rd Sep 20207:00 amRNSDugbe Gold Project Financing
15th Sep 202010:01 amRNSTR-1: Notification of major holdings
11th Sep 20205:06 pmRNSBlock Listing Six Monthly Return
11th Sep 20201:34 pmRNSTR-1: notification of major holdings
8th Sep 20204:48 pmRNSExercise of Options and Total Voting Rights
1st Sep 20207:00 amRNSCompletion of the acquisition of Kouroussa Project
26th Aug 20207:00 amRNSInterim Results
19th Aug 20204:38 pmRNSExercise of Options and Total Voting Rights
19th Aug 20208:08 amRNSStatement on Situation in Mali
18th Aug 20202:06 pmRNSSecond Price Monitoring Extn
18th Aug 20202:01 pmRNSPrice Monitoring Extension
14th Aug 20203:02 pmRNSTR-1: Notification of major holdings
10th Aug 20201:47 pmRNSExercise of Options and Total Voting Rights
5th Aug 20208:00 amRNSQ2 2020 Production Results and Operational Update
14th Jul 202011:44 amRNSExercise of Options and Total Voting Rights
10th Jul 202010:25 amRNSTR-1: Notification of major holdings
8th Jul 202011:59 amRNSTR-1: Notification of major holdings
8th Jul 20207:00 amRNSExercise of Options and Total Voting Rights
6th Jul 202011:26 amRNSTR-1: Notification of major holdings
6th Jul 202011:25 amRNSTR-1: Notification of major holdings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.