Trading Statement

26 Jan 2011 07:00

RNS Number : 0698A
Highland Gold Mining Limited
26 January 2011
 





 

HIGHLAND GOLD MINING LIMITED

TRADING UPDATE FOR THE SECOND HALF OF 2010

 

26 January 2011 - Highland Gold Mining Limited ("Highland Gold", or the "Company") is pleased to announce its trading update for the half year ended 31 December 2010. 

 

HIGHLIGHTS

 

·; The Company met its 2010 production guidance by producing 200,028 oz of gold and gold equivalents from Mnogovershinnoye ("MNV"), Novoshirokinskoye ("Novo") (48.3%) and its newly commissioned third mine, Belaya Gora, a 23% increase year-on-year

·; At Unkurtash initial C1+C2 reserves estimate (1.70 Moz) submitted to Kyrgyzstan GKZ for approval, with JORC compliant audit results expected during H1 2011

·; JORC compliant audit confirms original Belaya Gora GKZ reserve (0.82 Moz)

·; Novo continues to ramp up mining and processing levels

·; 12,000 metres of resource conversion drilling completed at Lyubov

·; Group currently is debt free after fast tracking loan repayments, with a cash and cash equivalent position of US$ 235 million at 31 December 2010

·; Production in 2011 (MNV, Novo and Belaya Gora) is forecast in the range of 210,000 - 220,000 oz of gold and gold equivalents

 

OPERATIONS

 

Mnogovershinnoye (MNV) - Khabarovsk region, Russia

 

At the MNV mine, actual production exceeded targeted production during the second half of 2010 as process plant throughput increased substantially to 622,604 tonnes of ore processed and 94,585 oz of gold produced. Process plant recoveries remained in-line with those of the first half. Process grinding and gravity upgrades are underway and expected to improve recoveries going forward. Mined ore tonnes and grades remained consistent from both open pit and underground sources. New capital equipment introduced during the first half has improved productivity levels while helping to control operating costs.

 

 MNV

H2 2010

H2 2009

2010

2009

Mine development

Stripping

1,220,558

900,568

1,933,948

2,238,637

Underground development

metres

3,098

4,396

6,725

8,635

Mining

Total ore mined

tonnes

642,878

544,435

1,192,896

1,009,384

 Average grade

g/t

5.1

5.2

5.1

5.4

Ore processing

Ore processed

tonnes

622,604

541,278

1,144,459

1,081,605

Average grade

 g/t

5.4

5.2

5.3

5.2

Recovery rate

%

87.4

88.4

87.6

88.3

Gold produced

oz

94,585

84,787

170,356

163,208

 

Novoshirokinskoye - Zabaikalsky region, Russia

 

Since shipping initial concentrates in February 2010 production has continued to be ramped up as planned. Productivity improvements were seen in both mining and process operations with 397,075 tonnes of ore processed during the year. Second half underground ore production and waste development metres remained on target while processed throughput exceeded target.

 

Novoshirokinskoye 100%

H2 2010

H1 2010

Mine development

Underground development

Metres

3,221

3,143

Mining

Ore mined

Tonnes

223,989

121,748

 Average grade *

g/t

6.48

6.12

Processing

Ore processed

Tonnes

233,752

163,323

Average grade *

g/t

6.34

5.38

Recovery rate *

%

81.0%

78.0%

Gold Produced *

HGML (48.3%) interest

oz

oz

38,662

18,654

20,741

10,018

*calculated Au equivalent

 

Belaya Gora - Khabarovsk region, Russia

 

The review of synergies between Belaya Gora and nearby MNV resulted in the mobilisation of equipment and personnel for the commencement of select mining oxide ores for delivery to the MNV processing plant early in H2 2010. The actual start of mining was delayed until November due to permit requirements. In total, 10,971 tonnes of ore from Belaya Gora were milled, yielding 1,000 oz of gold with a considerable stockpile of ore accumulated. Mining operations now continue on target with expected production of approximately 1,000 oz of gold per month throughout 2011. In addition, the construction of a stand-alone processing facility with an anticipated commissioning date of mid-2012 has been initiated.

 

Belaya Gora

Nov & Dec 2010

Mining

Waste Stripping

226,000

Ore mined

tonnes

76,000

Average grade

g/t

1.66

Select Ore to MNV

tonnes

26,700

Average grade

g/t

2.41

Processing at MNV

Ore processed

tonnes

10,971

Average grade

g/t

3.25

Recovery rate

%

87.3

Gold Produced

oz

1,000

 

DEVELOPMENT PROJECTS

Taseevskoye - Zabaikalsky region, Russia

 

The Company is currently conducting semi-industrial pilot testing concentrating on pressure oxidation (POX) specific processing technology. The aim of this testing is to develop all the design documentation and produce a comprehensive production flow sheet, with a full feasibility study to be produced by the year ending 2011. In the coming year, reviews will be undertaken on the ZIF-1 and Sredne-Golgotayskoye deposits, in an effort to calculate the net benefits of introducing these two additional resources into the current economic model.

 

EXPLORATION

 

Mnogovershinnoye (MNV) - Khabarovsk region, Russia

 

At MNV, encouraging drilling results have been achieved from the near-mine exploration programme intended to discover additional reserves for open-pit exploitation over the short term. The focus in 2010 was on surface exploration which included more than 6,200 metres of drilling at 4 exploration targets within the MNV license area. As a result, pit optimisation is now underway for the Pebble (Valunistoye) prospect which is part of Quiet (Tikhoye) - Pebble zone is estimated to host 190,000 oz of gold contained in open-pit mineable ore grading between 3.0 - 5.0 g/t. Positive drilling results obtained from other targets warrant follow-up work and highlight the considerable exploration potential that still remains at MNV.

 

During 2011 the near-mine exploration budget anticipates 8,000 metres of surface drilling with an additional 16,000 metres allocated to underground exploration.

 

Unkurtash - Kyrgyzstan

 

At Unkurtash, a pre-feasibility study for registration of preliminary C1+C2 category reserves of 1.71 million oz has been submitted to the State Committee on Reserves of the Kyrgyz Republic (GKZ) and represents a major step towards future mine development. The audit, in compliance with JORC standards, is planned to be completed by mid-2011.

 

Exploration activities continue at the three adjoining prospects - Unkurtash, Sarytube and Karatube. Over 13,000 metres of reverse circulation (RC) and core drilling has been completed in addition to underground exploration at Unkurtash where 430 metres of old workings were rehabilitated and 142 new metres developed. Drilling results continue to support the potential for hosting a large open-pit mineable stockwork-type resource at Unkurtash in addition to a smaller satellite deposit at Karatube.

 

A substantial increase in budgeted annual exploration expenditure underpins the Company's confidence in realising the potential of this project. Over 30,000 metres of RC and core drilling has been allocated at the three targets in addition to 3,000 metres of underground exploration development planned at Unkurtash during 2011.

 

Lyubov - Zabaikalsky region, Russia

 

At Lyubov, 12,000 metres of resource definition drilling has been completed at the Evgraf granitic stock and its surrounding shale with the objective of increasing the C1+C2 category reserves potential through conversion of adjacent prognostic P1 resources.

 

As previously reported to the regulatory authorities, the Evgraf target (exclusive of Evgraf West) was estimated to contain C2+P1 resources of 43.3 tonnes of gold (1.67 million oz) at an average grade of 1.83 g/t and a cut-off grade of 0.75 g/t (unaudited in-house estimate). To date 95% of drilling results have been received and are in-line with the Company's own resource model. Final assays with evaluation of results are expected to be completed by Q1 2011.

 

During 2011 the Company plans to complete additional drilling and other work, which will fulfill critical requirements for a pre-feasibility study. Together with a reserve calculation, it is planned to be submitted for approval to the State Committee on Reserves of the Russian Federation (GKZ) in H2 2011. A JORC compliant resource audit is expected prior to the year end 2011.

 

Blagodatnoye - Khabarovsk region, Russia

 

At Blagodatnoye, a resampling programme of old trench workings was completed in H2 2010. Overall this has returned positive results, which define several continuous intercepts of gold mineralisation. Blagodatnoye has a reported prognostic resource estimate of 161,000 oz of gold and features stockwork-type gold mineralisation with reported average gold grades in the range of 1.5-2.0 g/t.

 

The exploration programme planned for 2011 aims to increase the reported resource substantially and includes 10,000 metres of drilling to confirm continuity of mineralisation at depth.

 

Qualified Persons Statement: Mr. Werner Klemens, Head of Exploration at Highland Gold has reviewed and verified the information contained in this release with respect to drilling and resource / reserves matters. Mr. Klemens holds a Ph.D. in Geology from the University of Toronto. He has 13 years experience in mineral exploration and is a fellow of the Geological Association of Canada. A rigorous quality assurance programme complying with international standards is in effect at all exploration projects and includes duplicate sampling, insertion of standards and check assaying with external laboratories.

 

HEALTH, SAFETY & ENVIRONMENT

 

The provision of a safe working environment, management of production risks, training of personnel and improvement of personal responsibility for site safety, remains of paramount importance to the Company. As a result of this work the lost time incident ("LTI") rate (the LTI rate is the number of lost time incidents for every 200,000 man hours worked) decreased to 0.37 during 2010 (0.55 in 2009). During the year all sites worked 6 specific months with zero LTI incidents reported. 1,258 employees went through introductory (1 day) safety training, 477 employees went through a course of introductory hazardous work (5 days) safety training and 111 employees were involved in industrial safety certification and training courses.

 

Environmental compliance remained in good standing with regulatory authorities. In particular, environmental audit procedures for all sites of the Company were implemented during the year. Environmental safety requirement training was provided to 68 employees at MNV and Taseevskoye, while an additional 24 MNV employees were provided with environmental risks and assessments training and 42 employees passed their best practices of environmental protection training.

 

The Company has also initiated efforts towards implementation of an accredited environmental management system (ISO 14001 compliant) Group wide with final compliance auditing targeted by YE 2012.

For further information please contact:

Highland Gold

Dmitry Yakushkin, Head of Communications + 7 495 424 95 21

Duncan Baxter, Chairman + 44 (0) 1534 814 202

Matrix

Robin Henshall, +44 (0) 20 3206 7172

(Nominated Adviser and broker)

Tim Graham, +44 (0)20 3206 7206

Fin Public Relations

Alex Glover + 44 (0) 20 7608 2280

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTZMGZMVKRGMZM
Date   Source Headline
24th May 20182:28 pmRNSResult of Annual General Meeting
4th May 20187:00 amRNSMailing of 2017 Annual Report and Notice of AGM
30th Apr 20187:00 amRNSQ1 2018 Operating Results
26th Apr 20187:00 amRNSAgreement to Purchase Gold Assets in Chukotka
17th Apr 20187:00 amRNS2017 Final Results
11th Apr 20187:38 amRNSFull Year Results Announcement Date
22nd Feb 20188:47 amRNSResources and Reserves Update as at 31 Dec 2017
7th Feb 20187:00 amRNSBelaya Gora/Blagodatnoye PFS and Resource Update
6th Feb 20187:00 amRNSKekura Feasibility Study and Resource Update
5th Feb 20187:00 amRNSBlock listing Interim Review
18th Jan 20187:00 amRNSQ4 2017 Operating Results
13th Dec 20177:00 amRNSBoard of Directors Adopts Dividend Policy
30th Nov 20174:33 pmRNSHolding(s) in Company
20th Nov 20177:00 amRNSUpdated Resource and Reserve Estimates for Novo
9th Nov 201710:17 amRNSAppointment of Chief Operating Officer
11th Oct 20177:00 amRNSQ3 2017 Operating Results
9th Oct 20178:56 amRNSAppointment of Joint Corporate Broker
18th Sep 20173:42 pmRNSHolding(s) in Company
4th Sep 20177:00 amRNSInterim Results Announcement for H1 2017
30th Aug 20177:00 amRNSInterim Results Announcement Date
3rd Aug 20177:00 amRNSBlock listing Interim Review
24th Jul 20177:00 amRNSQ2 2017 Operating Results
5th Jun 20177:00 amRNSCompany Cleared to Proceed with Kekura Development
22nd May 20177:00 amRNSNew Exploration Licences Adjacent to MNV
17th May 20171:11 pmRNSResult of AGM
5th May 20177:00 amRNSDirector/PDMR Shareholding
5th May 20177:00 amRNSUpdated Resource and Reserve Estimates for MNV
28th Apr 201710:32 amRNSMailing of 2016 Annual Report and Notice of AGM
27th Apr 20177:01 amRNSQ1 2017 Operating Results
10th Apr 20177:00 amRNS2016 Final Results
4th Apr 20177:00 amRNSNotice of Results
20th Mar 20177:04 amRNSUnkurtash Scoping Study
1st Mar 20171:25 pmRNSDirector/PDMR Shareholding
21st Feb 20174:06 pmRNSHolding(s) in Company
3rd Feb 20177:00 amRNSBlock listing Interim Review
26th Jan 20179:03 amRNSQ4 2016 Operating Results
9th Nov 20167:00 amRNSDirector/PDMR Shareholding
3rd Nov 20167:00 amRNSQ3 2016 Operating Results
26th Sep 20167:00 amRNSInterim Results Announcement for H1 2016
23rd Sep 20162:54 pmRNSInterim Results Announcement Date
5th Sep 20167:00 amRNSAgreements Signed for State Support of Kekura
9th Aug 20168:30 amRNSQ2 2016 Operating Results (Replacement)
9th Aug 20167:00 amRNSQ2 2016 Operating Results
3rd Aug 20167:00 amRNSBlock listing Interim Review
25th May 201612:00 pmRNSResult of AGM
23rd May 20167:00 amRNSQ1 2016 Operating Results
19th May 20167:00 amRNSKekura Project Update
20th Apr 20167:00 amRNS2015 Final Results
15th Apr 20162:18 pmRNSNotice of Results
3rd Feb 20167:00 amRNSBlocklisting Interim Review

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.