Project Progress Update

27 Jul 2011 07:00

RNS Number : 1013L
Highland Gold Mining Limited
27 July 2011
 



BELAYA GORA PROJECT PROGRESS UPDATE

27 July 2011 - Highland Gold Mining Limited ("Highland Gold" or the "Company" (AIM: HGM)) is pleased to announce that it has submitted the final design documents for approval for the second stage of development of the Belaya Gora Project. First phase mining at the Belaya Gora project was started in November 2010 with delivery of select oxide ore to the MNV processing plant. Progressing to the second important stage in accordance with previously declared timelines underpins the Company's commitment to launch the stand-alone gold processing plant at Belaya Gora during H2 2012.

The design documentation for the second stage of the Belaya Gora Project development was prepared by Zabaikalzolotoproekt (ZZP) Institute (Highland's in-house engineering group), in conjunction with selected consultants. It was submitted for review to the Federal GlavGosExpertise Agency. The anticipated design process capacity averages 1.5 million tonnes of ore per annum with an associated expected gold production ranging from 75,000 to 110,000 oz per annum. Project capex spent to date is approximately US$11.0 million out of a total budget of US $101.1 million planned over the period 2011/12.

Based on comprehensive metallurgical studies completed by the consultancy firm TOMS Research Institute (author of the design process regulation) conventional metallurgical processing based on gravity concentration and whole ore cyanidation technology has proven optimal for gold recovery. CJSC Mekhanobr Engineering, responsible for the design of the tailings storage facility, and LLC Agrospetskompleks, responsible for the design of the water treatment facility, have both provided the expertise to develop comprehensive plans that will ensure that the project remains in compliance with the environmental requirements and guidelines.

The Belaya Gora Project is located 66 kilometers south of the Mnogovershinnoye mine (MNV) and is accessed by an all weather road. In July 2009, the State Committee on Reserves of the Russian Federation (GKZ) registered 820,000 oz of C1+C2 reserves onto the state balance. In order to enhance project economics the Company commenced selective mining of ore with processing via the MNV facilities in November 2010. This first stage of production is expected to continue through to commissioning of the stand alone process plant.

Belaya Gora's management team is in the process of finalising the detailed construction schedule and work plans in order to commence site specific activities. Land clearing and preparation for construction have already commenced and site construction will immediately follow the receipt of the construction permit. The Company's capital construction team has already initiated the selection of a general contractor as well as preparation of tendering documents for the supply of capital equipment.

For further information please contact:

Highland Gold

Dmitry Yakushkin, Head of Communications + 7 495 424 95 21

Duncan Baxter, Chairman + 44 (0) 1534 814 202

Matrix

Robin Henshall, Partner +44 (0) 20 3206 7172

(Nominated Adviser and Broker)

Nick Stone +44 (0) 20 3206 7343

Fin Public Relations

Alex Glover + 44 (0) 20 7608 2280

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEMFDMFFSEEW
Date   Source Headline
17th Sep 20204:30 pmRNSRegulatory Approval
17th Sep 20202:34 pmBUSFORM 8.3 - HIGHLAND GOLD MINING
17th Sep 20201:58 pmBUSForm 8.3 - Highland Gold Mining Ltd
17th Sep 202011:44 amRNSForm 8.5 (EPT/NON-RI)
16th Sep 20201:50 pmBUSForm 8.3 - HIGHLAND GOLD MINING LTD
16th Sep 20209:04 amRNSForm 8.5 (EPT/NON-RI)
16th Sep 20208:54 amRNSForm 8.5 (EPT/RI)
15th Sep 20203:30 pmBUSForm 8.3 - HIGHLAND GOLD MINING LTD
15th Sep 20208:55 amRNSForm 8.5 (EPT/RI)
14th Sep 202011:36 amBUSForm 8.3 - Highland Gold Mining Ltd
14th Sep 202010:44 amRNSHolding(s) in Company
11th Sep 20201:58 pmBUSForm 8.3 - HIGHLAND GOLD MINING LTD
11th Sep 202011:50 amPRNForm 8.3 - Highland Gold Mining Ltd
11th Sep 202010:14 amRNSForm 8.5 (EPT/RI) - Amendment
11th Sep 202010:07 amRNSForm 8.5 (EPT/RI)
10th Sep 20202:22 pmBUSForm 8.3 - HIGHLAND GOLD MINING LTD - AMENDMENT
10th Sep 20201:57 pmRNSHolding(s) in Company
10th Sep 202011:49 amBUSForm 8.3 - Highland Gold Mining Ltd
10th Sep 202011:19 amPRNForm 8.3 - Highland Gold Mining Ltd
10th Sep 20208:55 amRNSForm 8.5 (EPT/RI)
9th Sep 20202:46 pmBUSForm 8.3 - Highland Gold Mining
9th Sep 202012:05 pmPRNForm 8.3 - Highland Gold Mining Ltd
9th Sep 202010:42 amBUSForm 8.3 - HIGHLAND GOLD MINING LTD
9th Sep 20208:15 amRNSForm 8.5 (EPT/RI)
8th Sep 20202:36 pmBUSFORM 8.3 - HIGHLAND GOLD MINING
8th Sep 202010:29 amBUSForm 8.3 - HIGHLAND GOLD MINING LTD
8th Sep 20208:07 amRNSForm 8.5 (EPT/RI)
7th Sep 20203:30 pmEQS***Amended*** Form 8.3 - Tibra Trading PTY Limited: Highland Gold Mining Ltd
7th Sep 20202:55 pmEQSForm 8.3 - Tibra Trading PTY Limited: Highland Gold Mining Ltd
7th Sep 202012:49 pmPRNForm 8.3 - Highland Gold Mining Ltd
7th Sep 202010:35 amRNSForm 8.5 (EPT/NON-RI)
7th Sep 202010:30 amBUSForm 8.3 - Highland Gold Mining Ltd
7th Sep 202010:07 amRNSForm 8.3 - Highland Gold Mining Ltd
7th Sep 20208:54 amRNSForm 8.5 (EPT/RI)
4th Sep 20202:55 pmEQSForm 8.3 - Tibra Trading PTY Limited: Highland Gold Mining Ltd
4th Sep 202012:06 pmPRNForm 8.3 - Highland Gold Mining Ltd
4th Sep 202011:47 amBUSForm 8.3 - Highland Gold Mining Ltd
4th Sep 20209:14 amRNSForm 8.5 (EPT/NON-RI)
4th Sep 20208:35 amRNSForm 8.5 (EPT/RI)
3rd Sep 20202:55 pmEQSForm 8.3 - Tibra Trading PTY Limited: Highland Gold Mining Ltd
3rd Sep 20201:21 pmPRNForm 8.3 - Highland Gold Mining Ltd
3rd Sep 202011:41 amBUSForm 8.3 - HIGHLAND GOLD MINING LTD
3rd Sep 20209:42 amRNSForm 8.3 - Highland Gold Mining Ltd
3rd Sep 20208:41 amRNSForm 8.5 (EPT/RI)
2nd Sep 20202:55 pmEQSForm 8.3 - Tibra Trading PTY Limited: Highland Gold Mining Ltd
2nd Sep 20202:55 pmBUSForm 8.3 - Highland Gold Mining Ltd
2nd Sep 202012:27 pmPRNForm 8.3 - Highland Gold Mining Ltd
2nd Sep 202010:19 amRNSForm 8.3 - Highland Gold Mining Ltd
2nd Sep 20209:07 amRNSForm 8.5 (EPT/RI)
2nd Sep 20207:00 amRNSForm 8.3 - Highland Gold Mining Limited

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.