Update re Operations and Year-end Reserves

15 Feb 2017 07:00

RNS Number : 8937W
Nighthawk Energy plc
15 February 2017
 

15 February 2017

 

NIGHTHAWK ENERGY PLC

("Nighthawk" or "the Company")

 

Company Update

 

Nighthawk, the US focused oil development and production company (AIM: HAWK and OTCQX: NHEGY), announces an update to operations, year-end reserves and cash position.

 

Year-end Reserves Update

The Company has finalized its year-end reserve report and has received the audited Proved Developed Producing reserve report from the Company's independent reserve engineering firm, Ryder Scott Company LP under SPE standards. The reserves were estimated using current production, anticipated decline curves, actual operating costs and future NYMEX prices ranging from $56.11 to $58.10

The reserve volumes, in barrels, are presented below:

 

31-Dec-16

 

31-Dec-15

Audited

Proved Developed Producing (PDP)

1,101,144

1,405,800

Proved Undeveloped (PUD)

442,063

0

Total Proved Reserves (audited)

1,543,207

1,405,800

 

 

 

Probable Reserves

1,800,00

1,423,015

Possible Reserves

545,000

807,000

Total 3P reserves

3,888,207

3,635,815

Although the Company did not perform an audit of Probable and Possible Reserves at 31 December 2016, it is management's opinion that the reserve amounts shown above accurately reflect the Probable and Possible reserve values as of 31 December 2016. The increase in Probable Reserves from 31 December 2015 is primarily due to improved response estimates and reclassification of reserves from the Possible Reserves classification due to the commencement of the water flood pilot project. The methodology used by the Company to arrive at 31 December 2016 Probable and Possible reserves is the same methodology as its independent reserve engineering firm.

The increase from prior year total Proved Reserves is due to reserves associated with Proved Undeveloped category which were deemed uneconomic at 2015 year-end pricing. Based upon current pricing as of 31 December 2016, certain PUDs are now economic and have therefore been included in the above table. The decrease in Proved Developed Producing, which is net of 2016 annual production of 482,119 gross barrels, is due to annual production consistent with expected normal decline curves.

Operations update

Water flood

As reported on 3 January 2017, the Company has commenced injection into both of the water flood pilot project injection wells. It is anticipated that as the injected water fills existing pore volume, consistent with normal nature of water flood projects, a measurable response will be seen. The Company expects this response to be during the second quarter 2017. As such, the incremental volumes expected from the water flood pilot project have not been included in the PDP reserves above but remain as Probable Reserves at the year-end. Once adequate response and evidence is seen as to the response, the reserves are expected to begin being reclassified to PDP.

Production

Total production for the month of January 2017 was approximately 43,595 gross (35,544 net) barrels as compared December 2016 production of 35,985 gross (28,885 net) barrels. The increase in production since December 2016 is due to the successful completion of a new zone in the Monarch 10-15 well, together with bringing wells back in production that were suspended during the installation of the water flood pilot project.

Year-end Cash Balance

As of 31 December 2016, the Company's cash balance was US$5.6 million, of which approximately US$1.2m is committed for expenditure on the Arikaree Creek water flood pilot project. Total expenditures for the water flood pilot project are estimated to total $3.5 million. Based upon current projections, the Company will have adequate cash reserves to maintain its current normal operating activities through 2017.

Chuck Wilson, Chief Operating Officer of Nighthawk, who has over 33 years of experience in the oil and gas industry and meets the criteria of qualified persons under the AIM guidance note for mining and oil and gas companies, has reviewed and approved the technical information contained in this announcement.

 

Enquiries:

 

Nighthawk Energy plc

 

Rick McCullough, Chairman 

+1 303 407 9600

Kurtis Hooley, Chief Financial Officer

+44 (0) 20 3582 1350

 

 

Stockdale Securities Limited

+44 (0) 20 7601 6100

Richard Johnson

 

David Coaten

 

 

 

 

 

Glossary

 

 

 

NYMEX - the New York Mercantile Exchange

 

Proved Reserves - Proved reserves are reserves that have a 90% chance of being higher than estimated and a 10% chance of being lower. Proved reserves include PDP, PDNP and PUD reserve classifications

 

PDP - Proved Developed Producing reserves are expected to be recovered from completion intervals (oil producing zones) that are open and producing at the time of the estimate

 

PDNP - Proved developed reserves that can be expected to be recovered from zones behind casing in existing wells, or from zones that shut-in for market conditions, pipeline connections or mechanical reasons and are capable of production, but the timing is uncertain.

 

PUD - Reserves that are expected to be recovered from new wells on undrilled acreage, or from existing wells where a relatively major expenditure is required for recompletion or opening of new zones of production.

 

2P - Proved and Probable Reserves

 

3P - Proved, Probable and Possible Reserves

 

Probable Reserves - Probable reserves are reserves that have a 50% chance of being higher than estimated and a 50% chance of being lower

 

Possible Reserves - Possible reserves are reserves that have a 10% chance of being greater than estimated and a 90% chance of being smaller

 

SPE - The Society of Petroleum Engineers

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTOKQDNKBKBPBD
Date   Source Headline
26th Mar 20097:00 amRNSHalf Yearly Report
10th Mar 20097:00 amRNSDevon Project Update
27th Feb 200912:09 pmRNSTotal Voting Rights
24th Feb 20097:00 amRNSJolly Ranch Well Acquisition
19th Feb 20097:00 amRNSDevon Discovery
12th Feb 200912:20 pmRNSHolding(s) in Company
12th Feb 200912:17 pmRNSHolding(s) in Company
5th Feb 20097:00 amRNSPlacing
21st Jan 20097:00 amRNSHolding(s) in Company
6th Jan 20097:00 amRNSJolly Ranch Update
19th Dec 20087:00 amRNSJolly Ranch Operational Update
17th Dec 20089:43 amRNSHolding(s) in Company
10th Dec 20087:00 amRNSDirectorate Change and Senior Appointment
9th Dec 200810:43 amRNSHolding(s) in Company
2nd Dec 20089:17 amRNSHolding(s) in Company
1st Dec 20081:01 pmRNSTotal Voting Rights
1st Dec 200810:03 amRNSHolding(s) in Company
26th Nov 20082:55 pmRNSResult of AGM
26th Nov 20087:00 amRNSJolly Ranch Group Update
25th Nov 20087:00 amRNSPlacing of ?5million
13th Nov 20087:00 amRNSCenturion Update
3rd Nov 20087:00 amRNSJolly Ranch Update
29th Oct 20084:38 pmRNSPrice Monitoring Extension
27th Oct 20087:00 amRNSFinal Results
8th Oct 200811:21 amRNSHolding(s) in Company
8th Oct 20087:00 amRNSUpdate on Projects
2nd Oct 20087:55 amRNSUpdate on Projects
23rd Sep 20087:00 amRNSHolding(s) in Company
18th Sep 20087:00 amRNSBuchanan Group Projects Update
4th Sep 20085:20 pmRNSHolding(s) in Company
21st Aug 20089:34 amRNSJolly Ranch Update
29th Jul 20089:05 amRNSHolding(s) in Company
24th Jul 20089:58 amRNSHolding(s) in Company
17th Jul 20089:06 amRNSHolding(s) in Company
30th Jun 20084:03 pmRNSTotal Voting Rights
16th Jun 20087:00 amRNSJolly Ranch and Middle Mist P
9th Jun 20087:00 amRNSBuchanan and Worden Projects
4th Jun 20084:51 pmRNSIssue of Equity
3rd Jun 20087:00 amRNSDevon Oilfield Update
30th May 200812:13 pmRNSTotal Voting Rights
27th May 20084:29 pmRNSIssue of Equity
7th May 20087:00 amRNSJolly Ranch Update
1st May 20082:01 pmRNSHolding(s) in Company
30th Apr 20085:11 pmRNSTotal Voting Rights
30th Apr 20087:01 amRNSJolly Ranch Update
22nd Apr 200812:51 pmRNSHolding(s) in Company
14th Apr 20084:39 pmRNSHolding(s) in Company
4th Apr 20081:56 pmRNSIssue of Equity
28th Mar 20087:01 amRNSHolding(s) in Company
18th Mar 20088:46 amRNSDirector/PDMR Shareholding

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.