Trading Update

1 May 2009 07:00

RNS Number : 5423R
Greenko Group plc
01 May 2009
 



 

Greenko Group PLC ("Greenko" or "the Group")

 

Year-end close and Project update

 

The Directors of Greenko, the Indian renewable energy owner and operator, are pleased to give the following trading update for the year ended 31 March 2009. Despite the difficult global financial market conditions, the renewable sector in India remains robust and Greenko continues to leverage this to its benefit. 

2008/9

 

The existing 6 Biomass plants have performed in line with forecasts, with significantly improved tariffs achieved at Sri Balaji and KMS power (from 3.2 to 3.8 Rs/Kwh), Roshni (from 3.2 to 6.00 Rs/Kwh) and Ravi Kiran power (from 3.1 to 5.00 Rs/Kwh) part way through the year offset to some extent by strategic shut-downs at certain plants. These new tariffs will have a strong impact on the profitability of the plants and the full impact will be apparent in the 2009/10 financial results. Further tariff increases are likely to be achieved as the energy shortage in India continues. 

 

The CER market underwent a significant fall due a number of technical, economic and political factors with prices falling to below €10 per unit. The Directors expect that markets will recover and stabilize but since cash reserves are strong took the decision not to sell the planned level of CER's in the current year. As a result Greenko has retained 160,000 CER units in stock. This retention of CER's will be reflected in a shortfall of income against budget in the year ended 31 March 2009. 

 

The strong performance of the existing assets has largely offset the decision to retain 160,000 CER's, so that the Company's earnings will be broadly in line with market expectation for the year ended 31 March 2009. 

New Projects

 

The Directors are pleased to confirm that AMR and Rithwik, both 24.5MW run-of-the-river hydro plants, have been fully constructedFollowing the commencement of the rainy season in India, which should start in June 2009, these plants will undergo the required regulatory testing prior to commissioning and the Group is confident of generating power at full capacity from these assets for the financial year 2009. In addition to this Sonna, a 10.5 MW run-of-river project, is approaching completion and will be ready to generate electricity in Q3, 2009.

 

The Group continues to identify and examine new projects and is fortunate that the current uncertainties in financial markets have increased the flow of such opportunities. 

 

Enquires:

 

Greenko Group plc

Anil Chalamalasetty +91 (0)98 4964 3333

Mahesh Kolli +44 (0)7767 692729

 

Arden Partners plc

Chris Hardie +44 (0)20 7398 1630

Adrian Trimmings

 

Cardew Group

Rupert Pittman +44 (0)20 7930 0777

Jamie Milton

Catherine Maitland 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTURANRKORSOAR
Date   Source Headline
19th Jun 20147:01 amRNSFinal Results
19th Jun 20147:00 amRNS50 MW of Wind Assets Commissioned
4th Jun 20147:00 amRNSWind Farm Commissioned
15th Apr 201411:00 amRNSDirector Shareholding
14th Apr 20147:00 amRNSTrading Statement
3rd Apr 20148:28 amRNSHolding(s) in Company
3rd Apr 20148:22 amRNSHolding(s) in Company
6th Mar 201411:00 amRNSHolding(s) in Company
6th Mar 20147:00 amRNSMangalore Wind Farm Commissioned
3rd Mar 20147:00 amRNSDirectorate Change
4th Feb 20147:00 amRNS70 MW Hydropower Acquisition
29th Jan 20147:00 amRNSWind Farm Commissioned
27th Jan 201411:00 amRNSHolding(s) in Company
14th Jan 20147:00 amRNSAppointment of Joint Broker
13th Jan 201411:00 amRNSHolding(s) in Company
4th Dec 20137:00 amRNSHalf Yearly Report
27th Nov 20137:00 amRNSNotice of Results
26th Nov 20137:00 amRNSWind Farm Commissioned
11th Nov 20137:00 amRNSWind Farm Commissioned
28th Oct 201311:00 amRNSHolding(s) in Company
28th Oct 201311:00 amRNSHolding(s) in Company
14th Oct 20134:00 pmRNSResult of AGM
10th Oct 20137:00 amRNSTrading Update
30th Sep 20131:23 pmRNSApplication of the Takeover Code
17th Sep 201312:08 pmRNSAnnual Financial Report
16th Sep 20136:08 pmRNSNotice of AGM
26th Jul 20137:00 amRNSDirector/PDMR Shareholding
24th Jul 20137:00 amRNSFinal Results
6th Jun 20135:08 pmRNSHolding(s) in Company
30th May 20133:55 pmRNSHolding(s) in Company
30th May 20133:50 pmRNSHolding(s) in Company
30th May 20133:18 pmRNSHolding(s) in Company
23rd May 20137:00 amRNSOperational Update
7th May 20137:00 amRNSAmendment to GEEMF Terms
8th Apr 20131:00 pmRNSResult of EGM
25th Mar 201312:26 pmRNSDirector/PDMR Shareholding
22nd Mar 20137:00 amRNSDispatch of EGM Circular
15th Mar 20133:10 pmRNSAdditional 425MW of Projects Under Development
15th Mar 20133:08 pmRNSProposed £100 million investment by GIC
28th Feb 20137:01 amRNSDirectorate Change
12th Feb 20134:40 pmRNSSecond Price Monitoring Extn
12th Feb 20134:35 pmRNSPrice Monitoring Extension
13th Dec 20127:00 amRNSHalf Yearly Report
4th Dec 20127:00 amRNSHydropower Acquisition
29th Nov 201211:00 amRNSNotice of Interim Results
19th Nov 201211:00 amRNSHolding(s) in Company
19th Nov 20127:00 amRNSHydropower Acquisition
31st Oct 201212:45 pmRNSResult of AGM
17th Oct 20127:00 amRNSHalf Year Trading Update
5th Oct 20129:29 amRNSNotice of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.