NEWS RELEASE

16-01

January 26, 2016

www.first-quantum.com

 

 

 

 

FIRST QUANTUM MINERALS PROVIDES UPDATE ON POWER SUPPLY TO ITS ZAMBIAN OPERATIONS AND CONFIRMS EXPECTED PROGRESS WITH ITS STRATEGIC INITIATIVES

 

First Quantum Minerals Ltd. ("First Quantum" or the "Company", TSX Symbol "FM", LSE Symbol "FQM") today provided an update regarding the power supply situation in Zambia and in particular, the supply to its Zambian operations.

 

The Company also confirms that the processes, previously announced, to reduce its net debt position by over $1 billion by the end of Q1 2016, through a combination of asset sales and other strategic initiatives, are proceeding as planned with the continued support of its secured lenders.

 

POWER SUPPLY IN ZAMBIA

Zambia is in the midst of its annual rainy season which generally starts in November and runs through April. With the onset of the rains, the catchment area that feeds the Kariba dam, from which the majority of the country's electricity is generated, is being recharged. The river flow at all four upstream measuring stations above Kariba dam are all showing significant increases in flow rates over the past month. Water from the catchment area typically makes its way into the Kariba dam over a period of months with dam recharge occurring from January to June.

 

In addition to this annual replenishment, electricity availability will be augmented by approximately 420MW of new in-country capacity expected online during the current year from projects nearing completion (300MW thermal and 120MW hydro). Currently, the state-run power company is importing power from neighboring countries, and has announced additional power imports of up to 300MW from another utility in the region, and a further 200MW from an independent power producer.

 

First Quantum's Zambian operations, the Kansanshi mine, smelter and the Sentinel project, are being consistently provided a total of approximately 285MW. This allows for normal operations at the Kansanshi mine and smelter complex and for Sentinel to operate at above nameplate capacity throughput for periods.

 

First Quantum is also evaluating a number of options to independently secure power for its operations both in the near and long term.

 

On Behalf of the Board of Directors 12g3-2b-82-4461

of First Quantum Minerals Ltd. Listed in Standard and Poor's

G. Clive Newall

President

 

For further information visit our website at www.first-quantum.com

 

North American contact: Sharon Loung, Director, Investor RelationsTel: (647) 346-3934 Fax: (604) 688-3818 Toll Free: 1 (888) 688-6577 E-Mail: sharon.loung@fqml.comUnited Kingdom contact: Clive Newall, PresidentTel: +44 140 327 3484 Fax: +44 140 327 3494 E-Mail: clive.newall@fqml.com

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBSGDBBDDBGLL
Date   Source Headline
11th Nov 201510:32 amRNS3rd Quarter Results
3rd Nov 20151:58 pmRNSFirst Quantum Reports Strike Action at Cayeli Mine
3rd Nov 201510:47 amRNSHolding(s) in Company
2nd Nov 20155:54 pmRNSTotal Voting Rights
2nd Nov 20154:40 pmRNSSecond Price Monitoring Extn
2nd Nov 20154:35 pmRNSPrice Monitoring Extension
13th Oct 20158:54 amRNSHolding(s) in Company
6th Oct 20157:00 amRNSFinalization of Terms of Precious Metals Stream
6th Oct 20157:00 amRNSUpdate on Key Developments and Actions
5th Oct 20154:56 pmRNSBlocklisting Interim Review
2nd Oct 20157:00 amRNSDirector/PDMR Shareholding
1st Oct 20155:05 pmRNSTotal Voting Rights
1st Oct 20153:04 pmRNSDirector/PDMR Shareholding
30th Sep 20155:39 pmRNSDirector/PDMR Shareholding
28th Sep 20155:22 pmRNSCHANGES TO THE BOARD OF DIRECTORS
28th Sep 20153:57 pmRNSHolding(s) in Company
28th Sep 20152:54 pmRNSFILES NI 43-101 TECHNICAL REPORT
22nd Sep 201511:44 amRNSHolding(s) in Company
22nd Sep 201511:28 amRNSHolding(s) in Company
4th Sep 20153:39 pmRNSHolding(s) in Company
2nd Sep 20153:28 pmRNSTotal Voting Rights
21st Aug 20151:03 pmRNSHolding(s) in Company
21st Aug 20159:51 amRNSDirector/PDMR Shareholding
6th Aug 20155:20 pmRNSRestoration of Full Power to Zambian Operations
4th Aug 20154:50 pmRNSTotal Voting Rights
30th Jul 20157:00 amRNSInterim Dividend Declaration
30th Jul 20157:00 amRNSQ2 2015 RESULTS
28th Jul 20157:00 amRNSIMPOSED POWER REDUCTION AT ZAMBIAN OPERATIONS
22nd Jul 201512:00 pmRNSAMENDED TECHNICAL REPORT FOR COBRE PANAMA
22nd Jul 20157:00 amRNSSTART OF RE-COMMISSIONING AT RAVENSTHORPE
20th Jul 20154:41 pmRNSDirector/PDMR Shareholding
17th Jul 20151:18 pmRNSCLARIFIES INFORMATION FILED TECHNICAL REPORT
6th Jul 20155:10 pmRNSTotal Voting Rights
1st Jul 20152:05 pmRNSDirector/PDMR Shareholding
25th Jun 20155:51 pmRNSUpdate on the Ramp-Up of the Copper Smelter
25th Jun 20153:38 pmRNSDirector/PDMR Shareholding
11th Jun 20158:57 amRNSNotification of Major Interest in Shares
4th Jun 20152:15 pmRNSCLOSING OF EQUITY FINANCING
1st Jun 20152:29 pmRNSTotal Voting Rights
26th May 20157:00 amRNSExercise of Over-Allotment Option
21st May 20153:35 pmRNSTerms of Equity Offering
21st May 20157:00 amRNSCommon Shares Offering
18th May 20153:02 pmRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
11th May 20157:00 amRNSVoting Results for Election of Directors
8th May 20157:00 amRNSDirector/PDMR Shareholding
1st May 20152:48 pmRNSTotal Voting Rights
1st May 20157:00 amRNS1st Quarter Results
16th Apr 20152:50 pmRNSAnnual Information Update
15th Apr 20154:17 pmRNSNotice of Release Date for Q1 2015 Results
7th Apr 20153:33 pmRNSAnnual Disclosure Documents Available Online

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.