The latest Investing Matters Podcast episode featuring financial educator and author Jared Dillian has been released. Listen here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksEuropa Metals Regulatory News (EUZ)

Share Price Information for Europa Metals (EUZ)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 1.15
Bid: 1.10
Ask: 1.20
Change: 0.00 (0.00%)
Spread: 0.10 (9.091%)
Open: 1.15
High: 1.15
Low: 1.15
Prev. Close: 1.15
EUZ Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Quarterly Activities and Cashflow Report

30 Jul 2015 07:00

RNS Number : 4990U
Ferrum Crescent Ltd
30 July 2015
 

30 July 2015

 

Ferrum Crescent Limited

("Ferrum Crescent", the "Company" or the "Group")(ASX: FCR, AIM: FCR, JSE: FCR)

Quarterly Activities and Cashflow Report

For the period ended 30 June 2015

 

Highlights

 

Moonlight Iron Project Bankable Feasibility Study ("BFS"):

 

· The Moonlight Iron Project ("Moonlight" or "Project") involves the proposed future mining and beneficiation of the Moonlight Deposit to produce a high grade concentrate for transport to a pellet manufacturing facility at or near the town of Thabazimbi in Limpopo Province, South Africa for the production of direct reduction ("DR") and blast furnace grade iron pellets for export and domestic sale

· Marketing study instigated relating to the identification of potential South African offtakers for products from the Project

· Planning activities ongoing with infrastructure suppliers (power, water, rail and port)

· Project on schedule to benefit from new regional/national infrastructure developments

· Full assessment of domestic supply options will position Ferrum Crescent as an economic development partner to the Republic of South Africa

· Planned next BFS phases:

o Full Ore Reserve, in terms of JORC (2012), to be established - Infill drilling over Zones A, B and C for advanced mine design work and metallurgical analysis

o Decision to be made on whether bulk sampling is needed

o Final beneficiation and pelletiser designs/costings to be completed

o In the final phase, negotiations and agreements to be concluded with infrastructure providers

Corporate:

· Private placing completed in May 2015 to raise GBP0.5 million (AU$0.97 million) before expenses

· Memorandum of understanding ("MOU") entered into with Principle Monarchy Investments (Proprietary) Limited ("PMI"), whereby PMI may acquire up to 39% of the Project's holding company by way of a 3 tranche subscription for ZAR142 million, subject to the achievement of key milestones

· PMI is a BEE controlled South African company with extensive commercial interests in South Africa ("BEE" is the term used within South Africa to describe entities that meet relevant regulatory criteria as being controlled by historically disadvantaged South Africans)

· First ZAR2m interim funding payment from PMI expected to be received shortly, whereupon the MOU will become legally binding

· Cash balance at the end of the quarter: AU$1.029 million

 

Ferrum Crescent, the ASX, AIM and JSE quoted DR grade pellet project developer, today submits its quarterly activities and cashflow report for the period ending 30 June 2015.

 

During the quarter, the Company entered into an MOU with PMI, under which PMI may acquire up to 39% of Ferrum Iron Ore (Pty) Ltd ("FIO"), the Group's Project holding company for ZAR142 million. Under the terms of the MOU, payment of the first subscription tranche of ZAR30 million must be made by 1 December 2015. In the meantime, PMI is required to make interim payments to FIO of ZAR2 million per month, so that FIO's operational team can continue work on the BFS in close consultation with PMI. Such interim payments are to continue until payment of the first subscription tranche of ZAR30 million, with the monthly payments to be credited towards this first tranche.

 

Receipt of the first ZAR2 million interim payment from PMI is expected shortly. Upon receipt, the MOU will become legally binding, and the parties will thereafter complete a new shareholders' agreement for FIO.

 

Commenting today Tom Revy, Managing Director, said:

 

"Following recommencement of the BFS at Moonlight in Q4 2014, we have confirmed the location for open pit mining operations during the first 10 years of the mine's life and have begun advanced pit design work. Utilising the recent drilling data, we continue to progress the economic model for both the mine and the associated DR pellet complex to be situated at the Thabazimbi railhead.

 

"I cannot overemphasise the significance of securing a partner such as PMI for this Project. In particular, PMI brings commercial and economic strength to Moonlight - through their links with major engineering groups and South African institutions - and we are increasingly doing more to align the Project with the infrastructure plans of the South African and Limpopo governments and seek to address the aspirations and interests of such authorities and those of the local communities and municipalities. We will, of course, make sure that we can provide end product to users within South Africa, and to this end we have commissioned a thorough South African market survey to ensure that domestic needs are met. Overall, we continue to endeavour to maximise the value of Moonlight for the benefit of all stakeholders."

 

For further information on the Company, please visit www.ferrumcrescent.com or contact:

 

Australia enquiries:

UK enquiries:

Ferrum Crescent Limited

Tom Revy T: +61 8 9474 2995

Managing Director

 

Ferrum Crescent Limited

Laurence Read (UK representative)

T: +44 7557672432

Strand Hanson Limited (Nominated Adviser)

Rory Murphy/Matthew Chandler

T: +44 20 7409 3494

Beaufort Securities (Broker)

Elliott Hance

T: +44 20 7382 8416

 

South Africa enquiries:

Bravura Capital (Pty) Ltd (JSE Sponsor)

Doné HattinghT (direct): +27 11 459 5037

 

 

Appendix 5B:

http://www.rns-pdf.londonstockexchange.com/rns/4990U_-2015-7-29.pdf

 

  

 

Notes to Editors:

Ferrum Crescent's principal project is the Moonlight Iron Project located in Limpopo Province in the north of South Africa. The Moonlight Deposit (upon which the Project is based) is a magnetite deposit located on the Moonlight, Gouda Fontein and Julietta farms and is the main operational focus for the Company. Iscor Limited ("Iscor"), which explored the Project in the 1980s and '90s, reported mineralisation capable of producing a concentrate grading at 68.7% iron. At that time, Iscor concluded that the deposit, which was described as being comparable to the world's best, was easily mineable due to its low waste-to-ore ratio. The beneficiation attributes of Moonlight ore are extremely impressive, with low-intensity magnetic separation considered suitable for optimum concentration.

 

Metallurgical tests on Moonlight material, undertaken since then by Ferrum Crescent, suggest that Iscor's historical results are conservative, that good metal recoveries can be achieved, and that the resulting concentrates have a high iron content and only negligible impurities, at grind sizes considered to be industry standard (P80 of 75 - 125 microns).

 

Key features of the Project to date are:

 

Ø JORC (2012) compliant Mineral Resource;

 

Ø Historical drilling, drilling by the Group, geological modelling and a high density geophysical survey conducted by the Company in 2012 confirm tonnage upside potential;

 

Ø 30 year Mining Right granted;

 

Ø Environmental licence (EIA) in place for the Moonlight mining area (approved 4 April 2013);

 

Ø Metallurgical test work indicates the potential for high quality pellets in excess of 69% iron with low deleterious elements (DR grade pellets for use in direct reduction iron/electric arc steel-making processes);

 

Ø Low stripping ratio; slurry pipeline planned to a pellet plant located at a rail head (Thabazimbi); export through Richards Bay;

 

Ø Duferco offtake partner (4.5 Mtpa plus first right on a further 1.5 Mtpa if not sold domestically);

 

Ø Independent valuation by The Mineral Corporation completed in June 2014;

Ø Located near Kumba railhead at Thabazimbi (Kumba operation depleting in grade), Limpopo Province, northern South Africa;

 

Ø New Eskom power plant (4,800MW) commissioning first 800MW module;

 

Ø Richards Bay port expansion for iron ore products.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAPXNAFSSEFF
Date   Source Headline
12th May 20162:15 pmRNSStmnt re Share Price Movement
4th May 20167:00 amRNSHolding(s) in Company
29th Apr 20167:00 amRNSQuarterly Activities and Cashflow Report
27th Apr 201612:42 pmRNSEquity fundraising of £650,000 gross
6th Apr 20167:00 amRNSResults of General Meeting
31st Mar 20169:00 amRNSStrategic Update and Directorate Changes
15th Mar 20169:07 amRNSHalf Yearly Report
15th Mar 20167:00 amRNSHalf Yearly Report
4th Mar 20167:00 amRNSPosting of Notice of General Meeting
25th Feb 201610:00 amRNSFundraising and Notice of General Meeting
16th Feb 20167:00 amRNSOption Over Lead-Zinc Exploration Projects, Spain
29th Jan 20167:00 amRNSQuarterly Activities and Cashflow Report
14th Jan 20167:00 amRNSExtension of Timetable
16th Dec 20157:00 amRNSDirectorate Change
30th Nov 20158:32 amRNSResult of AGM
6th Nov 20158:54 amRNSResponse to ASX Letter re Appendix 5B
30th Oct 20153:30 pmRNSHolding(s) in Company
30th Oct 20157:00 amRNSQuarterly Activities and Cashflow Report
29th Oct 20157:00 amRNSMail-out of Notice of Annual General Meeting
14th Oct 20157:00 amRNSBFS Farm-In Agreement Concluded with BVI/Ovation
30th Sep 20157:00 amRNSFinal Results
30th Jul 20157:00 amRNSQuarterly Activities and Cashflow Report
22nd Jul 201510:30 amRNSUpdate re PMI Funding Arrangements
16th Jul 201512:00 pmRNSUpdate re First Funding Payment from PMI
12th Jun 20159:00 amRNSChange of Address of Share Registry
3rd Jun 20157:00 amRNSUpdate re: BFS Financing Agreement
1st Jun 201512:00 pmRNSUpdate re: Admission of Placement Shares
29th May 20157:00 amRNSChange of Adviser
15th May 201511:34 amRNSReplacement- Changes to Directors' Interests
15th May 20158:00 amRNSDirector/PDMR Shareholding
14th May 20158:01 amRNSPrivate Placing
5th May 20157:01 amRNSUS$12m BFS Financing Agreement
29th Apr 20157:00 amRNSQuarterly Activities and Cashflow Report
28th Apr 20157:00 amRNSBFS Infrastructure Process Update, South Africa
24th Apr 20154:40 pmRNSSecond Price Monitoring Extn
24th Apr 20154:35 pmRNSPrice Monitoring Extension
1st Apr 20158:00 amRNSFirst Mine Location Identified Following Drilling
25th Mar 20157:00 amRNSChange of Registered Office
23rd Mar 201510:00 amRNSChange of Adviser
16th Mar 20157:00 amRNSHalf Yearly Report
2nd Mar 20157:00 amRNSAppointment of Financial Adviser
11th Feb 20159:00 amRNSGrant of Options to Adviser
2nd Feb 20157:00 amRNSFirst BFS Drill Programme Complete
29th Jan 20157:00 amRNSQuarterly Activities and Cashflow Report
21st Jan 20154:40 pmRNSSecond Price Monitoring Extn
21st Jan 20154:35 pmRNSPrice Monitoring Extension
19th Jan 20157:00 amRNSChange of Adviser
15th Dec 201410:35 amRNSHolding(s) in Company
12th Dec 20147:00 amRNSDirectorate Change
10th Dec 20147:00 amRNSIssue of Equity

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.