EQTEC plc (AIM: EQT), the technology solution company for waste gasification to energy projects, is pleased to provide an update on the progress the Company has made with its near-term project pipeline since the completion of acquisition and readmission on 28 December 2017.

 

As stated in the Admission document dated 27 November 2017, a series of projects have been secured by way of an EPC contract and/or an MOU including, Reliable Energy Melton Hull and Reliable Energy Seal Sands projects as well as Zebec Energy project located in the municipality of Usk, Wales.

 

The Company is pleased to report significant progress by signing a new Memorandum of Understanding ("MOU") and taking key steps towards commencing these projects.

 

 

Usk Project (previously known as Zebec Energy project)

The Usk Project located in the municipality of Usk is for a facility which will have a capacity to process ca. 42,000 tonnes of wood waste per year and a power output of 6.4 MWe.

The Company was recently informed by Brooke Energy, Ltd ("Brooke") that the Usk Project in south-east Wales is now to be built and operated by a consortium led by Brooke, a company that builds, operates and manages biomass fuelled power plants that cover the South West of England and Wales.

EQTEC had to renew its agreements with the new operator of the project and has now signed an MOU with the consortium containing Brooke, Exergon Sp. z o.o. ("EXERGON") and RAFAKO SA ("RAFAKO").

 

Under the terms of the MOU, EQTEC will sell its patented EQTEC Gasifier Technology ("EGT") to RAFAKO who is the Engineering, Procurement and Construction ("EPC") Contractor for the whole power plant and will exclusively use its proprietary EGT for the gasification and gas cleaning process. The Usk site has already in place gas engines, a biomass drier, absorption chiller and grid connection among other equipment and the new owner has chosen EGT to complete the project.

 

Brooke will seek to secure equity finance for the project and RAFAKO will seek the debt financing. Financial close and the commencement of the project is, as previously expected, in the first half of 2018.

 

EQTEC revenues from the Usk Project are still expected to be c. €11 million to be invoiced over a period of two years.

 

 

Reliable Energy Solutions

 

Reliable Energy Solutions ("Reliable") is focused on developing Melton Hull and Seal Sands, two 16 MWe Energy from Waste ("EfW") projects in the North East of England.

 

A primary EPC contract was signed in July 2017 between Reliable and Energy China for both projects which specifies the use of the Company's EGT. The total project investment for the two plants is forecast to be approximately €210 million and each plant is expected to process 130,000t of waste each year.

 

In 2018, EQTEC and Energy China have been working on the engineering of a revised scheme for the application of EGT coupled to a steam turbine instead of the previous scheme of coupling to a gas engine. The shift to a steam turbine is because initial indications show an increase on the projected returns of the project. A future benefit of this revised scheme is that the additional engineering work will enable the Company to compete in a wider range of projects with power outputs up to 50 MWe.

 

As a result of the revision of the scheme, financial close and the commencement of both projects is now expected to occur within the next three to six months, when the engineering works to develop the revised scheme for the application of EGT coupled to a steam turbine will be finished. The estimated turnover of EQTEC on each project is €19 million of the EPC contract to be spread over a period of two years.

 

Discussions are ongoing with China Construction Bank for debt finance for the projects and with a major third-party investor for the provision of equity for each project.

 

Luis Sanchez, CEO of EQTEC plc, commented: "We are pleased that our three near-term projects in the UK are all progressing well. The objective of our strategy of forming strategic alliances with major players in the energy infrastructure sector such as COBRA, Energy China and RAFAKO is to accelerate growth and increase scale in order to take advantage of the lack of domestic incineration and gasification capacity that is forcing the UK to pay European incinerators to take its waste. The strategic alliances also enable us to be in a prime position to win Energy from Waste projects in the UK, Spain, France and Croatia."

 

Enquiries

 

EQTEC plc

+353 (0)21 2409 056

Luis Sanchez - Chief Executive Officer

Gerry Madden - Finance Director

 

 

 

Northland Capital Partners Limited - Nomad and Joint Broker

+44 (0)20 3861 6625

Tom Price / Dugald J. Carlean

 

 

 

SVS Securities Plc - Joint Broker

+44 (0)20 3700 0093

Tom Curran / Ben Tadd

 

 

 

VSA Capital Limited - Financial Adviser and Joint Broker

+44 (0)20 3005 5000

Andrew Monk / Andrew Raca

 

 

 

Luther Pendragon - Financial PR

+44 (0)20 7618 9100

Harry Chathli / Alexis Gore / Ana Ribeiro

 

 

Notes to Editors

 

About EQTEC plc

 

EQTEC's business model involves sourcing and providing assistance in developing waste elimination projects to which it will ultimately sell its EQTEC Gasifier Technology ("EGT") and O&M services. EGT enables project developers to construct waste elimination plants and recover electrical and thermal energy from the waste streams.

 

EQTEC sources projects that have a local supply of waste in need of elimination and conversion. It builds relationships and brings together the developers, the waste owners, the building contractors and funders. It then supplies the energy recovery technology and provides engineering services to the projects. Furthermore, EQTEC will provide O&M services to the operating projects generating recurring revenues over the life of the projects.

 

The Company is quoted on AIM and trades as EQT. Further information on the Company can be found at www.eqtecplc.com.

 

About RAFAKO and EXERGON

 

RAFAKO is part of the PBG Group and is involved in the power generation industry with particular experience in biomass and waste power plants.

 

EXERGON is a spinout from the Silesian University of Technology in Poland. It operates in the power and related industries, providing computing and consulting services, preparing feasibility studies and business plans.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCXQLFBVXFLBBD
Date   Source Headline
25th Feb 20263:55 pmRNSChange of Name
25th Feb 20267:00 amRNSHigh-Grade Copper and Gold Potential at Green Rock
23rd Feb 20267:00 amRNSFacility Conversion Notice and Cancellation
16th Feb 20263:13 pmRNSCompletion of Proposals
12th Feb 20263:04 pmRNSResult of Extraordinary General Meeting
29th Jan 20267:33 amRNSPlacing, Debt Restructure and Acquisition
21st Jan 20267:00 amRNSPublication of Circular and Notice of EGM
14th Jan 20265:30 pmRNSFacility Conversion Notice
14th Jan 20267:00 amRNSComplementary strategic expansion
23rd Dec 202511:45 amRNSDrawdown and Funding Update
15th Dec 20253:38 pmRNSFacility Conversion Notice
11th Dec 20256:02 pmRNSFacility Conversion Notice
9th Dec 20257:00 amRNSHoldings in Company
3rd Dec 20258:14 amRNSProject Funding Update: France
24th Nov 202512:30 pmRNSCorporate and Funding Update
7th Nov 20254:35 pmRNSFacility Conversion Notice
24th Oct 20257:00 amRNSCompany update, Board changes and Funding
6th Oct 20257:00 amRNSUltimate Beneficial Owner Notification
29th Sep 20257:00 amRNSInterim Results
25th Sep 20256:00 pmRNSResult of Annual General Meeting
29th Aug 20257:00 amRNSProposed Capital Reorganisation and Notice of AGM
11th Aug 202510:37 amRNSExercise of Option & Subscription of £250k
25th Jun 20251:27 pmRNSResults of EGM
2nd Jun 20257:00 amRNSPublication of Circular and Notice of EGM
10th Apr 20257:00 amRNS£1.5m Subscription and Loan Transfer
15th Nov 20248:10 amRNSDisposal of MetalNRG Shares
15th Nov 20247:00 amRNSHolding(s) in Company
5th Nov 20247:00 amRNSCollaboration Framework Agreement in the USA
26th Sep 20247:04 amRNSInterim Results
18th Sep 20247:00 amRNSAppointment of Non-executive Director
16th Sep 20247:00 amRNSSenior Management Appointment
12th Sep 20247:00 amRNSSuccessful steam oxygen gasification test results
9th Sep 20248:03 amRNSResult of WRAP Retail Offer
4th Sep 20247:51 amRNSWRAP Retail Offer for up to £200,000
4th Sep 20247:50 amRNS£1.1m Fundraise, Retail Offer & Debt Conversion
4th Sep 20247:00 amRNSReceipt of funds under Settlement Agreement
14th Aug 20247:00 amRNSUpdate on Settlement Agreement with Logik
9th Aug 20247:00 amRNSTransition of Group COO role
6th Aug 20242:20 pmRNSResults of 2024 AGM
29th Jul 20241:30 pmRNSUpdate on Settlement Agreement with Logik
26th Jul 20247:00 amRNSAcquisition of property housing Italy MDC plant
15th Jul 20247:00 amRNSUpdate on Settlement Agreement with Logik
10th Jul 20247:00 amRNSNotice of AGM
28th Jun 20248:23 amRNSUpdate on Settlement with Logik Developments
28th Jun 20247:00 amRNSFinal Results
26th Jun 202412:22 pmRNSHolding(s) in Company
12th Jun 20244:09 pmRNSHolding(s) in Company
11th Jun 20241:58 pmRNSEquity placement update and total voting rights
31st May 20241:56 pmRNSEquity placement update and total voting rights
28th May 20247:00 amRNSEquity placement of c. £850,000

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.