Operations Update

14 Aug 2013 07:00

RNS Number : 6219L
Eland Oil & Gas PLC
14 August 2013
 



 

14 August 2013

 

ELAND OIL & GAS PLC

 

("Eland" or the "Company")

 

Operations Update

 

Eland Oil & Gas PLC (AIM: ELA), an oil & gas development and exploration company operating in West Africa with a principal focus on Nigeria, announces the following update on activities for the OML 40 License, located in on shore Nigeria ("OML 40").

 

Highlights

 

Once first oil is achieved, the long term development and appraisal drilling programme for OML 40 will commence with the Opuama Field which has certified gross 2P reserves of 54 Million bbls (from a total licence 2P number of 82 Million) and an initial production capacity of 30,000 bopd.

 

· Refurbishment of existing facilities is now progressing with operations personnel on site and initial integrity tests indicating that the facilities are in good condition

 

· Some delays in contracting services and local permitting have been experienced to date and as a result first oil production in excess of 2,500 bopd from two previously shut in wells is now anticipated in October

 

· The Swamp Rig 'Depthwize Imperial' is planned to mobilize to OML 40 in Q4 2013 allowing the commencement of drilling the first new well before year end. Contractual arrangements are currently being finalized by the operator, NPDC

 

· Year end exit production rate is anticipated in the range 2,500 to 5,500 bopd, dependent on timing of completion of the first new well. It is expected that production will increase by circa 3,000 bopd for each subsequent new well drilled

 

· Debt facilities already agreed are available post first oil.

 

 

OML 40 Operations update

 

Since the Company's previous operations update, contained in the 2012 Annual Results published on 29 May 2013, planning and work for the rehabilitation and restart of existing production facilities on OML 40 has continued.

 

NPDC's refurbishment and recertification of the existing production flowstation facilities and the 30 metre sectional repair of the export pipeline is on-going. Integrity tests have been made on the facilities and all are in good condition with a minimum level of refurbishment needed. Two new 4" flowlines are being installed to replace the pre-exiting lines as a precautionary measure against corrosion.

 

Initial production will be from two existing wells that were shut in in 2006 in a controlled shutdown. These wells are anticipated to flow at a minimum rate of 2,500 bopd based on the well test conducted immediately prior to the controlled shutdown with additional development wells forecast to flow at 3,000 bopd. With this work still underway, production restart on OML 40 is expected for October.

 

Following the restoration of production, the development drilling programme will start on the Opuama field where there are production and export facilities with a throughput capacity of 30,000 bopd and where Netherland, Sewell & Associates, Inc. recently certified gross 2P reserves of 54.2 MMbbls.

 

Initial drilling will be performed by the swamp rig 'Imperial', which will be secured by NPDC and committed to the development programme on OML 40 in Q4 2013. It is planned that the Imperial will move across to OML 40 later in the year, when it's current operator completes a single well program.

 

Previous guidance for drilling has been 2 production wells to spud in 2013 with a year end exit production rate of 10,000 bopd. Due to a delay in rig availability the Company is adjusting its guidance to one new development well being spudded in Q4 2013 with an exit production rate in the range of 2,500 and 5,500 bopd, dependent on timing of completion of the first new well. The spudding of the second development well on Opuama field, planned and budgeted for 2013, is now anticipated for early 2014 in conjunction with the on-going field development plan.

 

 

 

Les Blair, CEO of Eland Oil & Gas, commented:

 

"Field refurbishment is progressing well and despite earlier delays, indications are that the facilities are in good condition which bodes well for the long-term development of OML 40. We are looking forward to gaining entry to the two previously shut in wells and our first production revenues.

 

Furthermore, we are very excited at the prospect of drilling of our first new production well and subsequently beginning the process of rapid production growth, at what we anticipate to be a rate of circa 3,000 bopd for each scheduled new well.

 

The momentum of OML 40 development work is now gathering pace."

 

 

 

For further information:

 

Eland Oil & Gas PLC (+44 (0) 207 016 3180)

Les Blair, CEO

George Maxwell, CFO

Edward Cozens, IR

 

Canaccord Genuity Limited (+44 (0) 207 523 8000)

Henry Fitzgerald-O'Connor

Peter Stewart

 

FirstEnergy Capital LLP (+44 (0) 207 448 0200)

Majid Shafiq

Khalid Ahmed

 

Citigate Dewe Rogerson (+44 (0) 207 638 9571)

Martin Jackson

Jack Rich

 

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBUGDIBUBBGXX
Date   Source Headline
11th Dec 20185:38 pmRNSTransaction in Own Shares
10th Dec 20186:03 pmRNSTransaction in Own Shares
7th Dec 20186:03 pmRNSTransaction in Own Shares
6th Dec 20185:52 pmRNSTransaction in Own Shares
6th Dec 20187:00 amRNSUbima Appraisal Update
5th Dec 20185:37 pmRNSTransaction in Own Shares
4th Dec 20185:35 pmRNSTransaction in Own Shares
3rd Dec 20186:02 pmRNSTransaction in Own Shares
3rd Dec 20187:00 amRNSTransaction in Own Shares
29th Nov 20186:06 pmRNSRefinancing of Reserve-Based Lending Facility
29th Nov 20186:01 pmRNSTransaction in Own Shares
28th Nov 20186:08 pmRNSTransaction in Own Shares
27th Nov 20185:28 pmRNSTransaction in Own Shares
26th Nov 20185:30 pmRNSTransaction in Own Shares
23rd Nov 20186:08 pmRNSTransaction in Own Shares
22nd Nov 20186:18 pmRNSTransaction in Own Shares
21st Nov 20185:30 pmRNSTransaction in Own Shares
21st Nov 20187:00 amRNSDirector and PCA Dealing
21st Nov 20187:00 amRNSTransaction in Own Shares
19th Nov 20187:00 amRNSShare Buyback Programme
16th Nov 20187:00 amRNSGbetiokun Operations Update
15th Nov 20187:01 amRNSChange of Joint Broker
15th Nov 20187:00 amRNSChange of Nominated Advisor and Joint Broker
12th Nov 20187:00 amRNSConfirmation of Licence Renewal
29th Oct 201810:35 amRNSDirector and PCA Dealing
26th Oct 20187:00 amRNSOperations Update
5th Oct 201811:45 amRNSHolding(s) in Company
20th Sep 20187:00 amRNSInterim Results for the six months to 30 June 2018
18th Sep 20187:00 amRNSOpuama and Ubima Update
16th Aug 20187:00 amRNSOpuama Operations Update
31st Jul 20187:00 amRNSCommencement of Ubima Appraisal
25th Jul 20187:00 amRNSOpuama-10 Update
9th Jul 20181:08 pmRNSDirector and PCA Dealing
6th Jul 201811:58 amRNSDirector and PCA Dealing
4th Jul 20187:00 amRNSOpuama Field Operations Update
3rd Jul 201811:41 amRNSDirector and PCA Dealing
2nd Jul 20185:51 pmRNSHolding(s) in Company
2nd Jul 20182:22 pmRNSDirector and PCA Dealing
26th Jun 201812:56 pmRNSDirector and PCA Dealing
21st Jun 20184:49 pmRNSDirector and PCA Dealing
20th Jun 20184:04 pmRNSAppointment of Non-Executive Director
14th Jun 20187:00 amRNSOpuama-9 Update
25th May 20189:15 amRNSLong Term Incentive Plan ("LTIP") Awards
17th May 20181:00 pmRNSCapital Markets Day Presentation
17th May 201812:09 pmRNSRig contract signed for the drilling of Ubima-1
16th May 20187:00 amRNSOpuama-9 Update
15th May 20185:33 pmRNSResult of Annual General Meeting
23rd Apr 20189:30 amRNSPosting of Annual Report & Notice of AGM
18th Apr 20187:00 amRNSFinal Results for the Year ended 31 December 2017
18th Apr 20187:00 amRNSOpuama-9 Operations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.