Operations Update

16 Oct 2013 07:00

RNS Number : 5998Q
Eland Oil & Gas PLC
16 October 2013
 



 

16 October 2013

 

Eland Oil & Gas PLC

 ("Eland" or the "Company")

 

Operations Update

 

Eland Oil & Gas PLC (AIM: ELA), an oil & gas development and exploration company operating in West Africa with an initial focus on Nigeria, announces the following update on activities for the OML 40 licence, located onshore Nigeria ("OML 40").

 

HIGHLIGHTS

 

 

· The Opuama Production Facility was shut down in March 2006 and consequently there has been some deterioration of infrastructure. Eland have worked closely with the Operator (NPDC) to re-start the production in a challenging operating environment. This joint approach has ensured that the complex issues have been addressed collectively and resolved to provide the best opportunity for an early restart of production on the facility which has been shut in for 7 years. Operational activities in 2013 have therefore been initially focused on replacement of the corroded infield flowlines, refurbishment of the production flowstation and the repair of the oil export pipeline including the replacement of all corroded and damaged sections.

 

· The work of fabrication and installation has been completed to fully replace the 3 flowlines on the planned existing start-up wells in the Opuama Field. These flowlines have been trenched and overlaid with protective concrete mats at major water crossings. A cathodic protection system has also been installed.

 

· The 8" and 10" sections of the export pipeline have been surveyed and repaired (first 12km of 36km). This section of the line is currently being flushed prior to conducting a full pressure test to verify its integrity. The repairs to the final 24km-long 12" section to Otumara (custody transfer point) are on-going and expected to complete within the next 3-4 weeks.

 

· The Opuama Flowstation Rehabilitation work is currently underway with purchasing of the major components ongoing and site activities starting.  The work program is expected to have a 3-5 week duration.

 

· With these final works expected to complete over the coming weeks, management is confident that production will commence before year end. While this is a deferment from the previously prognosed October, comfort can be drawn from the fact that work on all components is underway and is being vigorously monitored for ways of improvement.

 

· Drilling of the initial six development wells within the Opuama Field (Gross Certified 2P Reserves of 54.2 Million bbls) is planned to commence upon the release of the Depthwize Imperial swamp rig currently on a single well assignment with Conoil on OPL 2007. The latest information from the current operator indicates that the Rig should be released from location in early 2014.

 

· Year-end exit production rate is anticipated to be in excess of 2,500 bopd from the planned restart of the two existing wells in the Opuama Field. It is then anticipated that production will increase by circa 3,000 bopd for each subsequent new well drilled during 2014. These wells will be hooked up to the production facility as they are drilled.

 

· The agreed debt facilities with Standard Chartered Bank remain available following first oil and the Company currently has sufficient cash to meet first oil requirements.

 

 

Les Blair, CEO of Eland Oil & Gas, commented:

"Our immediate focus is to restore oil production on OML 40 and we have a close working relationship with the Operator, NPDC, to achieve this goal. In parallel we continue planning for the extensive development drilling campaign on OML 40, starting with six wells on the Opuama Field.

The delays we have experienced are frustrating but not unexpected in a project of this complexity and in the environment in which we are operating. The management of Eland have significant experience of working in Nigeria and have established excellent working relationships with NPDC and all of our stakeholders in the license area. This will stand the Company in good stead to unlock the value inherent in OML 40, which will be amply demonstrated when the drilling campaign gets underway."

 

For further information:

 

Eland Oil & Gas PLC (+44 (0) 207 016 3180)

Les Blair, CEO

George Maxwell, CFO

Edward Cozens, IR

 

Canaccord Genuity Limited (+44 (0) 207 523 8000)

Henry Fitzgerald-O'Connor

Peter Stewart

 

FirstEnergy Capital LLP (+44 (0) 207 448 0200)

Majid Shafiq

Khalid Ahmed

 

Citigate Dewe Rogerson (+44 (0) 207 638 9571)

Martin Jackson

Jack Rich

 

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDDBDGDUBBGXU
Date   Source Headline
18th Apr 20187:00 amRNSOML 40 Reserves and Resources Update
6th Apr 20187:00 amRNSRBL Facility Update
21st Mar 20187:00 amRNSOpuama Operations Update
8th Mar 20187:00 amRNSTR-1: notification of major holdings
13th Feb 20187:00 amRNSOpuama Operations Update
25th Jan 20181:34 pmRNSTR-1: Notification of major holdings
17th Jan 20187:00 amRNSOpuama-8 and -9 Infill Wells Update
12th Jan 20184:37 pmRNSPrice Monitoring Extension
27th Dec 20172:21 pmRNSHolding(s) in Company
22nd Dec 20177:00 amRNSSyndication of RBL
21st Dec 20172:24 pmRNSOpuama-8 Update
15th Nov 20177:00 amRNSOpuama Operations Update
10th Nov 201712:14 pmRNSImplementation of Long Term Incentive Plan
9th Nov 20177:00 amRNSOpuama Work Programme Confirmed
7th Nov 20177:00 amRNSOpuama-7 and Opuama-8 Update
23rd Oct 20177:00 amRNSOpuama-7 side-track and Work Programme Update
26th Sep 20177:00 amRNSInterim results for the six months to 30 June 2017
18th Sep 20177:00 amRNSOpuama-7 Drilling and Crude Sales Update
5th Sep 20177:00 amRNSAppointment of Non-Executive Director
1st Sep 20177:00 amRNSMobilisation of Rig to the Opuama Field
1st Aug 20177:00 amRNSAppointment of CFO
24th Jul 20177:00 amRNSDirectorate Change
24th Jul 20177:00 amRNSOperations Update
4th Jul 20177:00 amRNSReplacement - Conversion of Shares
29th Jun 20174:36 pmRNSHolding(s) in Company
29th Jun 20171:45 pmRNSResult of Annual General Meeting
22nd Jun 20176:11 pmRNSConversion of Shares by Helios Natural Resources
15th Jun 20174:42 pmRNSTR-1: Notification of Major Interest in Shares
13th Jun 20177:00 amRNSRig contract signed
8th Jun 201711:35 amRNSNotice of AGM
7th Jun 20176:25 pmRNSCompletion of Oversubscribed Placing
7th Jun 20177:00 amRNSProposed placing by way of accelerated bookbuild
6th Jun 20174:30 pmRNSFinal Results for the Year ended 31 December 2016
1st Jun 20177:00 amRNSOperations, 2016 Accounts & OML 40 Resource Update
25th May 201711:07 amRNSProduction Update
18th May 201712:02 pmRNSPrice Monitoring Extension
27th Apr 20172:30 pmRNSCapital Markets Day
27th Apr 20177:00 amRNSNear-Term Reserves Update
24th Apr 20177:00 amRNSOperational and Funding Update
4th Apr 20177:05 amRNSHolding(s) in Company
4th Apr 20177:00 amRNSHolding(s) in Company
31st Mar 20177:38 amRNSReplacement - Quarterly Update
31st Mar 20177:00 amRNSQuarterly Update
21st Feb 20177:00 amRNSOperational Update
31st Jan 20177:00 amRNSRecommencement of Production
23rd Nov 20167:00 amRNSProduction Test and Operational Update
3rd Nov 20169:45 amRNSUpdated Presentation
22nd Sep 20167:00 amRNSInterim results for the six months to 30 June 2016
11th Jul 20167:01 amRNSDirectorate Change
11th Jul 20167:00 amRNSOperations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.