Goudron Drilling and Infrastructure Update

11 Jul 2014 07:00

RNS Number : 0427M
Leni Gas & Oil PLC
11 July 2014
 

For Immediate Release

11 July 2014

 

 

 

Leni Gas & Oil PLC

("LGO" or the "Company")

 

Goudron Drilling and Infrastructure Update

 

LGO today announces that the fourth of its planned Goudron development wells, GY-667, was successfully spudded yesterday at 1530 hrs T&T time and is now drilling ahead in the Goudron Sandstones.

 

The well is being drilled as a deviated hole from the same well pad as used for the recently drilled wells GY-665 and GY-666. 

Well GY-667 has a planned total depth of 3,600 feet true-vertical depth ("TVD") (equivalent to 3,840 feet measured depth) to a bottom-hole location that is approximately 590 feet south east of the surface location. The primary target of this well is the Gros Morne sandstones, the top of which are anticipated at a depth of approximately 2,180 feet TVD. The well will also investigate the reservoir potential of the Lower Cruse at this location.

 

Further announcements will be made once the main reservoir targets have been drilled.

 

Separately, final approvals have now been received for the construction and installation of a new 2,000-barrel sales tank and construction contracts have been awarded. The new tank will be installed at the Goudron Field's oil sales point at Tank Battery Station 134 and will be adjacent to the two existing sales tanks increasing total daily export capacity equivalent to approximately 2,750 barrels of oil per day. It is anticipated that the new tank will be commissioned to coincide with the completion of the four wells being drilled on the current well pad; of which GY-667 is the third.

 

Negotiations for a second drilling rig are actively being progressed with a variety of different options emerging. It is planned to retain Well Services Rig 20 for at least a further six wells and no decision has yet been taken on the choice of the second rig.

 

Neil Ritson, LGO Chief Executive, commented:

 

"The 30 well drilling campaign continues to advance extremely well and we are making considerable progress in learning about the geology and drilling characteristics of the field. That knowledge is being used to optimize the development and we anticipate both cost and timing efficiencies will continue to be made through the remainder of the program. The addition of an optimally specified second rig remains an objective for the third quarter. "

 

Results from the drilling program to date are given in the table in Appendix below.

 

 

 

Competent Person's Statement:

The information contained in this announcement has been reviewed and approved by Neil Ritson, Chief Executive Officer and Director for Leni Gas & Oil Plc, who has over 35 years of relevant experience in the oil industry. Mr. Ritson is a member of the Society of Petroleum Engineers (SPE), an Active Member of the American Association of Petroleum Geologists (AAPG) and is a Fellow of the Geological Society of London.

 

Enquiries:

Leni Gas & Oil plc

David Lenigas

Neil Ritson

+44 (0)20 7440 0645

 

Beaumont Cornish Limited

Nomad and Joint Broker

Rosalind Hill Abrahams

Roland Cornish

+44(0) 20 7628 3396

 

Old Park Lane Capital Plc

Joint Broker

Michael Parnes

+44(0) 20 7493 8188

 

Pelham Bell Pottinger

Financial PR

Mark Antelme

 +44 (0) 20 7861 3232

Henry Lerwill

 

Appendix:

Well

Name

Spud

Total Depth

(MD feet)

Total Depth

Goudron

Net Pay

(feet)

Gros Morne

Net Pay

(feet)

Lower Cruse Net Pay

(feet)

Compl-etion

Formation

Completed Interval (feet)

Initial Production Rate

(bopd)

1

GY-664

28 April

4212

13 May

192

300

79

30 May

Gros Morne

278

240

2

GY-665

27 May

2750

8 June

195

256

np

3

GY-666

16 June

3357

1 July

185

209

28

4

GY-667

10 July

All depths are quoted as measured depth in feet below Kelly bushing

np = not penetrated

 

Glossary:

Pay: A reservoir or portion of a reservoir formation that contains economically producible hydrocarbons. The overall interval in which pay sections occur is the gross pay; the portion of the gross pay that meets specific criteria such as minimum porosity, permeability and hydrocarbon saturation are termed net pay.

MD: Measured Depth

TD: Total Depth

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLRMMTTMBIBTFI
Date   Source Headline
10th Oct 20147:00 amRNSGoudron Update, Trinidad
2nd Oct 20147:00 amRNSDrilling Update,Trinidad
29th Sep 201410:00 amRNSGoudron Field Update
26th Sep 20144:27 pmRNSUnaudited Interim Results to 30 June 2014
25th Sep 20141:00 pmRNSRecord Oil Production and Well Update
17th Sep 20147:00 amRNSInitial Flow Rate GY-665
8th Sep 20147:00 amRNSPresentation at Proactive Investor Forum
1st Sep 20147:00 amRNSGoudron Drilling Update, GY-668
27th Aug 20147:00 amRNSBoard Changes
21st Aug 20147:00 amRNSGoudron Drilling Update, GY-668
11th Aug 20147:00 amRNSDrilling Report
7th Aug 20147:00 amRNSDirectorate Change
4th Aug 20147:34 amRNSGoudron Drilling Update
31st Jul 201411:56 amRNSTotal Voting Rights
31st Jul 20149:02 amRNSGoudron Well GY-667 Reaches Total Depth
31st Jul 20147:00 amRNSSettlement of Litigation Costs
22nd Jul 20147:00 amRNSGoudron Drilling Update
17th Jul 20147:00 amRNSLGO raises £7 million
16th Jul 20147:00 amRNSPotential Acquisition of Producing Oil Field
11th Jul 20147:00 amRNSGoudron Drilling and Infrastructure Update
7th Jul 20146:18 pmRNSExercise of Warrants and Total Voting Rights
7th Jul 20142:32 pmRNSResult of AGM
3rd Jul 20147:00 amRNSGoudron Well GY-666 Reaches Total Depth
30th Jun 20142:33 pmRNSTotal Voting Rights
24th Jun 20147:11 amRNSGoudron Drilling Update
19th Jun 20145:10 pmRNSAnnual Financial Report - Replacement
17th Jun 20146:20 pmRNSExercise of Warrants and Total Voting Rights
17th Jun 20147:00 amRNSGoudron Development Drilling Update
13th Jun 20144:38 pmRNSAnnual Financial Report
11th Jun 201412:42 pmRNSGoudron Drilling Update
9th Jun 20147:00 amRNSGoudron Drilling Update
4th Jun 20149:34 amRNSTalks on potential partnership in Spain terminated
3rd Jun 20143:03 pmRNSLGO Fully Closes YAGM Equity Swap
3rd Jun 201411:47 amRNSGY-665 Drilling Update
2nd Jun 201411:28 amRNSTotal Voting Rights
2nd Jun 20147:00 amRNSGY-664 Production and GY-665 Update
28th May 20147:00 amRNSGoudron Drilling Update
27th May 20148:30 amRNSReserves Clarification, Trinidad
27th May 20147:00 amRNSGoudron Update
19th May 20147:00 amRNSGoudron Development Update, Trinidad
14th May 20147:00 amRNSWell GY-664 Update, Trinidad
12th May 20147:00 amRNSProduction and Drilling Update, Trinidad
6th May 20147:01 amRNSUpdate on GY-664 Goudron, Trinidad
1st May 20147:00 amRNSDrilling Report
28th Apr 20149:31 amRNSGoudron Drilling
25th Apr 20146:19 pmRNSFunding and New Trinidad producing fields review
24th Apr 20149:00 amRNSCompany Update
17th Apr 20147:00 amRNSRig Mobilisation, Goudron Field, Trinidad
10th Apr 201412:11 pmRNSUpdate Maxim Joint Venture in Trinidad
3rd Apr 201411:48 amRNSLitigation Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.