Kalia Mine JORC Resource Increase

26 Sep 2011 07:00

RNS Number : 8675O
Bellzone Mining PLC
26 September 2011
 



 

 

 

 

 

26 September 2011

 

 

 

 

Bellzone Mining plc

("Bellzone" or the "Company")

 

Significant Increase in Kalia Mine JORC Resource

 

Highlights:

 

·; Total Kalia I JORC magnetite mineral resource increased to 6.16 billion tonnes

 

- 63% increase in the measured and indicated JORC resource of the Kalia I banded iron formation ("BIF") magnetite from 670mt at 27.7% Fe to 1,095mt at 27.4% Fe

- 65% increase in overall Kalia I magnetite JORC resource (BIF and Schist) from 3.74 billion tonnes to 6.16 billion tonnes

·; 7km of the 19km Kalia I strike has been drilled to date

·; Bulk testwork has shown the magnetite can be readily beneficiated using a standard grinding and magnetic process to produce a magnetite concentrate of +68% Fe

 

Bellzone Mining plc (AIM:BZM), is pleased to announce an overall 65% increase to 6.16 billion tonnes in the total JORC magnetite resource at its 100% owned Kalia Mine Project in Guinea, West Africa. The updated JORC resource was prepared by independent consultant CSA Global UK.

 

The Kalia Mine Project has a current magnetite iron ore resource of:

Kalia Mineral Resource Estimate as at 23 September 2011

JORC Resource Class

Magnetite

Billion

Fe%

Host Material

Tonnes

MEASURED

BIF

0.24

27.9

INDICATED

BIF

0.85

27.3

MEASURED + INDICATED

BIF

1.095

27.4

INFERRED

BIF

3.54

25.4

SUB - TOTAL BIF RESOURCE

BIF

4.63

25.9

INFERRED

SCHIST

1.53

9.6

TOTAL JORC RESOURCE

BIF + SCHIST

6.16

21.9

EXPLORATION POTENTIAL

BIF + SCHIST

1.0 - 1.7

15.00-25.00

 

 

The Company has now completed an 18,000m diamond drilling ("DD") infill programme, which commenced in Q3 2010, which resulted in the increase to the magnetite measured and indicated JORC resource.

 

The competent BIF JORC resource has increased from 3.05 billion tonnes, grading at 25.8%Fe to 4.63 billion tonnes grading at 25.9% Fe, with the softer lower grade magnetite schist inferred JORC resource increasing from 690 million tonnes to 1.53 billion tonnes.

 

The next phase of the Company's magnetite extension DD programme is expected to add a further 1km to the drilled strike length and to extend the resource depths. The results of the magnetite extension DD programme are expected in Q2 2012. The exploration potential of an additional 1.0 to 1.7 billion tonnes will be targeted as part of this ongoing programme.

 

Resource classification was based on a number of criteria, including grade interpolation parameters, geology continuity, drill core samples, survey and bulk density data, the drilling grid, Davis Tube Magnetite recovery test work and an updated preliminary Whittle optimisation assessment completed to determine project economics. The bulk test work assays and Davis Tube results provide the following product composition:

 

Kalia Mineral Resource Estimate Concentrate Potential

Domain

Mass recovery %

Fe%

SiO2%

Al2O3%

P%

S%

BIF

31.86

68.74

3.91

0.14

0.01

0.29

Schist

4.14

63.66

4.34

0.29

0.01

0.17

 

537 Davis Tube Results were completed on the BIF and schist domains to support the JORC estimate, with an ongoing testwork programme in place to further refine the quality and grade versus grind size to ensure the optimum product will be produced from the Kalia Mine.

All assay and metallurgical test work was undertaken by independent laboratories in Perth, Western Australia

 

The Kalia Mine Project has a current total iron ore resource of:

Tonnes 'm

Grade Fe

Product Tonnes 'm

Product Grade Fe

Inferred Oxide JORC Resource

193

38.6%

70.1

58.0%

Inferred SBIF JORC Resource

92.5

36.5%

37*

63.4%*

Measured, Indicated and Inferred BIF JORC Resource

4,630

25.9%

1,475**

68.7%**

Inferred Schist JORC Resource

1,530

9.8%

63.3*

63.7%*

*estimations have been made on preliminary testwork results

** results supported by bulk testwork

 

Nik Zuks, Chief Executive Officer, commented: "I am pleased the target of defining one billion tonnes of measured and indicated BIF JORC resource was achieved as planned. This significant magnetite increase has been established on the back of our oxide JORC programme and further validates the creation of one of Africa's largest iron ore projects.

"The JORC increase supports our own estimate of some 10 billion tonnes of BIF across the Kalia site and the growing demand for the high quality magnetite concentrate in the steel industry, based on better furnace efficiencies and lower greenhouse emissions, underlines the strategic importance of Kalia. We now have JORC resources of more than 1.4 billion tonnes of contained iron and, in addition to the valuable partnership with China International Fund Limited, and the Forecariah JV project being on track for near-term production in Q1 of 2012, the management and operational team are continuing to work efficiently to schedule."

 

 

 

Enquiries:

Bellzone Mining plc

Nik Zuks/Graham Fyfe

+61 (0) 8 9420 8900

Canaccord Genuity Limited

Nominated Adviser and Joint Broker to Bellzone

+44 (0)20 7050 6500

Andrew Chubb/Tarica Mpinga

Renaissance Capital Limited

Joint Broker to Bellzone

+44 (0)20 7367 7777

Jeremy Wrathall

Tavistock (UK)

Jos Simson/Paul Youens

+44 (0)20 7 9203 150 / +44 (0)7899 870 450

PPR (Australia)

 

David Ikin

+61 (0) 8 9388 0944 / +61 (0) 408 438 772

 

CSA Global UK, the independent geologists have established and certified the Company's JORC complaint oxide, Supergene BIF and magnetite resource for Kalia.

 

The mineral resource information disclosed in this announcement has been reviewed by Galen White (MAusIMM), Principal Consultant of CSA Global. Mr White is a member of the Australasian Institute of Mining and Metallurgy and is qualified as a Competent Person in terms of the "Australasian Code for Reporting of Exploration Results, Mineral resources and Ore Reserves (JORC Code 2004 Edition). Mr White has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking, to qualify as a Competent Person for the purposes of this announcement.

 

About Bellzone Mining Plc

 

Bellzone Mining plc is an exploration and resource development company with iron ore and nickel / copper permits in the Republic of Guinea, West Africa.

 

Kalia Mine

The Company's flagship project, the Kalia Mine Project, is planned to commence production in 2014 and be producing iron ore and iron ore concentrate at a rate of 50 million tonnes per annum in 2018. The Kalia Mine Project has a 6.16 billion tonnes magnetite JORC resource and an oxide JORC resource of 193 million tonnes. A Supergene BIF JORC resource of 92.5 million tonnes at 36.5% Fe has been delineated and shows the potential to upgrade to produce 37 million tonnes of 63% Fe material. The oxide and Supergene BIF resources have been established from just 10.5% of the 55km2 of the mapped surface oxides on the Kalia permit. Drilling results and internal estimates indicate that the Kalia Mine Project has the potential to host more than 10 billion tonnes of magnetite and 2 billion tonnes of oxide.

CIF - Project, Financing & Infrastructure Partner

Bellzone has a Definitive Agreement ("Agreement") with China International Fund Limited ("CIF"). The Agreement gives CIF right of first refusal to purchase the Kalia Mine Project's production at market rates and CIF commits to providing Bellzone commercially related funding for the development of the Kalia Mine Project.

The Agreement contains CIF's commitment to fund and build commercially operated rail and port infrastructure that will enable Bellzone to export production from the Kalia Mine Project. The infrastructure is being developed by Kalia Horizon Minerals Pte Limited, an entity that is 90% owned by CIF with Bellzone having a 10% carried interest. The Agreement provides for Bellzone to be the lowest cost user with permanent priority access.

Forécariah JV

Bellzone and CIF also have fully funded a joint venture to undertake the accelerated exploration and development programme at CIF's Forécariah iron permits that lie between 30 and 80 kilometres from the Guinea coast. Production is scheduled to start in Q1 2012 with an initial production rate of 3-4 mtpa of oxide ore, ramping to a rate of 10 mtpa in 2013.

Other activities

Bellzone has completed a mapping and surface sampling programme identifying highly prospective targets at its Sadeka Nickel/Copper Project. A VTEM aerial survey is currently being conducted to further define areas for a targeted drilling programme.

Bellzone has acquired the rights to buy 70% of Compagnie Miniere de L'Ouest Africain SA, incorporated and holding tenements in Mali. The company is undertaking geological studies on the tenements which are prospective for iron ore before making an investment decision.

 

GLOSSARY

"Al2O3"

Aluminium Oxide

"BIF"

banded iron formation

"Fe"

Chemical symbol for Iron

"Indicated Mineral Resource"

as defined in the JORC Code, is that part of a Mineral Resource which has been sampled by drill holes, underground openings or other sampling procedures at locations that are too widely spaced to ensure continuity but close enough to give a reasonable indication of continuity and where geoscientific data are known with a reasonable degree of reliability. An Indicated Mineral Resource will be based on more data and therefore will be more reliable than an Inferred Mineral Resource estimate

"Inferred Mineral Resource"

as defined in the JORC Code, is that part of a Mineral Resource for which the tonnage and grade and mineral content can be estimated with a low level of confidence. It is inferred from the geological evidence and has assumed but not verified geological and/or grade continuity. It is based on information gathered through the appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes which may be limited or of uncertain quality and reliability

"JORC"

Joint Ore Reserve Committee An internationally recognised method of classifying mineral resources

"Magnetite"

An oxide mineral (Fe3O4). The most common ferromagnetic mineral and principal ore

"Measured Mineral Resource"

defined in the JORC Code, as that part of a Measured Mineral Resource for which the resource has been intersected and tested by drill holes, underground openings or other sampling procedures at locations which are spaced closely enough to confirm continuity and where geoscientific data are reliably known. A Measured Mineral Resource estimate will be based on a substantial amount of reliable data

"Mineral Resource"

a concentration or occurrence of material of intrinsic economic interest in or on the earth's crust in such a form that there are reasonable prospects for the eventual economic extraction. The location, quantity, grade, geological characteristics and continuity of a mineral resource are known, estimated or interpreted from specific geological evidence and knowledge. Mineral Resources are sub-divided into Inferred Mineral Resources, Indicated Mineral Resources and Measured Mineral Resources

"Oxide"

ore containing oxides of iron, chiefly haematite, goethite and magnetite

"P"

Chemical symbol for Phosphorous

"Schist"

a group of medium-grade metamorphic rocks, chiefly notable for the preponderance of lamellar minerals. Schist is characteristically foliated, meaning the individual mineral grains split off easily into flakes or slabs

"S"

Chemical symbol for Sulphur

"Supergene BIF"

BIF material that is weathered and more friable with an enriched Fe % compared to BIF in the magnetite resource.

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDKNDPPBKDNCB
Date   Source Headline
13th Dec 20185:42 pmRNSBellzone Mining
13th Dec 20182:58 pmRNSAppointment of Liquidators
3rd Dec 201811:01 amRNSFunding Update and Suspension of trading of shares
3rd Dec 201811:00 amRNSSuspension - Bellzone Mining Plc
15th Nov 20182:45 pmRNSFunding Update
31st Oct 20187:00 amRNSBoard Change
22nd Oct 20183:31 pmRNSCorporate Update
22nd Oct 201810:45 amRNSGeneral Meeting Result
3rd Oct 201811:05 amRNSSecond Price Monitoring Extn
3rd Oct 201811:00 amRNSPrice Monitoring Extension
2nd Oct 20184:01 pmRNSNotice of General Meeting and Investor Update Call
28th Sep 20183:09 pmRNSInterim Results
27th Sep 20184:45 pmRNSCorporate Update
3rd Sep 20188:21 amRNSKalia Mining Convention ratified National Assembly
13th Aug 20187:00 amRNSDirectorate Change
31st Jul 201812:34 pmRNSDirectorate Change and Result of AGM
27th Jul 20181:05 pmRNSTotal Voting Rights
23rd Jul 20181:38 pmRNSShare Awards and Director/PDMR Shareholding
18th Jul 20188:20 amRNSIssue of Equity - Replacement
13th Jul 20187:00 amRNSNotice of AGM and Investor Conference Call
12th Jul 20187:00 amRNSIssue of Equity
11th Jul 20184:41 pmRNSSecond Price Monitoring Extn
11th Jul 20184:35 pmRNSPrice Monitoring Extension
9th Jul 20189:59 amRNSKalia Mining Convention ratified by Parliament
11th Jun 20189:45 amRNSCorporate Update
25th May 20187:00 amRNSResults for the year ended 31 December 2017
8th May 20184:40 pmRNSSecond Price Monitoring Extn
8th May 20184:35 pmRNSPrice Monitoring Extension
2nd May 20181:27 pmRNSTotal Voting Rights
1st May 20187:00 amRNSFerronickel Feasibility Study ? Bulk Sample Update
23rd Apr 20183:43 pmRNSShare Awards and Director/PDMR Shareholding
23rd Mar 201810:45 amRNSAmendment to Loan Availability and Repayment Dates
26th Jan 201811:12 amRNSShare Awards
29th Nov 20177:00 amRNSResults of Placing
23rd Nov 20177:44 amRNSPlacing and appointment of joint broker
9th Nov 201710:08 amRNSMining Convention Update Signed
31st Oct 20174:41 pmRNSSecond Price Monitoring Extn
31st Oct 20174:35 pmRNSPrice Monitoring Extension
6th Oct 20174:35 pmRNSPrice Monitoring Extension
26th Sep 20177:00 amRNSInterim Results
14th Sep 201710:04 amRNSMining Convention Update
18th Aug 20177:19 amRNSAmendment to Hudson Loan Repayment Dates
28th Jul 201711:37 amRNSResult of AGM and Board Change
18th Jul 20177:00 amRNSAmendment to Loan Repayment Date
10th Jul 20174:35 pmRNSPrice Monitoring Extension
10th Jul 20177:00 amRNSNotice of AGM and Board Change
30th Jun 20177:00 amRNSResults For The Year Ended 31 December 2016
8th Jun 20177:00 amRNSCorporate Update
29th Mar 201712:33 pmRNSMining Convention and Funding Update
1st Mar 20177:00 amRNSAppointment of Broker

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.