Forecariah Iron Project Update

2 Sep 2011 07:00

RNS Number : 4750N
Bellzone Mining PLC
02 September 2011
 



 

 

 

 

 

2 September 2011

 

 

 

 

Bellzone Mining plc

("Bellzone" or the "Company")

 

Forécariah JV Progress Update

 

·; Project remains on schedule to achieve production Q1 2012

·; Internal resource estimates on track for September 2011 announcement

·; Port feasibility study completed

·; Contract for port EPCM awarded

·; Haulage truck fleet purchased

·; Mine crush and screen plant purchased

·; Mine earth moving fleet and vehicles purchased

·; Mine haul trucks purchased

·; Mine accommodation village purchased

·; Clearing and grubbing of road to port completed

·; Borrow pits for road base opened and layering to commence in September

 

Bellzone Mining plc (AIM:BZM) is pleased to provide a progress report on the Forécariah JV Project (the "JV") with China International Fund ("CIF") in the Republic of Guinea, West Africa, which remains on schedule to commence production of iron ore in Q1 of 2012.

 

Resource Development

 

As announced on 1 August 2011, Bellzone delineated an initial iron oxide cap volume of 8 million m3 at the Yomboyeli site. Bulk density readings ranging from 2.6t/m3 through 3.9t/m3 have been obtained from the oxide material in this area and first production will target the 2 million m3 of higher tenor material identified within the larger oxide cap.

The initial volume is based on drilling over 1.0km2 of the 2.7km2 of mapped oxide at surface and ongoing exploration and mapping has identified additional prospective targets of oxide and magnetite that are outside the currently mapped 2.7km2 oxide that is under development.

The iron oxide cap in the mapped 2.7km2 area is a product of the Marampa beds. The Marampa beds extend from within Sierra Leone to 8km NNW of Yomboyeli. Of the 8km strike of the prospective Marampa Beds within the JV, only the Yomboyeli and Yaneyah prospects have been subjected to any degree of exploration. Beneath the oxide cap layer, drilling has identified parallel zones of iron schists in the Marampa beds.

Two reverse circulation ("RC") rigs are currently conducting infill drilling of the Yomboyeli ridge. One rig will switch in approximately two weeks to a program extending the oxide package. A third RC drill rig has arrived on site and is being operationally commissioned.

The infill drilling programme through the initial 1km2 target has been completed and assays are being processed in Perth. The programme is on track to provide resource information in September which will allow detailed mine planning and production scheduling to be undertaken in October this year.

Work done on the resource development to date includes:

·; 50 diamond drill ("DD") holes totalling 5,558 metres have been drilled to depths of 250m

·; 1,880 metres in 21 trenches have been completed to map and identify the surface oxide

·; Trench profiles have been completed and initial assay grades have identified additional high grade target areas

·; 68 holes of RC drilling have been completed delivering 7,516m metres

 

Road Development

 

The 76km road route comprises 20km of new road required to bypass small villages, and 56 km of existing road. The existing road upgrade and new road construction to support the bulk ore road trains will being done in five sections that will each be covered under contracts. All sections have had contracts awarded to Guinea based contractors for the grub and clear work which is now complete. Construction contracts for three sections have been awarded to Guinean contractors and the contracts for the remaining two sections are under final negotiation with awarded expected shortly.

The clearing and grubbing activities scheduled during the wet season has been completed. Currently borrow pits and construction preparation is underway with road base layering expected to start in week 2 of September. The road development is on track for completion to allow trucking of ore in February 2012 as per schedule.

The contract to conduct a LiDar study to define the topography for the site and the pathway to the proposed rail connection, to replace the haul road as the rail is commissioned, has been awarded to the global specialist Fugro and is due for completion in Q4 2011.

 

Konta Port Development

 

China Communications and Construction Company ("CCCC") and Second Harbour Consultants Co have completed the port feasibility study. The study has been issued to the Government and work will commence once approval has been received.

Port EPCM contracts have been awarded to CCCC and detailed engineering and procurement activities are in progress.

Approval to start land acquisition and clearance has been submitted to the Government and is expected to commence in September 2011.

The marine fleet required for the trans-shipping operation have been sourced and commercial negotiations have commenced along with vessel marine inspection.

 

Mine and Plant Development

 

The Bellzone and CIF mining team have completed the mining and processing feasibility study and key long lead items have been purchased, which include:

·; The crushing and screening plant

·; The road haulage truck fleet

·; Mining haulage fleet

·; Earthmoving equipment

·; Accommodation camp

·; Drill and blasting equipment

A vessel has been chartered, leaving China in early October, to deliver the purchased equipment and plant to Guinea.

 

Nik Zuks, Chief Executive Officer, commented: "Progress continues at a fast pace with several key long lead items purchased and clearing of the route to port complete ensuring we remain on schedule and on budget. Recent investors who visited the site were able to see what has been achieved since January 2011 and the pace of development continues to increase. 

During my recent discussion with His Excellency, the President of Guinea, Alpha Condé, our commitment to deliver this project in Q1 2012 was well received and supported. There is no doubt of the significance of this project in terms of the development of the iron ore sector in Guinea and the growing importance of West Africa as an iron ore province on the global stage."

 

The mineral resource information disclosed in this announcement has been reviewed by Peter Batten, BAppSc, member of the Australasian Institute Mining and Metallurgy. He has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which is being undertaken, to qualify as a Competent Person for the purposes of this announcement.

 

Enquiries:

Bellzone Mining plc

Nik Zuks/Terry Larkan

+61 (0) 8 9420 8900

Canaccord Genuity Limited

Nominated Adviser and Joint Broker to Bellzone

+44 (0)20 7050 6500

Andrew Chubb/Tarica Mpinga

Renaissance Capital Limited

Joint Broker to Bellzone

+44 (0)20 7367 7777

Jeremy Wrathall

Tavistock (UK)

Jos Simson/Paul Youens

+44 (0)20 7 9203 150 / +44 (0)7899 870 450

PPR (Australia)

 

David Ikin

+61 (0) 8 9388 0944 / +61 (0) 408 438 772

 

About Bellzone Mining Plc

 

Bellzone Mining plc is an exploration and resource development company with iron ore and nickel / copper permits in the Republic of Guinea, West Africa.

 

Kalia Mine

The Company's flagship project, the Kalia Mine Project, is planned to commence production in 2014 and be producing iron ore and iron ore concentrate at a rate of 50 million tonnes per annum in 2018. The Kalia Mine Project has a 3.74 billion tonne JORC resource and an initial oxide JORC resource producing 43 million tonnes of 58% product from just 4.2% of the 55km2 of the mapped surface oxides on the Kalia permit. Drilling results and internal estimates indicate that the Kalia Mine Project has the potential to host more than 10 billion tonne of magnetite and 2 billion tonne of oxide.

CIF - Project, Financing & Infrastructure Partner

Bellzone has a Definitive Agreement ("Agreement") with China International Fund Limited ("CIF"). The Agreement gives CIF right of first refusal to purchase the Kalia Mine Project's production at market rates and CIF commits to providing Bellzone commercially related funding for the development of the Kalia Mine Project.

The Agreement contains CIF's commitment to fund and build commercially operated rail and port infrastructure that will enable Bellzone to export production from the Kalia Mine Project. The infrastructure is being developed by Kalia Horizon Minerals Pte Limited, an entity that is 90% owned by CIF with Bellzone having a 10% carried interest. The Agreement provides for Bellzone to be the lowest cost user with permanent priority access.

Forécariah JV

Bellzone and CIF also have fully funded a joint venture to undertake the accelerated exploration and development programme at CIF's Forécariah iron permits that lie between 30 and 80 kilometres from the Guinea coast. Production is scheduled to start in Q1 2012 with an initial production rate of 3-4 mtpa of oxide ore, ramping to a rate of 10 mtpa in 2013.

Other activities

Bellzone has completed a mapping and surface sampling programme identifying highly prospective targets at its Sadeka Nickel/Copper Project. A VTEM aerial survey is currently being conducted to further define areas for a targeted drilling programme.

Bellzone has acquired the rights to buy 70% of Compagnie Miniere de L'Ouest Africain SA, incorporated and holding tenements in Mali. The company is undertaking geological studies on the tenements which are prospective for iron ore before making an investment decision.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEALNFEFXFEFF
Date   Source Headline
13th Dec 20185:42 pmRNSBellzone Mining
13th Dec 20182:58 pmRNSAppointment of Liquidators
3rd Dec 201811:01 amRNSFunding Update and Suspension of trading of shares
3rd Dec 201811:00 amRNSSuspension - Bellzone Mining Plc
15th Nov 20182:45 pmRNSFunding Update
31st Oct 20187:00 amRNSBoard Change
22nd Oct 20183:31 pmRNSCorporate Update
22nd Oct 201810:45 amRNSGeneral Meeting Result
3rd Oct 201811:05 amRNSSecond Price Monitoring Extn
3rd Oct 201811:00 amRNSPrice Monitoring Extension
2nd Oct 20184:01 pmRNSNotice of General Meeting and Investor Update Call
28th Sep 20183:09 pmRNSInterim Results
27th Sep 20184:45 pmRNSCorporate Update
3rd Sep 20188:21 amRNSKalia Mining Convention ratified National Assembly
13th Aug 20187:00 amRNSDirectorate Change
31st Jul 201812:34 pmRNSDirectorate Change and Result of AGM
27th Jul 20181:05 pmRNSTotal Voting Rights
23rd Jul 20181:38 pmRNSShare Awards and Director/PDMR Shareholding
18th Jul 20188:20 amRNSIssue of Equity - Replacement
13th Jul 20187:00 amRNSNotice of AGM and Investor Conference Call
12th Jul 20187:00 amRNSIssue of Equity
11th Jul 20184:41 pmRNSSecond Price Monitoring Extn
11th Jul 20184:35 pmRNSPrice Monitoring Extension
9th Jul 20189:59 amRNSKalia Mining Convention ratified by Parliament
11th Jun 20189:45 amRNSCorporate Update
25th May 20187:00 amRNSResults for the year ended 31 December 2017
8th May 20184:40 pmRNSSecond Price Monitoring Extn
8th May 20184:35 pmRNSPrice Monitoring Extension
2nd May 20181:27 pmRNSTotal Voting Rights
1st May 20187:00 amRNSFerronickel Feasibility Study ? Bulk Sample Update
23rd Apr 20183:43 pmRNSShare Awards and Director/PDMR Shareholding
23rd Mar 201810:45 amRNSAmendment to Loan Availability and Repayment Dates
26th Jan 201811:12 amRNSShare Awards
29th Nov 20177:00 amRNSResults of Placing
23rd Nov 20177:44 amRNSPlacing and appointment of joint broker
9th Nov 201710:08 amRNSMining Convention Update Signed
31st Oct 20174:41 pmRNSSecond Price Monitoring Extn
31st Oct 20174:35 pmRNSPrice Monitoring Extension
6th Oct 20174:35 pmRNSPrice Monitoring Extension
26th Sep 20177:00 amRNSInterim Results
14th Sep 201710:04 amRNSMining Convention Update
18th Aug 20177:19 amRNSAmendment to Hudson Loan Repayment Dates
28th Jul 201711:37 amRNSResult of AGM and Board Change
18th Jul 20177:00 amRNSAmendment to Loan Repayment Date
10th Jul 20174:35 pmRNSPrice Monitoring Extension
10th Jul 20177:00 amRNSNotice of AGM and Board Change
30th Jun 20177:00 amRNSResults For The Year Ended 31 December 2016
8th Jun 20177:00 amRNSCorporate Update
29th Mar 201712:33 pmRNSMining Convention and Funding Update
1st Mar 20177:00 amRNSAppointment of Broker

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.