The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAtalaya Mining Regulatory News (ATYM)

Share Price Information for Atalaya Mining (ATYM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 430.50
Bid: 430.50
Ask: 432.50
Change: 0.00 (0.00%)
Spread: 2.00 (0.465%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 430.50
ATYM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

3rd Quarter Operations Update

12 Oct 2017 07:00

RNS Number : 3752T
Atalaya Mining PLC
12 October 2017
 

12 October 2017

Atalaya Mining Plc

("Atalaya" or the "Company")

Third Quarter 2017 Operations Update

 

Atalaya Mining plc (AIM:ATYM, TSX:AYM) is pleased to announce its operations update for the three months ended September 30, 2017.

 

PROYECTO RIOTINTO

 

Third Quarter

Second Quarter

Full year forecast

2017

2016

2017

2017

Ore mined

(M tonnes)

2.4

2.5

2.3

9.0 - 9.2

Waste mined

(M tonnes)

5.2

3.6

4.6

18.1 - 18.2

Ore milled

(M tonnes)

2.2

2.0

2.2

8.7 - 9.0

Cu grade

(%)

0.58

0.52

0.49

0.49 - 0.51

Cu recovery

(%)

85.95

83.60

85.09

82 - 84

Cu production

(tonnes)

10,679

8,752

9,058

36,000 - 39,000

 

Copper production at Proyecto Riotinto has increased almost 18 % to record production levels versus Q2. All other parameters were well above targets for the quarter ended September 30, 2017. The operation reported an average copper head grade of 0.58%, a throughput rate of 2.2 million tonnes of ore processed and a recovery rate of 85.95 %. Record production of 10,679 tonnes of copper contained in concentrate is the result of higher copper head grade and recovery rates than initially anticipated. Guidance for copper production has been adjusted accordingly and is now estimated to be within the range of 36,000 - 39,000 tonnes.

 

Mining operations are running at a consistent rate quarter-on-quarter, as a result of improved operational efficiencies and the availability of additional mining fleet. On a combined basis, ore, waste and marginal ore amounted to 2.7 Mm3 in Q3 2017 versus 2.8 Mm3 in Q2 2017. As part of the mining fleet replacement programme three new excavators and eight new trucks have been delivered, assembled and commissioned during the quarter. The processing plant was down for maintenance during the last five days of the quarter when relining of the primary mill and other maintenance activities were completed.

 

At the end of the quarter, the Company´s continuous improvement programme reported completion and commissioning of a new 300 m3 primary rougher flotation cell. Installation of plastic lining of one of the paddocks at the tailings storage facilities is also nearing completion and new initiatives designed to improve process and fresh water supply are currently under evaluation.

 

Dust mitigation measures have been successful over the summer months with indicators significantly reduced and within legal requirements. Installation of a dome covering the coarse ore stockpile is ongoing with civil foundations reaching advanced stages. Dewatering of the Cerro Colorado pit is now complete and will now be limited to pumping runoff water as required. Relocation of pumping stations from the Cerro Colorado pit to the Atalaya pit was completed with dewatering activities now underway.

 

On-site concentrate inventories at the end of the quarter were approximately 2,000 tonnes. All concentrate in stock at the beginning of the quarter and produced during the quarter was delivered to the port at Huelva.

 

Copper prices rose during the quarter with an average realised price per pound of copper payable of $2.66/lb compared with $2.18/lb in Q3 2016 and $2.61/lb in Q2 2017. The average spot copper price during the quarter was $2.88/lb.

 

Management expects All-in sustaining costs ("AISC") for the year to be maintained in the range of $1.95/lb to $2.10/lb. The increase from the original estimate is mainly due to different capitalisation criteria applicable to mining stripping costs.

 

Near-mine exploration drilling has turned its focus on to the north-west extension of the Cerro Colorado pit now that the east-west extension of Filon Sur has been completed. The exploration block model has been updated with results which will be part of the resources and reserves update that form part of the studies related to the expansion to 15 Mtpa Project.

 

Exploration has initiated during the quarter an airborne VTEM geophysical survey to help further understand deep geological structures in the mining and exploration concessions of the Company.

 

The archaeological programmed initiated in the previous quarter as part of the Company's Corporate Social Responsibility programme is expected to reach an important milestone at the end of the year when the first archaeological level will be fully documented.

 

PROYECTO TOURO

 

The permitting of Proyecto Touro is progressing according to schedule with the public hearing having taken place at the beginning of October. The Company anticipates a period of consultation with different regulatory bodies which should take place over the following months.

 

The technical report is progressing ahead of schedule with all efforts now concentrated on getting the report completed and ready for release during the Q4 2017. The technical report is confirmed to be at pre-feasibility level of detail and in compliance with NI 43-101 guidelines.

 

An exploration campaign was initiated during the quarter over the newly optioned exploration concessions around Proyecto Touro. The campaign includes an airborne VTEM geophysical survey, detailed assessment of structural geology and a regional geochemical campaign.

 

Alberto Lavandeira, CEO commented:

"The continuing improvement in performance at Proyecto Riotinto is very gratifying and gives us confidence that our annual production will be at the upper end of the guidance range.

Touro progresses on schedule and we look forward to sharing further details in due course."

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

 

 

Contacts:

Newgate Communications

Charles Chichester / James Ash / James Browne

+44 20 7680 6550

Canaccord Genuity (NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / Martin Davison / James Asensio

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch/Neil Haycock/Tom Rider

+44 20 7236 1010

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLDMMMGNMRGNZM
Date   Source Headline
20th Jun 20138:20 amRNSExercise of Options
18th Jun 201311:04 amRNSExercise of Options - Correction
18th Jun 20138:00 amRNSExercise of Options
13th Jun 201310:48 amRNSAGM Statement
13th Jun 201310:47 amRNSResult of AGM
13th Jun 20138:51 amRNSFunding Update
3rd Jun 20137:00 amRNSPermitting Update
30th May 20137:00 amRNSInvestor Briefing
23rd May 20137:00 amRNSPermitting Update
17th May 20133:00 pmRNSNotice of AGM
14th May 20133:03 pmRNSQuarterly Financial Report
23rd Apr 20137:00 amRNSEMED Mining at Master Investor
17th Apr 20137:00 amRNSQuarterly Operational Update
16th Apr 20137:00 amRNSTailings Project Update
15th Apr 20137:00 amRNSPermitting Update
4th Apr 201310:59 amRNSExercise of Options
2nd Apr 20137:00 amRNSExposure to Cyprus Bank Restructuring
25th Mar 20135:47 pmRNSAmendment of Option Agreements
25th Mar 20137:00 amRNSFinal Results
21st Mar 20133:38 pmRNSRio Tinto Copper Project Update
18th Mar 20131:05 pmRNSProposed Levy on Deposits in Cyprus
18th Feb 20137:30 amRNSEMED Mining completed an updated Technical Report
16th Jan 20137:00 amRNSQUARTERLY OPERATIONAL UPDATE
9th Jan 20137:00 amRNSShareholder Briefing
19th Dec 20129:27 amRNSResult of GM and Rio Tinto Project Update
11th Dec 20127:00 amRNSInvestor Briefing
28th Nov 201210:00 amRNSDespatch of Circular and EGM
22nd Nov 20122:00 pmRNSApproval of Interim Mining Lease Area in Slovakia
15th Nov 201210:21 amRNSRio Tinto Site Visit
14th Nov 20123:00 pmRNSQuarterly Financial Results
14th Nov 20127:00 amRNSEMED Arranges a US$50 Million Funding Package
18th Oct 20127:00 amRNSUpdate of Progress at Rio Tinto Copper Project
2nd Oct 20124:35 pmRNSReceipt of AAU public comments report
1st Oct 20127:00 amRNSAppointment of Non-Executive Director
27th Sep 20129:10 amRNSQUARTERLY OPERATIONAL UPDATE
19th Sep 20127:00 amRNSSlovakia Update
4th Sep 20127:00 amRNSEMED Mining progresses towards production
31st Aug 20121:00 pmRNSCompletion of acquisitions of remaining land
20th Aug 20121:30 pmRNSCompletion of US$5m Equity Subscription by XGC
7th Aug 20127:00 amRNS2012 Interim Results
3rd Aug 20127:00 amRNSLand Acquisition
16th Jul 20127:00 amRNSEMED MINING QUARTERLY OPERATIONAL UPDATE
9th Jul 20127:00 amRNSAgreement With Owner of Lands
26th Jun 20127:00 amRNSInvestor Briefing
21st Jun 20121:30 pmRNSIssue of equity following warrant exercise
18th Jun 20127:00 amRNSInvestors Briefing Update
13th Jun 20121:31 pmRNSResult of AGM
13th Jun 20121:30 pmRNSAGM Statement
18th May 201212:30 pmRNSNotice of AGM
14th May 20127:00 amRNSEMED Mining Quarterly Financial Report

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.