Roundtable Discussion; The Future of Mineral Sands. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAntofagasta Regulatory News (ANTO)

Share Price Information for Antofagasta (ANTO)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 2,192.00
Bid: 2,189.00
Ask: 2,192.00
Change: 60.00 (2.81%)
Spread: 3.00 (0.137%)
Open: 2,140.00
High: 2,195.00
Low: 2,118.00
Prev. Close: 2,132.00
ANTO Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Q1 2018 Production Report

25 Apr 2018 07:00

RNS Number : 0037M
Antofagasta PLC
25 April 2018
 

NEWS RELEASE, 25 APRIL 2018

Q1 2018 PRODUCTION REPORT

 

Antofagasta plc CEO, Iván Arriagada said: "As planned and in line with budget the year has started with lower grades at our operations. During the quarter, we have also successfully concluded the labour negotiations at Los Pelambres.

"First quarter copper production was 153,800 tonnes and will increase quarter-on-quarter as grades improve during the year and into 2019. For the full year our production guidance is unchanged at 705-740,000 tonnes.

"Net cash costs were $1.54/lb, reflecting the lower grades experienced in the quarter and a stronger Chilean Peso, but with grades increasing during the year and improved by-product performance, costs will reduce and so guidance for the full year is unchanged at $1.35/lb."

 

HIGHLIGHTS

PRODUCTION

· As expected, copper production in Q1 2018 decreased by 10.5% to 153,800 tonnes compared with the same quarter in 2017 mainly due to the anticipated lower grades

· Gold production was 32,300 ounces in Q1 2018, 39.4% lower than in Q1 2017 and 20.4% lower than in the previous quarter as grades were down at Centinela

· Molybdenum production increased by 40.9% compared to the same period in 2017 due to better grades and recoveries

 

CASH COSTS

· Cash costs before by-product credits in the quarter increased to $2.00/lb from $1.59 /lb in the same period of last year primarily because of lower production and a stronger Chilean Peso

· Net cash costs were $1.54/lb in Q1 2018, compared to $1.27 /lb in Q1 2017 and $1.36 /lb in the previous quarter, reflecting the changes in cash costs before by-product credits, partially offset by higher by-product credits arising from higher molybdenum production and a significant increase in the realised molybdenum price

GUIDANCE

· Guidance for the year is unchanged. Group copper production for the full year is expected to be 705-740,000 tonnes, with production increasing quarter-by-quarter during the year as grades improve at the operations to achieve guided grades for the full year

· Net cash costs guidance of $1.35/lb is also unchanged, assuming no further strengthening in the Chilean Peso during the balance of the year

OTHER

· In February this year, Los Pelambres successfully completed labour negotiations with the plant union and in March with the mine union. The one-off signing bonuses related to these three-year agreements increased Los Pelambres' cash costs by 8c/lb and Group cash costs by 4c/lb for the quarter, equivalent to 2c/lb and 1c/lb on an annual basis. These negotiation's conclude the Group's scheduled negotiations for the year

GROUP PRODUCTION AND CASH COSTS

Year to Date

Q1

Q4

 

 

 

2018

2017

%

2018

2017

%

Copper production

kt

153.8

171.9

(10.5)

153.8

177.8

(13.5)

Copper sales

kt

136.8

175.7

(22.1)

136.8

186.6

(26.7)

Gold production

koz

32.3

53.3

(39.4)

32.3

40.5

(20.2)

Molybdenum production

kt

3.1

2.2

40.9

3.1

3.3

(6.1)

Cash costs before by-product credits (1)

$/lb

2.00

1.59

25.8

2.00

1.69

18.3

Net cash costs (1)

$/lb

1.54

1.27

21.3

1.54

1.36

13.2

(1) Cash cost is a non-GAAP measure used by the mining industry to express the cost of production in US dollars per pound of copper produced.

 

Investors - London Media - London

Andrew Lindsay alindsay@antofagasta.co.uk Carole Cable antofagasta@brunswickgroup.com

Telephone +44 20 7808 0983 Telephone +44 20 7404 5959

Andres Vergara avergara@antofagasta.co.uk Will Medvei antofagasta@brunswickgroup.com

Telephone +44 20 7808 0988 Telephone +44 20 7404 5959

 

Investors - Santiago Media - Santiago

Francisco Veloso fveloso@aminerals.cl Pablo Orozco porozco@aminerals.cl

Telephone +56 2 2798 7000 Carolina Pica cpica@aminerals.cl

Telephone +56 2 2798 7000

 

MINING OPERATIONS

Los Pelambres

Los Pelambres produced 81,100 tonnes of copper in Q1 2018, 2.1% lower than in the same quarter last year, as grades fell to 0.64% as expected.

Compared with Q1 2017 molybdenum production rose 40.9% to 3,100 tonnes in Q1 2018, primarily due to higher grades and recoveries.

Gold production for the quarter was 14,900 ounces, 8.0% higher than the same period last year.

Cash costs before by-product credits in Q1 2018 were $1.72/lb, compared with $1.41/lb in Q1 2017. This increase in costs was primarily due to the lower grade, a stronger Chilean Peso and the payment of one-off bonuses related to the completion of labour agreements signed with the plant and mine unions.

Despite the higher cash costs before by-product credits, net cash costs in Q1 2018 were $0.99/lb, 4.8% lower than in the same quarter last year, as by-product credits increased from $0.37/lb to $0.73/lb on significantly higher molybdenum production and prices.

 

LOS PELAMBRES

Year to Date

Q1

Q4

 

 

 

2018

2017

%

2018

2017

%

Daily ore throughput

kt

165.2

160.9

2.7

165.2

168.5

(2.0)

Copper grade

%

0.64

0.68

(5.9)

0.64

0.69

(7.2)

Copper recovery

%

88.1

87.7

0.5

88.1

88.9

(0.9)

Copper production

kt

81.1

82.8

(2.1)

81.1

92.8

(12.6)

Copper sales

kt

73.2

82.7

(11.5)

73.2

99.2

(26.2)

Molybdenum grade

%

0.025

0.020

25.0

0.025

0.027

(7.4)

Molybdenum recovery

%

83.8

74.3

12.8

83.8

81.3

3.0

Molybdenum production

kt

3.1

2.2

40.9

3.1

3.3

(6.1)

Molybdenum sales

kt

2.9

2.1

38.1

2.9

2.4

20.8

Gold production

koz

14.9

13.8

8.0

14.9

15.3

(2.6)

Gold sales

koz

12.7

13.6

(6.6)

12.7

15.9

(20.1)

Cash costs before by-product credits (1)

$/lb

1.72

1.41

22.0

1.72

1.38

24.6

Net cash costs (1)

$/lb

0.99

1.04

(4.8)

0.99

0.92

7.6

(1) Includes tolling charges of $0.27/lb in Q1 2018, $0.26/lb in Q4 2017, and $0.28/lb in Q1 2017

 

Centinela

Total copper production at Centinela was 47,300 tonnes in Q1 2018, 14.8% lower than in the same quarter in 2017, primarily due to lower copper in concentrate production, which was partially offset by higher cathode production.

Copper in concentrate production was 25,300 tonnes in Q1 2018, 35.1% lower than in Q1 2017, primarily due to an anticipated fall in grades from 0.59% to 0.43%.

Production of copper in concentrates fell 16.2% against Q4 2017, again primarily due to falling grades and lower throughput, which was impacted by scheduled major maintenance during the quarter. The next major maintenance for the concentrator will be in September and is factored into guidance for the year.

Despite lower grades cathode production in Q1 2018 was 22,000 tonnes, 33.3% higher than in Q1 2017 as Encuentro Oxides ramps up to full production.

Gold production was 17,400 ounces in Q1 2018, 55.9% lower than in the same period due to significantly lower gold grades which followed changes in copper grades. Grades in the quarter were down to 0.12 g/t compared with 0.23 g/t in the same period last year.

Cash costs before by-product credits at $2.43/lb in Q1 2018 were higher than in the same quarter in 2017 due to the decrease in production, stronger local currency and additional costs associated with Encuentro Oxides during its ramp-up to full production which is expected to be completed by the end of Q2 2018.

Net cash costs were impacted by lower by-product credits compared to both Q1 2017 and Q4 2017 as the gold grade decreased significantly.

 

CENTINELA

Year to Date

Q1

Q4

 

 

 

2018

2017

%

2018

2017

%

CONCENTRATES

 

 

 

 

 

 

 

Daily ore throughput

kt

88.1

89.2

(1.2)

88.1

91.6

(3.8)

Copper grade

%

0.43

0.59

(27.1)

0.43

0.47

(8.5)

Copper recovery

%

81.4

84.8

(4.0)

81.4

79.2

2.8

Copper production

kt

25.3

39.0

(35.1)

25.3

30.2

(16.2)

Copper sales

kt

16.9

43.9

(61.5)

16.9

31.1

(45.7)

Gold grade

g/t

0.12

0.23

(47.8)

0.12

0.15

(20.0)

Gold recovery

%

64.6

70.8

(8.8)

64.6

62.3

3.7

Gold production

koz

17.4

39.5

(55.9)

17.4

25.2

(31.0)

Gold sales

koz

11.0

45.6

(75.9)

11.0

24.6

(55.3)

CATHODES

 

 

 

 

 

 

 

Daily ore throughput

kt

37.6

24.5

53.5

37.6

41.5

(9.4)

Copper grade

%

0.77

0.94

(18.1)

0.77

0.96

(19.8)

Copper recovery

%

73.8

74.5

(0.9)

73.8

61.1

20.8

Copper production - heap leach

kt

20.5

14.9

37.6

20.5

20.2

1.5

Copper production - total (1)

kt

22.0

16.5

33.3

22.0

20.8

5.8

Copper sales

kt

21.1

16.0

31.9

21.1

18.3

15.3

Total copper production

kt

47.3

55.5

(14.8)

47.3

51.0

(7.3)

Cash costs before by-products (2)

$/lb

2.43

1.79

35.8

2.43

2.28

6.6

Net cash costs (2)

$/lb

2.18

1.33

63.9

2.18

1.96

11.2

(1) Includes production from ROM material

(2) Includes tolling charges of $0.16/lb in Q1 2018, $0.18/lb in Q4 2017, and $0.20/lb in Q1 2017

 

Antucoya

Antucoya produced 14,600 tonnes of copper in Q1 2018, 28.1% lower than the same quarter last year. Production was impacted by lower throughput due to scheduled maintenance and unplanned downtime due to an earlier conveyor failure, which has now been repaired, and lower grades and recoveries.

During the quarter, the cash costs were $2.29/lb compared to $1.75/lb in Q1 2017. This was due to lower production during the period, a stronger Chilean Peso and increased acid costs.

ANTUCOYA

Year to Date

Q1

Q4

 

 

 

2018

2017

%

2018

2017

%

Daily ore throughput

kt

63.7

75.9

(16.1)

63.7

84.2

(24.3)

Copper grade

%

0.34

0.39

(12.8)

0.34

0.37

(8.1)

Copper recovery

%

70.1

76.0

(7.8)

70.1

73.1

(4.1)

Copper production

kt

14.6

20.3

(28.1)

14.6

21.1

(30.8)

Copper sales

kt

14.9

20.2

(26.2)

14.9

23.3

(36.1)

Cash costs

$/lb

2.29

1.75

30.9

2.29

1.64

39.6

 

Zaldívar

Copper production at Zaldívar was 10,800 tonnes in Q1 2018, an 18.8% decrease compared with the same period last year on the expected lower grades. Throughput was also impacted by unplanned stoppages of equipment largely related to the stacker reclaimer system whose replacement will be fully completed as planned in Q2 2018 with equipment acquired last year.

Cash costs at $1.86/lb in Q1 2018 rose by 13.4% compared to Q1 2017 primarily due to lower production, stronger local currency and higher acid prices.

ZALDÍVAR

Year to Date

Q1

Q4

 

 

 

2018

2017

%

2018

2017

%

Daily ore throughput

kt

30.8

42.2

(27.0)

30.8

45.3

(32.0)

Copper grade

%

0.70

0.86

(18.6)

0.70

0.68

2.9

Copper recovery (1)

%

62.3

64.5

(3.4)

62.3

60.8

2.5

Copper production - heap leach (2)

kt

8.3

10.1

(17.8)

8.3

10.1

(17.8)

Copper production - total (2,3)

kt

10.8

13.3

(18.8)

10.8

12.9

(16.3)

Copper sales (2)

kt

10.7

12.9

(17.1)

10.7

14.6

(26.7)

Cash costs

$/lb

1.86

1.64

13.4

1.86

1.70

9.4

(1) Average over full leach cycle

(2) Group's 50% share

(3) Includes production from secondary leaching

 

Transport

The division transported 1.5 million tonnes of freight in Q1 2018, 3.5% higher than in the same period last year when there was a strike at one of the division's customers. Compared to the previous quarter, tonnage transported was 10.1% lower as a customer reduced its acid haulage requirement.

TRANSPORT

Year to Date

Q1

Q4

 

 

 

2018

2017

%

2018

2017

%

Rail

kt

1,217

1,145

6.3

1,217

1,313

(7.3)

Road

kt

257

279

(7.9)

257

327

(21.4)

Total tonnage transported

kt

1,474

1,424

3.5

1,474

1,640

(10.1)

 

Commodity prices and exchange rates

 

Year to Date

Q1

Q4

 

 

 

2018

2017

%

2018

2017

%

Copper

 

 

 

 

 

 

 

Market price

$/lb

3.16

2.65

19.3

3.16

3.09

2.2

Realised price

$/lb

2.86

2.82

1.2

2.86

3.41

(16.4)

Gold

 

 

 

 

 

 

 

Market price

$/oz

1,330

1,219

9.1

1,330

1,276

4.2

Realised price

$/oz

1,348

1,277

5.6

1,348

1,280

5.3

Molybdenum

 

 

 

 

 

 

 

Market price

$/lb

12.2

7.8

56.6

12.2

8.8

39.3

Realised price

$/lb

14.9

8.2

81.1

14.9

8.8

69.6

Exchange rates

 

 

 

 

 

 

 

Chilean peso

per $

602

655

(8.1)

602

633

(5.0)

 

The spot commodity prices for copper, gold and molybdenum as at 31 March 2018 were $3.03/lb, $1,325/oz and $11.3/lb respectively this compares with $3.27/lb, $1,303/oz and $7.1/lb as at 31 December 2017, and $2.64/lb, $1,249/oz and $6.76/lb as at 31 March 2017.

The provisional pricing adjustments for the quarter were negative $85.9 million for copper, negative $0.04 million for gold and positive $20.7 million for molybdenum.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLFKQDDCBKDFQB
Date   Source Headline
1st Jun 20187:00 amRNSREPORT ON PAYMENTS TO GOVERNMENTS
31st May 20187:00 amRNSDirector Declaration
23rd May 20184:15 pmRNSResults of Annual General Meeting
23rd May 201810:26 amRNSCHAIRMAN'S COMMENTS AT THE 2018 AGM
8th May 20187:00 amRNSLos Pelambres Update
4th May 201810:58 amRNSFinal Dividend Payable
30th Apr 201810:41 amRNSDirector Declaration
25th Apr 20182:18 pmRNSDirector Declaration
25th Apr 20187:00 amRNSQ1 2018 Production Report
16th Apr 201812:34 pmRNSPublication of 2017 Annual Report & Notice of AGM
3rd Apr 201811:24 amRNSNotification of Management Transactions
27th Mar 201811:33 amRNSNotification of Management Transactions
13th Mar 20187:00 amRNSPRELIMINARY RESULTS ANNOUNCEMENT YEAR ENDED 2017
24th Jan 20187:00 amRNSQ4 2017 PRODUCTION REPORT
25th Oct 20177:00 amRNSQ3 2017 PRODUCTION REPORT
14th Sep 20173:30 pmRNSInterim Dividend Payable
22nd Aug 20177:00 amRNSHALF YEARLY FINANCIAL REPORT JUNE 2017
9th Aug 201710:16 amRNSAntofagasta Half Year 2017 Results - Webcast
26th Jul 20177:00 amRNSQ2 2017 PRODUCTION REPORT
23rd Jun 20177:00 amRNSREPORT ON PAYMENTS TO GOVERNMENTS
24th May 20173:26 pmRNSResults of Annual General Meeting
24th May 20177:00 amRNSCHAIRMAN'S COMMENTS AT THE 2017 AGM
8th May 201710:56 amRNSFINAL DIVIDEND PAYABLE
26th Apr 20177:00 amRNSQ1 2017 PRODUCTION REPORT
11th Apr 20177:00 amRNSPUBLICATION OF 2016 ANNUAL REPORT & NOTICE OF AGM
3rd Apr 201710:00 amRNSNOTIFICATION OF TRANSACTIONS
21st Mar 201711:00 amRNSREKO DIQ PROJECT - Arbitration Ruling
14th Mar 20177:00 amRNSPRELIMINARY RESULTS FOR THE YEAR ENDED 2016
2nd Mar 20177:00 amRNSAntofagasta Preliminary Results
25th Jan 20177:00 amRNSQ4 2016 PRODUCTION REPORT
20th Jan 20177:00 amRNSALTO MAIPO PROJECT
16th Dec 201611:11 amRNSTWIN METALS MINNESOTA MINING LEASES
15th Dec 201612:03 pmRNSDirector Declaration
5th Dec 20168:16 amRNSINVESTOR AND ANALYST SITE VISIT
30th Nov 20167:00 amRNSCHANGES TO BOARD COMMITTEES
28th Nov 20167:00 amRNSSALE OF MICHILLA
28th Oct 20165:05 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
26th Oct 20163:16 pmRNSBOARD CHANGES
26th Oct 20167:00 amRNSQ3 2016 PRODUCTION REPORT
21st Oct 20161:00 pmRNSTR-1: Notification of major interest in shares
16th Sep 20169:57 amRNSINTERIM DIVIDEND PAYABLE
16th Aug 20167:00 amRNSHALF YEARLY FINANCIAL REPORT
15th Aug 20167:00 amRNSDirectorate Change
27th Jul 20167:00 amRNSQ2 2016 PRODUCTION REPORT
23rd Jun 20167:00 amRNSReport on Payments to Governments
18th May 20161:45 pmRNSResults of Annual General Meeting
18th May 20167:00 amRNSCHAIRMAN'S COMMENTS AT THE 2016 AGM
3rd May 20161:04 pmRNSDIRECTOR DECLARATION
27th Apr 20167:00 amRNSQ1 2016 PRODUCTION REPORT
8th Apr 201612:00 pmRNSAppointment of New CEO

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.