Arckaringa Project BFS Work Programme Update

7 Feb 2011 07:00

RNS Number : 7553A
Altona Energy PLC
07 February 2011
 



Altona Energy Plc / Index: AIM / Epic: ANR / Sector: Exploration & Production

7 February 2011

Altona Energy Plc ('Altona' or 'the Company')

Arckaringa Project BFS Work Programme Update

 

Altona Energy Plc, the AIM listed Australian based energy company, is pleased to provide a positive update on progress at the Arckaringa Coal-to-Liquids ('CTL') Project in South Australia. This update specifically concerns the Bankable Feasibility Study ('BFS') and the implementation of a work programme aimed at evaluating the conversion opportunities for the estimated 7.8 billion tonne Arckaringa coal resource, of which 1.287 billion tonnes are currently JORC complaint. 

 

Overview

 

·; Appointment of General Prospecting Institute of the China National Administration for Coal Geology ('CNACG') to advance technical studies as part of BFS work programme for the Arckaringa Project - studies well underway and on schedule

·; Recent site visit attended by all parties including Altona, CNOOC-NEIA and CNACG

·; Checking and confirmation of data parameters completed for the existing geological database and the physical conditions governing the location of the Wintinna Coal Mine and supporting infrastructure

·; Preparing documentation to gain an Exploration Work Approval and to select local drilling and hydro-geological companies for field programmes

·; Aiming to design field drilling programmes to provide the detailed information needed for mine design and the groundwater management programme by April 2011

 

Altona's Managing Director, Chris Schrape, said, "It was exciting to join with our JV partner and technical consultants on the ground in South Australia as we collaborate in taking significant steps in advancing our BFS work programme. The work now in progress will build a solid platform for the detailed evaluation of the mining aspects at Arckaringa and is consistent with the structured approach required for a BFS on a large scale clean coal conversion project with a base case capacity of 15 mtpa."

 

CNACG has been appointed to advance technical studies as part of the BFS work programme for the Arckaringa Project. CNACG commenced work in the fourth quarter of 2010 under a contract approved by Altona and its Joint Venture partner CNOOC-NEIA, the Australian subsidiary of CNOOC, one of China's major oil companies. Consequently, the first three of the [previously announced] studies listed below are well underway:

 

·; Detailed review of coal deposit geology and consideration of supplemental drilling;

·; Groundwater investigation and verification;

·; Groundwater management research and design;

·; Environmental baseline studies;

·; Open cut coal mining methodology options; and

·; Product market research.

 

A technical team from CNACG visited South Australia from 19-27 January 2011. During this time they held a series of technical data review sessions with the JV Operating Team and met local hydrogeological and other consultants, including those employed during the Altona Pre Feasibility Study ('PFS') work. The team also visited the site and confirmed the parameters for the existing geological database and the physical conditions governing the location of the Wintinna mine and supporting infrastructure, including the transport corridor options to link into the nearby national rail and road network.

 

To date, CNACG has reviewed and consolidated all original technical data concerning the Wintinna deposit, including Altona's PFS work and historical data. CNACG is now focussed on a Geological Report on licence EL4512 to assist the development of the long term plan for the Wintinna Coal Mine, which it aims to complete during March 2011. It also aims to complete comprehensive geological and hydro-geological research reports to underpin the design of the field drilling programmes that will provide the detailed information needed for mine design and the groundwater management programme by April 2011.

 

In anticipation of the completion of the CNACG reports, the JV partners are preparing documentation to gain the required Exploration Work Approval ('EWA') from the South Australian Government and to select the local drilling and hydro-geological companies for the field programmes, which are scheduled to commence in mid 2011. Further details on the field programmes, including their scope and duration, will be announced when the EWA is in place.

**ENDS**

 

Christopher Lambert

Altona Chairman

Tel: +44 (0) 20 7024 8391

Christopher Schrape

Altona Managing Director

Tel: +44 (0) 20 7024 8391

Simon Edwards

Evolution Securities Ltd

Tel: +44 (0) 20 7071 4300

Tim Redfern

Evolution Securities Ltd

Tel: +44 (0) 20 7071 4300

Elisabeth Cowell

St Brides Media & Finance Ltd

Tel: +44 (0) 20 7236 1177

Hugo de Salis

St Brides Media & Finance Ltd

Tel: +44 (0) 20 7236 1177

 

Notes

Altona Energy Plc is an AIM listed Australian based energy company. Its asset is an estimated 7.8 billion tonne coal resource (non-JORC) in the Arckaringa Basin of South Australia (JORC-compliant: 1.287 billion tonnes). This is considered by the Board to be one of the world's largest untapped energy banks. Per Jacobs Engineering's study for the Company, assuming a 50% conversion of CTL fuels and 50% to synthetic gas ('Syngas'), Arckaringa total coal resources (both JORC and non-JORC) would represent respectively 28% and 29% of current North Sea remaining proven reserves of 10,900mb of oil and 114,800 bcf of natural gas.

 

Altona has already accomplished a number of key phases in its development:

 

·; The Company has agreed the terms of a joint venture agreement with CNOOC-NEI, a subsidiary of Chinese oil major China National Offshore Oil Corporation, to accelerate the Arckaringa Project towards commercialisation. 

·; Under the terms of the agreement, CNOOC-NEI will fund the bankable feasibility study ('BFS') for a coal mine and an integrated value-added project. 

·; The current base case is a 10mb per year CTL plant and 560MW co-generation power facility. 

·; CNOOC-NEI will also act as the operator and take responsibility for assessing the full potential of the coal resource, in return for a 51% interest in the exploration licences. 

·; It is envisaged that numerous new additional projects may also be opened up to create a multi-project, multi-national business. 

 

CTL

The quality of the Company's coal is suitable for conversion to synthetic gas ('Syngas'), using existing commercial CTL technologies. The process involves two major stages;

1. gasification to produce Syngas rich in hydrogen and carbon,

2. a liquefication stage where the Syngas is reacted over a catalyst to produce high quality, ultraclean synthetic fuels and chemical feedstocks. 

 

CTL is a prime example of clean coal technology - the associated combined cycle units produce negligible sulphur oxides, significantly less nitrogen oxides and 10-20% less CO2 per unit of power generated than a conventional coal fired plant, whilst carbon capture and storage offers the potential to reduce the overall greenhouse gas emissions from CTL to below the 'well to wheel' level of fuels derived from crude oil. The technology is best demonstrated in South Africa, where currently 30% of the country's gasoline and diesel fuel needs are met through CTL plants.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUNVNRAUAURAR
Date   Source Headline
29th Jul 20087:00 amRNSHolding(s) in Company
22nd Jul 200811:00 amRNSMemorandum of Understanding w
15th Jul 20086:26 pmRNSHolding(s) in Company
30th Jun 200811:00 amRNSASX Listing and Tranche 3 Ton
30th Jun 200810:00 amRNSTotal Voting Rights
16th Jun 20087:00 amRNSAppointment of Jacobs Austral
13th Jun 20085:56 pmRNSHolding(s) in Company
13th Jun 20087:00 amRNSAppointment of New Non-Execut
6th Jun 200811:31 amRNSCompletion of Tranche 2 Place
30th May 20087:00 amRNSArckaringa BFS Update
20th May 20089:32 amRNSTranche 2 Placement to Tongji
19th May 20083:00 pmRNSHolding(s) in Company
19th May 20082:15 pmRNSHolding(s) in Company
6th May 20085:09 pmRNSEGM Statement
14th Apr 20085:09 pmRNSEGM Statement
31st Mar 200810:45 amRNSInterim Results
20th Mar 20084:00 pmRNSNotice of EGM
5th Mar 20088:35 amRNSHolding(s) in Company
4th Mar 20087:02 amRNSField Programme Completion
29th Feb 200811:41 amRNSTotal Voting Rights
26th Feb 20087:01 amRNSGBP 11.6 Million Fundraising
21st Feb 20084:42 pmRNSHolding(s) in Company
20th Feb 200810:10 amRNSPotential New Investor
14th Feb 20084:21 pmRNSHolding(s) in Company
6th Feb 20087:01 amRNSHolding(s) in Company
15th Jan 20089:00 amRNSHolding(s) in Company
28th Dec 20072:00 pmRNSAGM Statement
4th Dec 20074:19 pmRNSFinal Results
27th Nov 20077:01 amRNSTechnical Programme Update
6th Nov 20077:00 amRNSAustralian Adviser
25th Oct 200710:00 amRNSMOU with FreightLink
22nd Oct 20077:01 amRNSGreenhouse Initiative
7th Sep 20077:01 amRNSUpdate on Feasibility Study
22nd Aug 20074:24 pmRNSAppointment of Broker
17th Aug 20073:30 pmRNSAIM Rule 26
25th Jul 200712:11 pmRNSHolding(s) in Company
20th Jul 200711:58 amRNSHolding(s) in Company
12th Jul 20077:00 amRNSExtension of MOU
3rd Jul 20077:01 amRNSAdviser Appointment
26th Jun 200711:06 amRNSProject Update
15th May 20078:57 amRNSHolding(s) in Company
11th May 20079:03 amRNSHolding(s) in Company
8th May 200710:48 amRNSWintinna Drilling Commences
30th Apr 200712:29 pmRNSHolding(s) in Company
30th Apr 20077:03 amRNSTotal Voting Rights
19th Apr 200711:27 amRNSDrilling & sampling to begin
18th Apr 20077:01 amRNSIssue of Equity
20th Mar 200711:37 amRNSInterim Results
21st Feb 200711:04 amRNSTrading Statement
23rd Jan 20072:09 pmRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.