Q2 2013 Production Report

29 Jul 2013 07:00

RNS Number : 3087K
African Minerals Ltd
29 July 2013
 

29th July 2013

African Minerals Limited

("African Minerals", "AML", or "the Company")

Q2 2013 Production Report

Highlights

·; Quarterly production of 4.0Mt, up 81% from previous quarter

·; Quarterly sales of 3.4Mt, up 65% on previous quarter

·; Achievement of 20Mtpa export rate 18 June 2013

·; Average FOB received price of $70/t (dry), down 22% from $89/t in Q1

·; Average shipping rate of $18/t, an improvement of 5% from $19/t in Q1

·; Average cash costs in Q2 of $40/t, a reduction of 19% from $49/t in Q1

·; End of period stockpiles at the mine of 2.4Mt of product

·; Sales guidance unchanged at 13-15Mt in 2013 (with production of 15-18Mt)

 

Keith Calder, Chief Executive Officer, said:

"African Minerals is making good progress this year, with production levels and sales rising in line with our expectations, and momentum building with the attainment of our target 20Mtpa target export run rate, which we reached in June 2013. It is particularly encouraging that this progress is being made during a wet season at the port which is similar to the one we experienced last year.

We will continue to focus on stabilising this current phase of operation, and bringing down costs to around the targeted $30/t level. In common with many other miners, we are focussing in the short term on cost reduction and improvements in efficiency and utilisation, and substantially reducing corporate overheads.

The successful stabilisation of the Phase 1 project will provide us with the springboard for our next phase of expansion, upon which we expect to report further during Q4 2013."

Summary

Q1 2013

Q2 2013

Variance

YTD

MINING

Tonnes P1 Ore Mined

Mt

2.8

4.7

70%

7.5

Tonnes Other Ore Mined

Mt

0.5

0.7

49%

1.2

Grade P1 Ore Mined

%

57.2

57.7

1%

57.5

Total Mined

Mt

3.3

5.5

67%

8.7

PROCESSING

Tonnes P1 Ore Treated

Mt

2.5

4.4

75%

7.0

Grade P1 Ore Treated

%

57.4

57.7

1%

57.6

Total DSO Produced

Mt

2.2

4.0

81%

6.1

End of Period Product Stockpile

Mt at mine

1.8

2.4

35%

2.4

EXPORT

Total Exported (Wet)

Mt

2.1

3.4

65%

5.5

Grade

%

57.9

58.2

1%

58.1

Moisture

%

10.8

11.1

3%

11.0

Total Exported (Dry)

Mt

1.9

3.1

65%

4.9

No of Vessels

#

12

20

67%

32

COSTS AND REVENUES

Cash Cost

$/t

49

40

-19%

44

Period Spot 58%

$/t

125

116

-7%

119

Shipping Rate

$/t

19

18

-5%

18

Achieved FOB (dry)

$/t

89

70

-22%

77

All figures are unaudited and subject to review

 

 

 

 

 

 

 

Production

Mining capacity continued to grow, and 5.5Mt of material were moved in the period, a 67% increase over the previous quarter. Phase 1 DSO ore mined was 4.7Mt, an increase of 70% over the previous quarter, with the balance being lower grade ore and pre-mining of saprolitic ore to be processed during future operations.

With the completion of the ramp up of the large wet process plant following the modifications to the trommel, apron feeder, cyclones and screens towards the end of Q1, tonnages continued to grow in the quarter. Total processed tonnes were 4.4Mt, an increase of 75% over the previous quarter, while yield improved from 86% to 89%, resulting in production of 4.0Mt of saleable product, up 81% from the previous quarter.

Mined grade and processed grade showed improvement quarter on quarter.

End of quarter stockpiles at the mine were 2.4Mt of saleable product.

Costs

As a result of the continued improvement in production, estimated cash costs fell from $49/t in Q1 to $40/t average for the quarter.

The steady decrease in cost per tonne as sales continue to grow gives us confidence in achieving a c$30/t cash cost by year end at the targeted output rate.

Exports

With the commissioning of the large second wagon dumper at the end of April, throughput capability at the port increased significantly in the second half of Q2, resulting in the sailing of 10 Ocean Going Vessels ("OGVs") within 30 days between May 18th and June 16th, as per our announcement on 18th June 2013. A total of 20 OGVs were despatched during the second quarter.

Exported grade improved slightly from 57.9% Fe to 58.2% Fe, and moisture levels remained stable at around 11%.

The mine continues to stockpile fines material in support of the seasonal shipping strategy which will see fines being shipped in the coming dry season. However, exports for the remainder of this wet season will be a lump blend product, with concurrently produced lump being blended with stockpiled A32 product. Lump blend, as is the case with A32, attracts an additional $5/t discount compared to standard fines pricing.

Sales

In Q1 2013, 6 of the 12 vessels were delivered into the Shandong Iron and Steel Group Discounted Offtake Agreement ("DOTA"), and in Q2 2013 12 of the 20 vessels were delivered into the DOTA. At the end of H1, 3.13Mt have already been delivered into the 4.80Mt DOTA annual commitment.

The weighted average 58% IODEX Platts index price for the period was $116/t (dry), down from $125/t in the previous quarter. The achieved FOB price in Sierra Leone was $70/t (dry), down from $89/t in the previous quarter, as a combined result of the drop in the benchmark price, a higher proportion of sales into the DOTA, adjustments on final versus provisional invoicing and the additional discount associated with selling lump blend. The price quoted is before marketing fees in China.

Freight rates reduced in the period from an average of $19/t to $18/t.

Guidance

Guidance for sales is reiterated at 13-15Mt in 2013 (with production of 15-18Mt).

Interim Results

 

Interim results for the six months ended 30th June are expected to be published on 11th September 2013.

 

 

Contacts:

 

African Minerals Limited

+44 20 3435 7600

Mike Jones

 

FTI Consulting

+44 20 7831 3113

Ben Brewerton

 

Jefferies

44 20 7029 8000

Nick Adams / Alex Collins

 

About African Minerals

African Minerals operates the Tonkolili Iron Ore Project (the "Project") in Sierra Leone, with a JORC compliant resource of 12.8Bnt. The Project, which currently has a 60+ year mine-life, is being developed in a number of staged expansions. The current Project operations are expected to produce 20 million tonnes of iron ore per annum at full capacity, with this run-rate of production having first been achieved in June 2013.

The next stage of Project expansion now contemplates the production of up to 35Mtpa of 64% high grade hematite concentrate and the expansion of the current port facilities at Pepel, expected to enter production in 2016.

The Company has also developed significant port and rail infrastructure to support the operation of the Project, via its subsidiary African Rail and Port Services (SL) Limited ("ARPS"), in which the Government of Sierra Leone ("GoSL") has a 10% free carried interest.

The Project companies are currently owned 75% by AML, and 25% by Shandong Iron and Steel Group ("SISG"), except for ARPS, which is currently owned 75% by AML and 25% by SISG, with the GoSL having the right to a 10% free carried interest from AML.

 

www.african-minerals.com

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCVVLFLXDFZBBK
Date   Source Headline
16th May 20127:00 amRNSCRM subscribes to Convertible Bond
14th May 20122:01 pmRNSAdditional Listing on Exercise of Share Options
2nd May 20124:12 pmRNSAdditional Listing on Exercise of Share Options
1st May 20127:00 amRNSDirectorate Change
11th Apr 20127:00 amRNSPreliminary Results
2nd Apr 20121:11 pmRNSReceipt of SISG funds and Secured Loan repayment
30th Mar 201212:33 pmRNSAML and SISG complete $1.5Bn investment
24th Feb 20127:00 amRNSAdditional Listing on Exercise of Share Options
16th Feb 20126:01 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
14th Feb 20125:47 pmRNSAdditional Listing on Exercise of Share Options
13th Feb 20127:00 amRNSShandong due to complete, $868m financing closed
9th Feb 20127:00 amRNSDrawdown of $417.7m Standard Bank Facility
31st Jan 20128:13 amRNSSuccessful Arrangement of $868m Financing Package
31st Jan 20127:00 amRNSOffering Of Up To $350 Million Convertible Bonds
27th Jan 20126:12 pmRNSFinancing arrangements for Phase 1 expansion
15th Dec 201111:57 amRNSUpdate on Shandong, Commissioning & Marketing
5th Dec 20118:59 amRNSTR-1: Notifications of Major Interests in Shares
15th Nov 20117:18 amRNSAdditional Listing on Exercise of Share Options
4th Nov 20117:00 amRNSLoading of First Tonkolili Iron Ore Shipment
31st Oct 20112:11 pmRNSTR-1 (UK) Notification of Major Interests in Share
25th Oct 20113:05 pmRNSAdditional Listing on Exercise of Share Options
19th Oct 20111:34 pmRNSAdditional Listing on Exercise of Share Options
5th Oct 20119:08 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
5th Oct 20119:08 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
30th Sep 20113:14 pmRNSDirector/PDMR Shareholding
30th Sep 20117:00 amRNSInterim Results
9th Sep 20112:54 pmRNSRESOLUTIONS PASSED AT 9 Sept 2011 AGM
18th Aug 20117:00 amRNSArrangement of c$90m equipment financing & update
15th Aug 20117:00 amRNSNotice of AGM
1st Aug 20117:00 amRNSAML Executes Agreements with SISG to Invest $1.5bn
29th Jul 20113:36 pmRNSAdditional Listing
28th Jul 201110:01 amRNSChange of Adviser
19th Jul 20111:36 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
19th Jul 20111:35 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
12th Jul 20118:35 amRNSDirectorate Change
30th Jun 20117:00 amRNS2010 Annual Report & Accounts Posted
27th Jun 20119:12 amRNSAdditional Listing on Exercise of Share Options
1st Jun 20117:26 amRNSUpdate on Negotiations with Shandong Iron & Steel
31st May 20112:08 pmPRNFinal Results
24th May 201111:00 amRNSMemorandum of Understanding with CCCC
19th May 20117:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
6th May 20117:26 amRNSAdditional Listing
3rd May 201111:53 amRNSRevised MoU for $1.5bn SISG Investment
27th Apr 201112:06 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
21st Apr 20113:35 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
14th Apr 20117:00 amRNSAdditional Listing on Exercise of Share Warrants
12th Apr 20117:00 amRNSAppointment of Independent Non-Executive Directors
12th Apr 20117:00 amRNSPreliminary Results for the year ended 31/12/2010
8th Apr 20112:56 pmRNSAdditional Listing on Exercise of Share Options
22nd Mar 20117:00 amRNSAdditional Listing

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.