Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAMI.L Regulatory News (AMI)

  • There is currently no data for AMI

Expansion Update

18 Dec 2012 09:02

RNS Number : 7760T
African Minerals Ltd
18 December 2012
 



18 December 2012

African Minerals Limited ("AML" or "the Company")

 

Expansion Update

 

African Minerals Limited today provides an update on various project matters as the Company continues to ramp up production at the Tonkolili iron ore mine in Sierra Leone.

SUMMARY

·; Following a recent scoping level review of expansion options, the Company now intends to expand the existing rail and port infrastructure at Pepel rather than develop a new port at Tagrin Point.

·; Targeting saprolite hematite concentrate production of up to circa 35Mtpa, with production commencing in 2016.

·; Total capital expenditure on the revised expansion plan estimated to be circa $2Bn, with cash costs similar or lower than the current direct shipping ore phase.

·; Substantial capital savings of circa $1Bn over previous expansion plan, with reduced risk, and lower social and environmental impact.

 

CEO, Keith Calder, commented:

"We have made good progress with value engineering and optimisation in our Tonkolili mine expansion strategy. While our strategy regarding the mine and plant is mostly unchanged, we have now decided to leverage our existing rail and port infrastructure at Pepel to achieve the expanded export tonnage. This will significantly reduce capital costs, and de-risk the project's delivery, whilst at the same time reducing social and environmental impacts. This approach will provide a significantly better value, capital efficiency and risk proposition for all of our stakeholders."

 

 

 

EXPANSION UPDATE

The 12.8Bnt Tonkolili deposit is in the early stages of its growth, and the Company is currently exploiting the direct shipping ore ('DSO') portion of the resource.

 

The Company has previously described the various stages of expansion of the deposit in "Phases", however the Company now considers it appropriate to consider the overall growth of the deposit as it moves into the saprolite hematite stage.

 

The production of saprolite hematite material is expected to begin in 2016, with saprolite capacity being ramped up as the DSO resource enters the end of its life, to a currently envisaged 35Mtpa concentrate production rate. Subsequently the project is expected to grow into the multi-generational magnetite resource.

 

The Company's scoping level assessment of Pepel shows that the current port can be expanded to handle the additional export tonnage that is expected, with substantial capital savings in not having to build a new port at Tagrin Point, as was previously envisaged, and associated rail spur. Notwithstanding an increased operating cost (as compared to our previous projections, with the need for transhipping being removed), there are expected to be significant net financial benefits in the net present value ('NPV') due to a lower upfront capital requirement.

 

There are also substantial risk benefits to not embarking on major greenfield construction that would require relocation of communities and the development of a new Environmental Impact Assessment, and which could have resulted in unforeseen project delays.

 

Thus, the Company has determined that, subject to formal Board approval, the plan for expansion into the saprolite will now encompass:

 

·; Production of up to circa 35Mtpa of 64% hematite concentrate;

·; Modular, sequentially constructed process plants, with the first expected to enter production in 2016;

·; Modification to the existing narrow gauge rail, including double tracks where necessary, and additional rolling stock;

·; Additional dredging and the construction of a second major ship-loading facility and wagon dumper at Pepel; and

·; Total capital expenditure on the revised expansion plan estimated to be circa $2Bn, with cash costs similar or lower than the current DSO phase.

Early works on this revised expansion plan have already begun to further refine project engineering design, and the Company expects to be in a position to provide more detail on capital cost and scheduling in H2 2013.

 

 

Contacts:

 

African Minerals Limited

+44 20 3435 7600

Mike Jones

 

FTI Consulting

+44 20 7831 3113

Billy Clegg / Ben Brewerton

 

Deutsche Bank

+44 207 545 8000

Brent Nabbs

 

African Minerals is developing its Tonkolili iron ore project in Sierra Leone, with a JORC compliant resource of 12.8Bnt. The project, which currently has a 60+ year mine-life, is being developed in a number of staged expansions. The current operations are expected to produce 20 million tonnes of iron ore per annum at full capacity, expected to be achieved in Q2 2013.

 

The next stage of expansion now contemplates the production of up to 35Mtpa of 64% high grade hematite concentrate and the expansion of the current port facilities at Pepel, expected to enter production in 2016.

 

 

The Company has also developed significant port and rail infrastructure to support the operation of the project, via its subsidiary African Rail and Port Services (SL) Limited ("ARPS"), in which the Government of Sierra Leone ("GoSL") has a 10% free carried interest.

 

The Tonkolili project companies are currently owned 75% by AML, and 25% by Shandong Iron and Steel Group ("SISG"), except for ARPS, which is currently owned 75% by AML and 25% by SISG, with the GoSL having a 10% free carried interest.

 

www.african-minerals.com

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGIBDDCUBBGDI
Date   Source Headline
16th Dec 201310:15 amRNSAdditional Listing on Exercise of Share Options
5th Nov 20137:00 amRNSQ3 2013 Production Report
26th Sep 20134:17 pmRNSRESOLUTIONS PASSED AT 2013 AGM
26th Sep 20137:00 amRNSProposed Strategic Investment
11th Sep 20137:00 amRNSrelated party transactions with Shandong
11th Sep 20137:00 amRNSInterim Results 2013
14th Aug 20137:00 amRNSDirectorate Change CEO
14th Aug 20137:00 amRNSDirectorate Change CFO
29th Jul 20137:00 amRNSQ2 2013 Production Report
22nd Jul 20134:33 pmRNSAdditional Listing on Exercise of Share Options
22nd Jul 20137:00 amRNSAppointment of Vice Chairman
28th Jun 20137:00 amRNSPosting of Annual Report and Accounts
26th Jun 201310:01 amRNSDirector/PDMR Shareholding
18th Jun 20137:00 amRNSAchievement of 20Mtpa export rate
22nd May 20138:58 amRNSHolding(s) in Company
14th May 201312:20 pmRNSHolding(s) in Company
14th May 201312:19 pmRNSHolding(s) in Company
14th May 201312:18 pmRNSHolding(s) in Company
19th Apr 20131:48 pmRNSAdditional Listing on Exercise of Share Options
18th Apr 201311:57 amRNSHolding(s) in Company
10th Apr 20137:00 amRNSFull Year Results
4th Mar 20137:00 amRNSAdditional Listing on Exercise of Share Options
5th Feb 20137:00 amRNSConfirmation of new financing arrangements
4th Feb 20137:00 amRNSChange of Nominated Adviser and Broker
14th Jan 20137:00 amRNSAppointment of Chief Operating Officer
4th Jan 20133:08 pmRNSDirector Share Dealing
27th Dec 20125:12 pmRNSDirector share dealing
18th Dec 20129:05 amRNSRaising of Limit of Ownership by CRM
18th Dec 20129:02 amRNSExpansion Update
17th Dec 20124:20 pmRNSOperational and Funding Update
13th Dec 20127:00 amRNSHolding(s) in Company
4th Dec 20127:00 amRNSHolding(s) in Company
23rd Nov 201212:00 pmRNSEstablishment of Finance Credit Facility
21st Nov 20125:44 pmRNSOperational and Financing Update Conference Call
21st Nov 201212:26 pmRNSOperational and Financing Update
1st Nov 20124:45 pmRNSRelated Party Transactions
11th Sep 20127:00 amRNSInterim Results
3rd Sep 20127:00 amRNSAppointment of Senior Personnel
24th Aug 20127:00 amRNSProject Update
2nd Aug 20123:34 pmRNSResult of AGM
17th Jul 20123:16 pmRNSAdditional Listing on Exercise of Share Options
13th Jul 20124:46 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
6th Jul 20125:44 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
6th Jul 201212:04 pmRNSGrant of Share Options
5th Jul 20124:45 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
4th Jul 20127:00 amRNSChange of directors
4th Jul 20127:00 amRNSAppointment of Chief Executive Officer
28th Jun 20124:16 pmRNS2011 Annual Report & Accounts and Notice of AGM
1st Jun 20126:36 pmRNSDirector/PDMR Shareholding
16th May 20125:33 pmRNSDirector share dealing

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.