Kalsaka Gold Project Update

27 Aug 2008 07:37

RNS Number : 0863C
Cluff Gold PLC
27 August 2008
 



Cluff Gold plc

("Cluff Gold" or the "Company")

SECOND MINE GOES INTO COMMISSIONING  AT THE KALSAKA GOLD PROJECTBURKINA FASO

Cluff Gold (AIM-"CLF") is pleased to announce  that its Kalsaka Gold Project ("Kalsaka") in Burkina Faso, has commenced the commissioning of the dry plant and that approximately 4,500 tonnes of ore have been processed and are now stacked on the leach pads. 

The plant has operated on a single shift basis but plans are underway to commence a twenty-four hour operation shortly. Gold production is expected to reach an annualised production level of 60,000 Au ounces by the end of this year.

Kalsaka is the second Gold Project that Cluff Gold has put into production this year. The first was its  Angovia Gold Mine in Code d'Ivoire The two gold projects are expected to produce 100,000 Au ounces of on an annualised basis from 2009

Douglas Chikohora, Technical Director of Cluff Gold plc comments, "We are pleased with the Company's progress made so far in 2008 despite the challenges associated with constructing and commissioning two projects almost simultaneously in the current mining and economic climate.  We believe Cluff Gold is well placed to tackle any potential issues going forward. Although the gold price has softened in the last couple of months, we believe it will remain buoyant over the longer term. We also believe the Company is now poised for significant growth in 2009 when the two gold projects are expected to reach their design production capacities. "

Douglas D Chikohora has reviewed and approved the information contained in this announcement. Douglas D Chikohora, Msc, (MIMMM, CEng) is Technical Director of the Company.

For further information, please contact: 

 Cluff Gold plc

 J.G. Cluff

 Tel: +44 (0) 20 7340 9790

W H Ireland

David Youngman/Katy Mitchell

Tel: +44 (0) 161 832 6644

Farm Street Communications

Simon Robinson

Tel: +44 (0) 7887985671

Notes to Editors:

About Cluff Gold

Cluff Gold plc is focused on the identification, acquisition and development of gold deposits in West Africa that are amenable to open-pit mining and low cost production techniques.

The Company has made significant progress since its admission to AIM in December 2004, increasing gold resources across its projects, expanding the project portfolio and broadening the investor base to an increasingly international audience.

Mt. YaoureCote d'Ivoire

The Mt. Yaoure permit is located 40km northwest of Yamoussoukro, the political capital of Cote d'Ivoire, and covers a surface area of 417km(2) including a 50

km2 mining permit. The licence area includes the Angovia gold mine which operated between 1998 and 2003. The mine reportedly produced over 180,000 ounces of gold during this period by heap leaching some 2 million tonnes of oxide material. The infrastructure in the area is good and includes a hydroelectric dam six kilometres from the Angovia mine site. A measured and indicated JORC resource of 451 000 ounces and an inferred JORC resource of 44 000 ounces has so far been delineated.

Recently, the company announced the commencement of gold production at Angovia at an annualized rate of 40 000 ounces of gold by the end of this year.

KalsakaBurkina Faso

Kalsaka is located approximately 150km north west of Ouagadougou, the capital of Burkina Faso. A measured and indicated JORC resource of 634 000 ounces and inferred JORC resource of 157 000 ounces has been delineated so far. The resource has been demonstrated, by a feasibility study, to be technically amenable to open-pit mining and processing via heap leaching. Water, environmental and mining permits for the project have been granted. The mining permit is valid for twenty years.

Construction has commenced at Kalsaka and commissioning is expected to commence in Q3, 2008 with production estimated to reach 60 000 ounces on an annualized rate by the end of this year.

BAOMAHUN, SIERRA LEONE

The Baomahun Gold Project covers an area of about 137 km2 and is located about 180 kilometres east of Freetown, in the Southern Province of Sierra Leone. The geological setting is similar to the Lake Victoria goldfields in Tanzania.

The Baomahun licence area covers more than 12 kilometres of prospective strike along the Kangari Hills which is composed of Archaean greenstone belt terrain consisting of banded iron formation (BIF) Gold mineralisation in the drilled areas is intimately associated with the BIF and other lithologies in close proximity to the BIF. Accordingly, future exploration and drilling will continue to use the BIF as a marker horizon for auriferous zones along the belt.

A measured and indicated JORC compliant mineral resource of 867,000 ounces of gold (8,933,000 tonnes grading 2.9 g/t Au) and inferred JORC compliant mineral resource of 486,000 ounces of gold (5,083,000 tonnes grading 3.0 g/t Au). A total JORC compliant mineral resource (measured, indicated and inferred) of 1,353,000 ounces of gold (14,016,000 tonnes grading 3.0 g/t Au) has so far been delineated.

On 17 July 2008, the Company announced that the Government of Sierra Leone had granted Baomahun Gold Limited, a 100 per cent owned subsidiary of the Company, a Mining Lease for 25 years over an area of 59.85sq kilometres.

Cluff Gold now holds 100 per cent of the Baomahun Gold Project. Cluff Gold announced on 4 August 2008 that it had acquired the outstanding 40 per cent interest in the project for US$21.8 million which was satisfied by the issue of 12,390,909 ordinary shares in the Company. 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUBONRWNRWURR
Date   Source Headline
16th Jul 20137:00 amRNSYaoure Gold Project Update
8th Jul 20131:40 pmRNSDIRECTORS' DEALINGS
3rd Jul 20134:40 pmRNSDIRECTORS' DEALINGS
2nd Jul 20137:00 amRNSBaomahun Feasibility Study
27th Jun 201310:10 amRNSNOTICE OF BAOMAHUN FEASIBILITY STUDY
12th Jun 20134:35 pmRNSPrice Monitoring Extension
5th Jun 201311:59 amRNSResult of AGM
22nd May 20137:00 amRNSQ1 2013 RESULTS
21st May 20137:00 amRNSGRANTING OF ENVIRONMENTAL PERMIT FOR SEGA PROJECT
13th May 20137:00 amRNSPOSTING OF ANNUAL REPORT AND NOTICE OF AGM
10th May 20137:00 amRNSFILING OF YAOURE TECHNICAL REPORT
30th Apr 20137:00 amRNSRECEIPT OF PERMITS FOR KALSAKA/SEGA HAUL ROAD
10th Apr 20134:00 pmRNSDirectors' Dealings
5th Apr 20134:35 pmRNSPrice Monitoring Extension
2nd Apr 20133:30 pmRNSDirectors' Dealings
27th Mar 20137:00 amRNS2012 AUDITED FULL YEAR RESULTS
25th Mar 20137:00 amRNSResource Update for Yaoure Gold Project
16th Oct 20127:00 amRNSPEA and Exploration Update for the Sega Project
3rd Oct 20127:00 amRNSConfirmation of change of ticker
1st Oct 20127:00 amRNSChange of name and corporate update
12th Sep 20127:00 amRNSStrategic Alliance between Cluff Gold and Samsung
24th Feb 20115:33 pmRNSResignation of Non-Executive Director
26th Jan 20117:00 amRNSOperational and Strategic Review for 2011
23rd Dec 20103:04 pmRNSAdditional Listing of 182,565 ordinary shares
22nd Dec 20103:59 pmRNSDirector's Dealings
21st Dec 20104:21 pmRNSDirectors' Shareholdings
1st Dec 20107:00 amRNSFinal VTEM Results for Baomahun Gold Project
30th Nov 20107:00 amRNSKalsaka Exploration Drilling Update
1st Nov 201011:06 amRNSAdditional Listing
28th Oct 20107:00 amRNSUS$15M Private Placement with Macquarie Bank
12th Oct 20105:00 pmRNSHolding(s) in Company
12th Oct 201011:49 amRNSHolding(s) in Company
8th Oct 20101:05 pmRNSHolding(s) in Company
6th Oct 20104:24 pmRNSAdditional Listing
29th Sep 20107:00 amRNS2010 Interim Results
9th Sep 20107:00 amRNSH1 2010 Trading Update
3rd Sep 20107:00 amRNSDirectorate Change
13th Aug 20105:42 pmRNSTECHNICAL REPORT ON BAOMAHUN FILED ON SEDAR
28th Jul 20105:10 pmRNSDirector/PDMR Shareholding
6th Jul 20109:49 amRNSGrant of Options to Directors
30th Jun 201011:58 amRNSResults of the Prelim Assessment for Baomahun Gold
29th Jun 20107:00 amRNSResult of AGM and new Board appointments
15th Jun 201011:42 amRNSPosting of Annual Report
4th Jun 20107:00 amRNSIncreased Mineral Resource Estimate at Baomahun
2nd Jun 20102:57 pmRNSForm 8.3 - Cluff Gold Plc
2nd Jun 201011:37 amRNSForm 8.5 (EPT/NON-RI)
1st Jun 20105:41 pmRNSTermination of Offer Talks
1st Jun 20103:05 pmRNSForm 8.3 - Cluff Gold Plc
1st Jun 201011:11 amRNSForm 8.5 (EPT/NON-RI)
1st Jun 201010:11 amRNSForm 8.5 (EPT/RI)

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.