What is coming up..6 Jan 2021 15:13
from recent Q and A.
Our milestones for H1 2021 are as below. In all of these goals we are dependent on third parties – regulatory agencies, suppliers and debt financiers and, even in this environment, we regard these goals as realistic.
1.To close Saltfleetby loan documentation before the end of January and begin drawdown very shortly thereafter.
2. To follow with the second stages of procurement for all of the kit during February with a view to having installation during Q2.
3. To begin commissioning Satlfleetby and work toward first gas around the end of Q2
4. To present to shareholders a commercially viable ESG project during Q1.
5. To obtain planning permission from West Sussex County Council, albeit with conditions, in the month of February to proceed with the welltest at Balcombe in H1.
6. To obtain Environment Agency approval for water injection at Brockham during Q2.
All good stuff which should see the sp steadily rise imo.