RE: Open Offer 2p30 Mar 2024 13:59
Hi clueless, this was from Jan's quarterly report.
The planned substation at Lesedi was designed for an initial 5MW of power, however the Company is working on options that may allow the substation design to be adapted to facilitate expansion beyond 10MW.
A new substation is required at the Lesedi end of the transmission line whereas at the opposite end, it will tie into the existing BPC substation at Serowe.
Including the additional work required to expand capacity beyond 10MW, the substations are approximately 37% complete. It is currently anticipated that the project will be completed around mid-2024.
Doesn't quote 25MW but is beyond 10MW so let's hope it is.