RE: interesting link6 Dec 2018 18:55
Great research Palmer.
Here is the interesting snippet .
8. Discussion and Action Items
a. Old Business
i. Biomass plant—update: Dan Rosenberg gave an update. We have signed a term sheet with an investor for the remaining $10 million, as a state bond issue. The total for the investor is $15 million. The bio-mass plant will be 2 megawatts from the beginning. One action that needs to be done is an ALTA survey. This will cost up to $6,000. The log deck is being operated by an Auberry logging business, and the owner, Richard Thornton, has agreed to provide enough feedstock for 5 years. A contract is in place. Our Mill Site log deck will be eventually leased by the North Fork Community Power.