RE: days till production20 Mar 2019 12:01
This from the SM website:-
“”Extraction of polyhalite will commence as soon as the shaft intersects the seam at 1,510m below ground level, as the roads and bit bottom are constructed within the polyhalite seam.
Initially, the extraction rate will be constrained by the capacity of the construction contractor’s temporary hoisting equipment. On completion of the production shaft fit out, the hoisting constraint will be removed and the mine will commence ramping up by adding more continuous miners (CMs), as shown below. First production would be in 2021, ramping up to 10 Mtpa in 2024.””
This is what you meant Bobster?
R