RE: Balcombe application link26 Aug 2020 20:13
From the Planning Statement:
4.1.2 Phase 1, pumping operation, is anticipated to take up to 4 weeks and will use a minimum
amount of surface equipment. Assuming this is successful, Angus Energy would then move
on to phase 2, the civil engineering works to upgrade the pad containment. Once
construction and installation of the pad membrane is complete, phase 3 would commence
with an EWT for 12 months depending on results. The final phase, plugging and restoration
of the site, phase 4, will be carried out on completion of the operation if future site production
is not achieved.
4.1.3 If the EWT confirms that there are hydrocarbon reserves which could be commercially
extracted, a separate planning application will be prepared for a future production phase. A
period of 12 months has been allowed for the submission of a planning application for
determination by WSCC.
4.1.4 The total duration of the project will last up to 30 months; however, surface operations during
this period will be confined to a much shorter duration of approximately 18 months. Appendix
1 is an indicative timeline to show the individual phases of surface activity and pauses in
surface development.