RE: B2Gold Results today & toll refine7 Nov 2018 16:26
Couple of things to bear in mind Aguila, B2Gold are in the process of getting the Jabali Antenna underground and pit permitted which will improve the economics of La Libertad. From B2:
"In the third quarter of 2018, La Libertad Mine in Nicaragua produced 21,995 ounces of gold, 39% (14,207
ounces) below original budget. As a result of the onset of national political unrest in Nicaragua,
development of the Jabali Antenna Underground project was temporarily suspended, resulting in flooding
of the underground workings. The Underground mine dewatering was completed in mid-August and ramp development has recommenced. Production from the underground operation is now anticipated to
commence by late-fourth quarter 2018. In addition, the mine permit for the new Jabali Antenna Pit continues
to be delayed although progress has been made. The Company now anticipates receiving the permit in time
to start production from the pit in the third quarter of 2019."
Also they put the increased AISC of El Limon down to the political unrest/road blockages and so expect costs to improve as production returns to normal.
Obviously we'll have to see if that pans out but just to say, the current negative snapshot for B2 in Nicaragua is not necessarily as bad as it looks on the face of it. Still think MC is looking to do some kind of deal with B2 though...