RE: Rig & Crew20 Dec 2020 19:52
Been refreshing my info on Clix-1001 well
30th Jan, drill complete Eagle Rig mobilised for testing
6th March, testing under way
15th April, testing suspended, rig re-deployed (due to Covid restrictions ref equipment & personnel outside of Arg.)
So I would say 5-7 weeks of testing performed.
Now looking back on CLM x-1 Eastern TA
12th December, drill complete
19th February, perforated, hydraulic stimulation and result (non commercial)
All completed in 9 weeks including hydraulic stimulation taking 2-3 weeks.
My point bring IMO would say it’s all probability, with 70% COS, initial testing shows commercialIty waiting on independent verification!
GLA