Hi GP,
The West Newton A-2 well was spudded on 26 April 2019 and, on 9 June 2019, reached a total depth (TD) of 2061 metres. So 45 days for total ops. I’m guessing the late release of the RNS was to check the data.
WNB spudded on 4th Oct so we are on day 20, nearly half way through the previous duration. Is hard to pin point where we are exactly as the footage from site hasn’t been great. Seen no casing laid out on racks or deliveries. Amazes me that people were sending out drone footage of the construction phase but then nothing during ops.
I will be extremely disappointed with the dynamic duo if we get 1 RNS at the end of the drilling.