2026 Results30 Apr 2026 09:48
Not sure why they are not showing as a live RNS, but the full year results where out yesterday and look decent. I've copied below for any who haven't yet seen. Full version on the company website. Sadly share price doesn't seem to agree but I didn't see any skeletons in the numbers. Just maybe a bit slower progress in Teren-Sai than some would like
Financial highlights
• Turnover increased in the year to US$175.4m (2024: US$96.5m) an increase of 82%.
• 50,442oz of gold were sold (2024: 38,708oz) an increase of 30%
• Average gold price achieved (including silver), US$3,474oz, (2024: US$2,441oz). An
increase of 42%.
• The Company made a profit after tax of US$62.0m (2024: US$26.4m).
• Adjusted EBITDA (Earnings before interest, tax, depreciation and amortisation) of
US$101.4m (2024: US$50.9m).
• The Company repaid borrowings of US$34.1m (2024: US$20.4m).
• Net debt at year-end (after deducting cash balances) was US$18.5m (2024:
US$49.7m).
Operational highlights
• Ore mined 926,000t (2024: 750,000t)
• Gold poured 53,852oz, (2024: 37,279oz)
• Mined gold grade 2.05g/t, (2024: 2.29g/t).
• All in sustaining cost (AISC) US$1,562/oz (2024: US$1,318/oz).
• Gold recovery rate 85.07% (2024: 85.4%).
• 5th year of no accidents or incidents
Underground development and exploration highlights
• Development of the ventilation works and buildings to support continued development
of the underground to lower levels.
• Transport decline 1 is at -34masl, decline 2 is at sea level (2024: Decline 1 at sea
level, decline 2 at +34masl)
• Completion of the main drainage complex at +150masl, and laying associated
pipelines amounting to 1,700 linear metres.
• Reconstruction of tailings dam 4 to extend its capacity was completed.
• Exploration drilling of blast holes at Sekisovskoye amounted to 169,000 linear metres
(2024: 216,000 linear metres).
• Licence for Teren-Sai was extended for 3 months from March 2026, during which time
the application process to move to a production licence will commence.
2026 Outlook
The Company has set a production benchmark of 50,000oz of gold and an ore processing
capacity of 1Mtpa. Building on this foundation, it is actively pursuing opportunities to expand
capacity to 2Mtpa.
At the Teren-Sai project, the Company is advancing the process to secure a production
license, with approval anticipated by the end of 2026. Preliminary testing and drilling results
have identified three high-potential sites.