Marklee1, we know that the old concentrator is working 24/7 and that the new concentrator is due to be commissioned within weeks.
It makes sense to have adequate training for new staff to be ready for the jump up to 16/7 for the crusher, Jig and mill and the new concentrator. When they are up to speed, it will be time to take on the final group of trainees, the ones that are being advertised for now, for the leap to 24/7 production.
We need 24/7 production in place, to ramp up to the 200 tonnes of tungsten ($4m gross sales) and 20 tonnes of tin ($367k gross sales) per month.
I’ll be happy with 30, 50 and 100 tonnes for July, August and September.