From Final Prospectus:
"Phase 1 of this development is currently in progress, comprising and expected to be completed in the first half of 2022, and includes the electrical interconnection, infrastructure and machine hosting facilities that are expected to support 100 MW of power capacity using immersion technology, at an estimated cost of $50 million. Phase 2 of this development, which is expected to be completed in the second half of 2022 and is expected to support an additional 100 MW of power capacity using immersion technology, at an estimated cost of $30 million. The costs of these facilities have been covered from the Company’s existing cash resources and the net proceeds of the Fundraising. These estimates do not include the cost of the mining machines that the Company will operate at the new mining facility"