RE: Delay again first gas April May June 202222 Nov 2021 09:15
Andrew Hockey, CEO of IOG, commented:
"The offshore subsea and hook-up scopes for the Blythe and Elgood fields are now complete. We continue to work closely with Bacton terminal operator Perenco and an enlarged workforce to complete the reception facilities recommissioning and deliver First Gas in Q4, albeit this may be challenging.
Meanwhile, we expect the Noble Hans Deul rig to re-mobilise to Southwark in early December once it has been re-certified for safe operation, with Southwark First Gas still on track for Q2 2022.
Can't see any gas until Feb imho not long though but full value will not come until all gas is on stream imho that could be June?