RE: Placing26 Feb 2019 07:39
Boom,
3 days to submit the below or what happens to the extension???
The OGA has agreed a 5 month extension of the initial term of licence P2112 to 19 May 2019.
Under the terms of the extension, the licence holder must:
By no later than 31 March 2019, advise the OGA that it either: (i) has elected to drill one well to 3800m or 100m into the Namurian (whichever is the shallower) and approved the necessary funding for the well commitment; or (ii) elected to terminate the licence;
Provide the results of two G&G studies to the OGA by 1 March 2019 together with a conclusion as to whether the results of these studies support a drill decision; and
Provide an update to the OGA by 1 March 2019 on all pre-drill decision work.