RE: Announcement Charlie update23 Feb 2020 21:41
Drilling and Logging
• Drilling to Total Depth (planned ~11,400’), Logging While Drilling and Wireline Logging estimated to
take ~30 days
State of the Art Subsurface Evaluation Program
• Utilisation of the latest proven technology
• Program specifically designed to evaluate:
• Formations that may have laminations resulting in low resistivity pay
• Formations with low to moderate permeability
• Formations with considerable bound water
• Prior to advent of specialist tools, the above challenges often resulted in pay being left behind
Flow Testing
• Subsurface evaluation to be followed by up to two production tests
• Zones of interest and final test design to be determined by results of logging
• Each test estimated to take ~14 days
Reporting
• Total program estimated to take ~60 days, with reporting of results determined by materiality and
continuous disclosure obligations