RE: Flow rates last 2 days.6 Oct 2022 18:20
The side track is expected to be spudded around 20th October with drilling operations expected to have a duration of no more than 35 days excluding well clean up and completion work. Simultaneous operations are permitted but we have allowed for two twelve-hour shut-in periods during this period to undertake critical works and enable certain equipment to be moved on site.
From rns.