Navitas reports other progress on the Sea Lion development as follows:
· The development works on the Falkland Islands have commenced and at this stage are focused on preparing the dock and shore base. Later this year, works will also commence for the construction of worker accommodation as well as additional infrastructure works in preparation for the commencement of drilling activity.
· The manufacturing of long lead items for the Phase 1 is ongoing.
· In early May 2026, the owner of the Aoka Mizu FPSO provided an update that production by the current operator had concluded and, by the end of May, disconnection works will be completed and the Aoka Mizu FPSO will sail to the shipyard for upgrade work to adapt it to Sea Lion's requirements.
· Drilling and completion works are scheduled to commence at the beginning of 2027. First oil from the Phase 1 is still currently expected in H1 2028.
Samuel Moody, Chief Executive Officer of Rockhopper, commented:
"We are delighted that the project is on track having taken the prudent decision in the light of the security situation arising from the Iran conflict to move the FPSO work from the Middle East to Asia. We are equally excited at the prospect that the development of additional barrels might be accelerated with the signing of the MOU for a second FPSO giving the opportunity to add a further 125,000 barrels per day of production to the 55,000 barrels per day from the first two phases."