Push21 Dec 2022 14:48
from your post on Friday at 12.18
If they manage to get the casing down through the motherbore cut window into the newly drilled section OK then I would expect them to have casing in over a 24hr period, then cement the casing in place, 24hr period ( including curing), then drill cement out that will be in the very bottom part of the new casing, 24hr period, then almost certainly they will need to run a cement bond log over the new section to prove the casing is fully cemented in behind the casing wall, 6 hr period.
I would say they "should" be back to start drilling the horizontal section by Tuesday, all being well & without any minor issues.
Does it concern you that we are now at Thursday and no news has of yet.