Time scales as reported in the most recent RNS approx five weeks ago.
i. Plateau drilling programme
The Company has recently completed Stage 1 of the drilling programme, which consisted of reverse circulation drilling of 6 drill holes. The next stages of the drilling programme at Plateau consist of the following:
· Stage 2 - Reverse circulation drilling of 4 drill holes, for 897 metres, and diamond drilling of 6 drill holes, for 1,664 metres, expected to take approximately ***three months***.
· Stage 3 - Reverse circulation drilling of 1 drill hole, for 251 metres, expected to take approximately ***one week*** and diamond drilling of 1 drill hole, for 779 metres, expected to take approximately ***two months***.