Independent Oil & Gas Confirms Pipeline Integrity, Gas Project Delayed

Tue, 25th Sep 2018 11:50

LONDON (Alliance News) - Independent Oil & Gas PLC on Tuesday confirmed the integrity of the Thames Pipeline, and said it has chosen to delay delivery of the first phase of offshore installation at its southern North Sea gas project.

Shares in the offshore oil & gas company were down 9.9% at 31.75 pence on Tuesday.

A pressure test of the Thames Pipeline confirmed its integrity and ability to deliver gas and a tethered pig inspection showed no internal corrosion or external defects, IOG said. The pipeline is expected to have a capacity of up to 550 million cubic feet of gas per day.

IOG intends to use the pipeline to carry its entire portfolio of gas in the southern North Sea.

Development its assets are ongoing, with the company expecting to proceed to a final investment decision and obtain field development plan approval in the fourth quarter of 2018.

The company has revised its southern North Sea project "to reflect the optimal timing for both fabrication and installation of key infrastructure".

As such, delivery of phase one offshore installation is to commence "immediately after the 2019-20 winter season", rather than the fourth quarter of 2019 as originally scheduled.

Related Shares

More News
11 Oct 2023 13:15

IOG appoints administrators to evaluate financial position

(Alliance News) - IOG PLC on Wednesday said it has appointed joint administrators, which are now evaluating the company's position.

28 Sep 2023 17:14

IOG shares suspended as places itself in administration

(Alliance News) - IOG PLC shares were suspended from trading on AIM on Thursday, after it said it will be placed into administration.

13 Sep 2023 11:49

LONDON MARKET MIDDAY: Stocks down as investors wait for US inflation

(Alliance News) - Stock prices in London were lower at midday Wednesday as investors eyed a key US inflation reading later in the day, ahead of the Fe...

13 Sep 2023 11:18

IOG says Blythe H2 well efficiency up but gas rate down in August

(Alliance News) - IOG PLC on Wednesday said operating efficiency for the Blythe H2 well in the UK North Sea was up in August compared to the year-to-d...

13 Sep 2023 10:52

AIM WINNERS & LOSERS: IOG down on "challenging" financial position

(Alliance News) - The following stocks are the leading risers and fallers on AIM in London on Wednesday.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.