Sierra Rutile Provides Q4 2012 Operational Update

9 Jan 2013 11:05

RNS Number : 1618V
Sierra Rutile Limited
09 January 2013
 

Sierra Rutile Limited

Sierra Rutile Provides Q4 2012 Operational Update

 

London, UK, 9 January 2013: Sierra Rutile Limited (AIM: SRX) ("SRL") is pleased to provide an operational update on developments during the fourth quarter of 2012 ("Q4" or "the Period") and the 2012 year.

 

Highlights:

·; Full-year 2012 rutile production of 94,493 tonnes, a 39% increase on 2011 production;

 

·; Full-year 2012 ilmenite production of 22,008 tonnes, a 38% increase on 2011 production;

 

·; Q4 production of 25,502 tonnes of rutile and 6,378 tonnes of ilmenite, both ahead of budget;

·; Lanti Dry Mining construction completed and commissioning commenced on budget and ahead of schedule. First product produced from Lanti Dry Mining concentrator.

·; Exceptional new Gangama Dry Mining project announced:

- US$507m pre-tax NPV10;

- 238% pre-tax IRR;

- 8-month project payback; and

- Detailed engineering work and project implementation plan underway.

·; Scoping study on Sembehun Dredge completed, providing long-term, low-cost production optionality for SRL with compelling economics:

- US$347m pre-tax NPV10;

- 34% pre-tax IRR; and

- 22-year project life.

Production

 

Full-year 2012 production was 94,493 tonnes of rutile and 22,008 tonnes of ilmenite, respectively 39% and 38% ahead of 2011 volumes (2011: 67,916 tonnes of rutile and 15,946 tonnes of ilmenite). This strong result was contributed towards by Q4 production of 25,502 tonnes of rutile and 6,378 tonnes of ilmenite.

 

 

Expansion projects

 

Construction of the Lanti Dry Mining plant was completed during the quarter and commissioning commenced. First ore was successfully processed through the concentrator and the concentrate transferred for onward processing in the mineral separation plant. Production ramp-up is continuing.

 

A significant change in SRL's expansion plans was announced on 31 October 2012 with the completion of a pre-feasibility study into the dry mining of the Gangama deposit ("Gangama Dry Mining). The pre-feasibility study reported an exceptional project with a pre-tax NPV10 of US$507 million, an impressive 238% pre-tax IRR and a payback period of just 8 months. Furthermore, as it replicates, on a larger scale, the Lanti Dry Mining project that was successfully completed within the quarter, Gangama Dry Mining represents a much lower-risk option of increasing SRL's production to the 200,000 tonnes per annum level. SRL has commenced detailed engineering work and a project implementation plan on the project in order to fast-track its development.

 

The Gangama Dry Mining project has replaced the new large dredge in SRL's near-term expansion plans. The feasibility study into the new large dredge has, however, been modified into a scoping study on the dredging of SRL's Sembehun deposit (the original feasibility involved the dredging of Gangama followed by Sembehun). This study yielded a pre-tax NPV10 of US$347 million, a 34% pre-tax IRR and a project life of 22 years, and provides a low-cost, long-term option for the development of SRL's assets.

 

 

Financing

 

SRL currently holds $24.6 million of cash and has inventory on hand of 22.9k tonnes of rutile.

 

 

Sales

 

Prices for Q4 have remained, as with Q3, at softer levels than in the first half of 2012. These prices remain, however, at very high levels when compared to historical prices for all SRL's products. Furthermore, SRL remains positive regarding the medium- and long-term demand for its products, and expects to see a strengthening of the market during 2013.

 

 

Commenting on the fourth quarter performance, CEO John Sisay said: "The quarter has seen further major advancements for SRL. Firstly, we have successfully implemented our first new production expansion, demonstrating that we can bring on new projects as well as restoring our existing assets to much higher levels of sustainable operation. Secondly, we have identified an exceptional new project with Gangama Dry Mining that is already low-risk, having just implemented a similar project at Lanti, but which also has highly impressive project economics. Finally, we have confirmed SRL's ability to be a meaningful low-cost and long-term producer of rutile with the Sembehun Dredge. We enter 2013 in an extremely robust shape and expect similar success for the coming year."

 

ENDS

For Further Information:

Sierra Rutile Limited

Yves Ilunga

Chief Financial Officer

 

 

+44 (0)20 7074 1800

RBC Capital Markets

Nominated Adviser and Joint Corporate Broker

Martin Eales / Jonathan Hardy

 

 

+44 (0)20 7653 4000

Mirabaud Securities

Joint Corporate Broker

Peter Krens

 

 

+44 (0)20 7321 2508

Kreab Gavin Anderson

Andy Jones/ Anthony Hughes

 

+44 (0)20 7074 1800

 

 

Notes to Editors

 

About Sierra Rutile Limited

 

Sierra Rutile produces titanium feedstock industrial minerals (primarily rutile, with some associated ilmenite), as well as smaller quantities of zircon. Sierra Rutile's mine, located in the south west of Sierra Leone, is one of the largest natural rutile deposits in the world, with a JORC-Compliant Mineral Resource for measured, indicated and inferred resources for the Sierra Rutile mine of over 600 million tonnes (as at February 2011).

www.sierra-rutile.com

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTBBGDBXGGBGXC
Date   Source Headline
7th Dec 20167:30 amRNSSuspension - Sierra Rutile Limited
6th Dec 201612:56 pmRNSMerger Update
5th Dec 20167:00 amRNSForm 8.3 - Iluka Resources
2nd Dec 20167:00 amRNSForm 8.3 - Iluka Resources
29th Nov 20167:00 amRNSMerger Update
25th Nov 20167:00 amRNSMerger Update
22nd Nov 20167:00 amRNSForm 8.3 - [offeree/offeror] - Iluka Resources
21st Nov 20162:39 pmRNSGerman Antitrust Authority Clearance Granted
17th Nov 20167:00 amRNSForm 8.3 - Iluka Resources
4th Nov 201610:00 amRNSMerger Update
3rd Nov 20167:00 amRNSRefinancing of Bank Facilities
3rd Nov 20167:00 amRNSForm 8.3 - Iluka Resources
27th Oct 20167:00 amRNSForm 8.3 - Iluka Resources Limited
26th Oct 20167:00 amRNSMerger Update
21st Oct 20167:00 amRNSQ3 2016 Operational Update
18th Oct 20167:00 amRNSForm 8.3 - Iluka Resources Limited
30th Sep 20167:09 amRNSSierra Rutile Limited H1 2016 Interim Results
29th Sep 20167:00 amRNSForm 8.3 - Iluka Resources Limited
26th Sep 20167:00 amRNSForm 8.3 - Iluka Resources Limited
15th Sep 20167:00 amRNSMerger Update
14th Sep 20167:00 amRNSMerger Update
6th Sep 20167:04 amRNSMerger Update
5th Sep 20167:00 amRNSForm 8.3 - Iluka Resource Ltd
2nd Sep 20167:00 amRNSForm 8.3 - Iluka Resources Limited
1st Sep 20164:28 pmRNSMerger Update
1st Sep 20167:00 amRNSForm 8.3 - Iluka Resources
25th Aug 20167:00 amRNSMerger Update
22nd Aug 20167:00 amRNSForm 8.3 - Iluka Resources Limited
12th Aug 20167:00 amRNSForm 8.3 - Iluka Resources Limited
11th Aug 20167:00 amRNSForm 8.3 - Iluka Resources Limited
10th Aug 20167:00 amRNSForm 8.3 - Iluka Resources Limited
9th Aug 20167:00 amRNSStatement regarding disposal of company or assets
9th Aug 20167:00 amRNSForm 8.3 - Iluka Resources Limited
3rd Aug 20167:00 amRNSForm 8.3 - Iluka Resources Limited
2nd Aug 20167:00 amRNSForm 8.3 - Iluka Resources Ltd.
1st Aug 20167:00 amRNSRecommended proposal for Sierra Rutile by Iluka
1st Aug 20167:00 amRNSForm 8.3 - Iluka Resources Ltd.
29th Jul 20167:18 amRNSAnnouncement re Iluka Resources Limited
15th Jul 20167:00 amRNSQ2 and Half-Year 2016 Operational Update
6th Jul 20163:43 pmRNSResults of AGM
2nd Jun 20167:00 amRNSSuccessful Gangama Dry Mine Commissioning
31st May 20167:00 amRNSTotal Voting Rights and Block Listing Return
28th Apr 20167:00 amRNSAnnual Financial Report and Accounts
26th Apr 20167:00 amRNSOperational Update
21st Apr 20167:00 amRNSNotification of Major Interest in Shares
21st Apr 20167:00 amRNSNotification of Major Interest in Shares
19th Apr 20168:50 amRNSAdmission Announcement
15th Apr 20162:08 pmRNSFull Exercise of Bookrunner Option
14th Apr 20167:00 amRNSSuccessful placing of $20.0 million in new equity
31st Mar 20167:00 amRNSPreliminary Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.