Kiliwani North Update

6 Jun 2016 07:00

RNS Number : 2428A
Solo Oil Plc
06 June 2016
 

FOR IMMEDIATE RELEASE, 7 am 6 June 2016

 

 

SOLO OIL PLC

("Solo" or the "Company")

 

Kiliwani North Update

Solo Oil plc has received an update from the Kiliwani North production operations in Tanzania from the operator Ndovu Resources Limited (a subsidiary of Aminex plc) ("Ndovu") and is pleased to provide the following highlights:

· Commissioning of the power generation system and other auxiliary facilities has been completed.

· Commissioning of the gas plant and sub-sea pipeline commenced on 1 June 2016

· On 2 June the first Kiliwani North-1 ("KN-1") gas was processed and entered the pipeline system connecting the Songo Songo plant with the national pipeline.

· During the commissioning, gas rates are planned to ramp up to 30 mmscfd while pressuring up the plant and pipeline.

· Ndovu and its partners have invoiced for April and May gas production in accordance with the terms of the signed Gas Sales Agreement ("GSA").

 

As previously advised, all gas produced during the build-up to full production rates will be paid for under the terms of the GSA signed with the sole buyer, Tanzania Petroleum Development Corporation ("TPDC"). Solo will receive US$3.00 per mmbtu (approximately US$3.07 per mcf) with expected net cash revenues of US$1-1.5 million per annum.

 

Initial production rates remain carefully managed to allow for testing and commissioning of the gas processing plant and pipeline, while recording critical pressure and flow rate measurements to determine the optimal flow rate to maximize the life of the reservoir. Together with TPDC the operator plans to conduct a well test during the production build up to determine the optimal flow rate. It is this optimal flow rate that will become the Commercial Production Rate under the GSA and the Ndovu intends to flow gas at that rate for as long as possible prior to a natural decline in production. Based on the initial pressure response from the KN-1 well it is expected that the well will be operated at approximately 30 mmcfd gross (4,500 barrels of oil equivalent per day).

Neil Ritson, Solo's Chairman commented:

"I visited the Songo Songo gas plant last week and was very impressed with the quality of the facilities and the progress being made with commissioning. I am encouraged by the work that has been undertaken by TDPC and Aminex, and expect that we will now reach the expected offtake rate in the next few months."

Qualified Person's Statement:

The information contained in this announcement has been reviewed and approved by Neil Ritson, Chairman and Director for Solo Oil Plc who has over 38 years of relevant experience in the energy sector. Mr. Ritson is a member of the Society of Petroleum Engineers, an Active Member of the American Association of Petroleum Geologists and is a Fellow of the Geological Society of London.

For further information:

Solo Oil plc

Neil Ritson

+44 (0) 20 3794 9230

 

 

Beaumont Cornish Limited

Nominated Adviser and Joint Broker

Roland Cornish

+44 (0) 20 7628 3396

 

Shore Capital

Joint Broker

Jerry Keen (Corporate Broker)

 

Bell Pottinger

Public Relations

Henry Lerwill

 

Cassiopeia Services LLP

Investor Relations

Stefania Barbaglio

 

+44 (0) 20 7408 4090

 

 

 

 

 

+44 (0) 20 3772 2500

 

 

 

+44 (0) 79 4969 0338

 

Notes to editors

 

Solo's assets in Tanzania comprise:

Kiliwani North Development Licence ("KNDL") (7.175%, non-operator)

The Kiliwani North Field has been independently estimated to contain 28 bcf gross contingent (2C) resource and will produce dry clean gas under high natural pressure (1,600 psi) from a high quality Neocomian late Cretaceous reservoir.  The Kiliwani North-1 well was tested at 40 mmcfd. The gas will be sold at the well head in $US at a fixed price and fed directly into the Tanzania's new pipeline infrastructure to Dar es Salaam. Solo holds options to increase its equity in the KNDL to 10% as certain project milestones are achieved.

Ruvuma Production Sharing Agreement (25%, non-operator)

The Ruvuma PSC acreage includes Solo's Ntorya-1 onshore Cretaceous gas discovery which has been independently ascribed 70 bcf gross contingent (2C) resource in the Ruvuma Basin. The well tested at 20 mmcfd. Appraisal drilling is anticipated to commence in 2016.

 

Glossary:

bcf

billion cubic feet

contingent resources

those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations, but the applied project(s) are not yet considered mature enough for commercial development due to one or more contingencies

GSA

gas sales agreement

KN-1

Kiliwani North-1 well

KNDL

Kiliwani North Development Licence

mmbtu

million British thermal units

mscf

thousand standard cubic feet

mmscfd

million standard cubic feet of gas per day

PSC

Petroleum Sharing Contract

reserves

reserves are defined by the SPE as those quantities of petroleum, here oil and gas, which are anticipated to be commercially recovered from known accumulations from a given date forward

TPDC

the Tanzanian Petroleum Development Corporation

US$

United States of America dollars

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSSFFALFMSESM
Date   Source Headline
26th Apr 200712:04 pmRNSAppointment of Broker
20th Apr 20075:45 pmRNSOffer Update
11th Apr 20074:31 pmRNSChange of Name
11th Apr 200711:28 amRNSResult of EGM
5th Apr 20074:48 pmRNSFurther re acquisition
30th Mar 20071:46 pmRNSFirst Closing Date
26th Mar 200712:09 pmRNSSch 1 - St James's Energy plc
15th Mar 200712:30 pmRNSAcquisition
15th Mar 200712:30 pmRNSRestoration - St James's Ener
7th Mar 20073:45 pmRNSStatement re.Reverse Takeover
7th Mar 20073:45 pmRNSSuspension-St James's Energy
23rd Feb 200712:50 pmRNSAnnual Report and Accounts
22nd Feb 20073:01 pmRNSAGM Statement
22nd Feb 200711:10 amRNSFinal Results
7th Feb 20072:01 pmRNSNotice of AGM
18th Dec 20064:27 pmRNSTotal Voting Rights
31st Jul 20066:24 pmRNSInterim Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.