We would love to hear your thoughts about our site and services, please take our survey here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksRMM.L Regulatory News (RMM)

  • There is currently no data for RMM

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Q1 2017 Production Results & Development Update

9 May 2017 07:00

RNS Number : 5242E
Rambler Metals & Mining PLC
09 May 2017
 

9 May 2017

Rambler Releases Q1 2017 Production Results & Development Update

 

London, England - Newfoundland and Labrador, Canada - Rambler Metals and Mining plc (TSXV: RAB, AIM: RMM) ("Rambler" or "the Company"), a copper and gold producer, explorer, and developer today provides production results for first quarter ended 31 March 2017 ('Q1/17').

 

Q1/17 Production Summary

· Copper feed grade of 1.13% with gold grades of 0.30 g/t. Total mill throughput for the period ending was 75,438 dry metric tonnes ('dmt'). During the period the plant averaged 910 metric tonnes per day ('mtpd') during operational hours.

· Average recoveries to concentrate for the quarter were: copper 96.6% and gold 64.0% with a concentrate grade of 28.2% and 5.2 g/t for copper and gold respectively.

o The mill produced 2,930 dmt of concentrate containing saleable metal of 794 tonnes of copper and 391 ounces of gold.

Development Update

· Mining focus in the first quarter was on the underground development necessary to achieve the company's growth target of sustainable production of 1,250 mtpd during the second half of the calendar year.

· Heavy underground development into the Lower Footwall continued during the quarter.

· Mill throughput averaged 910 mtpd per operational hour, with final plant modifications being made to allow for 1,250 mtpd. All work to be completed over the coming months.

· Rambler is on track to reach sustainable production of 1,250 mtpd during the second half of the calendar year.

 

Norman Williams, President and CEO, commented:

"The primary focus during the second quarter was on the development meters necessary to achieve our longer term mine plan of 1,250 mtpd, with a balance of development and stoping mineralization. As a result, mill feed grade was less than guidance for the period. This lower grade is a result of increased processing of low grade development ore while we continue to push underground headings in preparation for sustainable mining at 1,250 mtpd. We expect this trend to continue until the end of the second quarter when are expected to improve. Completing the primary and secondary development now is necessary to support the higher mining rate in the long term mine plan.

 

"At the end of the period mill throughput averaged 910 mtpd, for operational ran. Only minor plant modifications remain to push for our target throughput of 1,250 mtpd. These modifications will be made over the coming months in time for sustained production from the mine."

Q1 2017 Production Summary

 

The table below summarizes the production results for Q1/17 ending March 31, 2017.

 

Table 1 - Q1/17 Production Results with 2017 Guidance

(See Note 1 below)

 

PRODUCTION

Q1

2017

F2017

Guidance

Dry Tonnes Milled

75,438

350,000 - 400,000

Copper Recovery (%)

96.6

94 - 96

Gold Recovery (%)

64.0

65 - 70

Copper Head Grade (%)

1.13

1.3 - 1.6

Gold Head Grade (g/t)

0.3

0.5 - 1.0

 

CONCENTRATE

 

Copper grade (%)

28.2

26 - 28

Gold grade (g/t)

5.2

4.0 - 8.0

Dry Tonnes Produced

2,930

18,000 - 22,000

 

SALEABLE METAL

 

Copper (tonnes)

794

5,100 - 5,800

Gold (ounces)

391

4,400 - 5,100

 

 

 

Table 2 - Quarter over Quarter Results Comparison 

(see Note 1 below)

PRODUCTION

Q4/16

Q1/17

Q1/16

Q1/17

Dry Tonnes Milled

72,036

75,438

5%

58,362

75,438

29%

Copper Recovery

94.1

96.6

0%

96.3

96.6

0%

Gold Recovery

70.5

64.0

-9%

71.4

64.0

-10%

Copper Head Grade (%)

1.36

1.13

-17%

2.28

1.13

-50%

Gold Head Grade (g/t)

0.56

0.3

-46%

1.72

0.3

-82%

 

CONCENTRATE

 

Copper (%)

26.8

28.2

5%

27.1

28.2

4%

Gold (g/t)

9.2

5.2

-44%

16.3

5.2

-68%

Dry Tonnes Produced

3,168

2,930

-8%

4,260

2,930

-31%

 

SALEABLE METAL

 

Copper Metal (tonnes)

850

794

-7%

1,107

794

-28%

Gold (ounces)

865

391

-55%

2,096

391

-81%

ABOUT RAMBLER METALS AND MINING

Rambler is a mining and development company that in November 2012 brought its first mine into commercial production. Rambler has a 100 per cent ownership in the Ming Copper-Gold Mine, a fully operational base and precious metals processing facility and year round bulk storage and shipping facility; all located on the Baie Verte peninsula, Newfoundland and Labrador, Canada.

Rambler's ongoing Phase II plans are to increase mine and mill production to 1,250 mtpd by mid calendar 2017. This initial expansion has been fully funded through CEII's investment. Rambler will also continue advancing engineering studies on ore pre-concentration (DMS) and shaft rehabilitation with a view to further increase production to 2,000 mtpd at the Ming Mine. In addition, Rambler has initiated a detailed study at the mill with a goal to increase the gold recovery and production rate in the copper concentrator.

Along with the Ming Mine, Rambler also owns 100 per cent of the former producing Little Deer/ Whales Back copper mines and has strategic investment in the former producing Hammerdown gold mine.

 

Rambler is dual listed in London under AIM:RMM and in Canada under TSX-V:RAB.

 

For further information, please contact:

 

Norman Williams, CPA,CA

President and CEO

Rambler Metals & Mining Plc

Tel No: 709-800-1929

Fax No: 709-800-1921

Peter Mercer

Vice President, Corporate Secretary

Rambler Metals & Mining Plc

Tel No: +44 (0) 20 8652-2700

Fax No: +44 (0) 20 8652-2719

 

Nominated Advisor (NOMAD)

 

Investor Relations

David Porter, Craig Francis

Cantor Fitzgerald Europe

Tel No: +44 (0) 20 7894 7000

Nicole Marchand Investor Relations

Tel No: 416- 428-3533

Nicole@nm-ir.com

 

Website: www.ramblermines.com 

 

 

Larry Pilgrim, P.Geo., is the Qualified Person responsible for the technical content of this release and has reviewed and approved it accordingly. Mr. Pilgrim is an independent consultant contracted by Rambler Metals and Mining Canada Limited. Tonnes referenced are dry metric tonnes unless otherwise indicated.

Note 1: Results reported are accurate and reflective as of the date of release. The Company performs regular auditing and reconciliation reviews on its mining and milling processes as well as stockpile inventories, following which past results may be adjusted to reflect any changes.

 

Neither TSX Venture Exchange nor its Regulation Service Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ('MAR'). Upon the publication of this announcement via Regulatory Information Service ('RIS'), this inside information is now considered to be in the public domain.

 

Caution Regarding Forward Looking Statements:

Certain information included in this press release, including information relating to future financial or operating performance and other statements that express the expectations of management or estimates of future performance constitute "forward-looking statements". Such forward-looking statements include, without limitation, statements regarding copper, gold and silver forecasts, the financial strength of the Company, estimates regarding timing of future development and production and statements concerning possible expansion opportunities for the Company. Where the Company expresses or implies an expectation or belief as to future events or results, such expectation or belief are based on assumptions made in good faith and believed to have a reasonable basis. Such assumptions include, without limitation, the price of and anticipated costs of recovery of, copper concentrate, gold and silver, the presence of and continuity of such minerals at modeled grades and values, the capacities of various machinery and equipment, the availability of personnel, machinery and equipment at estimated prices, mineral recovery rates, and others. However, forward-looking statements are subject to risks, uncertainties and other factors, which could cause actual results to differ materially from future results expressed, projected or implied by such forward-looking statements. Such risks include, but are not limited to, interpretation and implications of drilling and geophysical results; estimates regarding timing of future capital expenditures and costs towards profitable commercial operations. Other factors that could cause actual results, developments or events to differ materially from those anticipated include, among others, increases/decreases in production; volatility in metals prices and demand; currency fluctuations; cash operating margins; cash operating cost per pound sold; costs per ton of ore; variances in ore grade or recovery rates from those assumed in mining plans; reserves and/or resources; the ability to successfully integrate acquired assets; operational risks inherent in mining or development activities and legislative factors relating to prices, taxes, royalties, land use, title and permits, importing and exporting of minerals and environmental protection. Accordingly, undue reliance should not be placed on forward-looking statements and the forward-looking statements contained in this press release are expressly qualified in their entirety by this cautionary statement. The forward-looking statements contained herein are made as at the date hereof and the Company does not undertake any obligation to update publicly or revise any such forward-looking statements or any forward-looking statements contained in any other documents whether as a result of new information, future events or otherwise, except as required under applicable security law

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDDMGGKRRGGNZM
Date   Source Headline
27th Apr 20237:00 amRNSBlock Listing Six Monthly Return
21st Apr 20237:00 amRNSUpdate – Creditors Voluntary Liquidation
17th Apr 20237:00 amRNSSale and Investment Solicitation Process
12th Apr 20231:53 pmRNSCompany Website Update
11th Apr 20235:45 pmRNSRambler Metals & Mining
11th Apr 20237:00 amRNSCreditors Voluntary Arrangement and Cancellation
6th Apr 20234:27 pmRNSMaterials publicly filed in the CCAA Proceedings
4th Apr 20232:42 pmRNSCompany Website
30th Mar 20238:33 amRNSOperational Update
24th Mar 20232:33 pmRNSGrant and Vesting of Restricted Share Units
17th Mar 20231:54 pmRNSMaterials publicly filed in the CCAA Proceedings
16th Mar 20233:58 pmRNSCCAA Proceedings
14th Mar 20239:12 amRNSMaterials publicly filed in the CCAA Proceedings
8th Mar 20237:00 amRNSMaterials publicly filed in the CCAA Proceedings
7th Mar 20237:00 amRNSCorrection: Materials publicly filed
6th Mar 20236:15 pmRNSMaterials publicly filed in the CCAA Proceedings
28th Feb 20236:15 pmRNSMaterials publicly filed in the CCAA Proceedings
28th Feb 20237:00 amRNSRambler Announces Strategic Process
27th Feb 20237:00 amRNSApplication for Initial Order for CCAA Protection
20th Feb 20237:00 amRNSUpdate on Gold Stream Repurchase Agreement
17th Feb 20237:00 amRNSUpdate on Financing and Operations
10th Feb 20237:00 amRNSUpdate on Gold Streaming Agreement
18th Jan 20237:00 amRNSQ4 2022 Operational Results
5th Dec 20223:49 pmRNSForward Sale on Copper Production
15th Nov 20227:00 amRNSForward Sale on Copper Production
10th Nov 20229:28 amRNSRambler Provides an Operational Update
1st Nov 20227:00 amRNSRambler Provides an Update on Financial Position
27th Oct 20227:30 amRNSSuspension - Rambler Metals & Mining PLC
27th Oct 20227:01 amRNSBlock Listing Six Monthly Return
27th Oct 20227:00 amRNSRambler Provides an Update on Financial Position
21st Oct 20227:00 amRNSQ3 2022 Operational Results
3rd Oct 20229:05 amRNSSecond Price Monitoring Extn
3rd Oct 20229:00 amRNSPrice Monitoring Extension
30th Sep 20222:06 pmRNSSecond Price Monitoring Extn
30th Sep 20222:00 pmRNSPrice Monitoring Extension
28th Sep 20224:41 pmRNSSecond Price Monitoring Extn
28th Sep 20224:35 pmRNSPrice Monitoring Extension
27th Sep 20224:40 pmRNSSecond Price Monitoring Extn
27th Sep 20224:35 pmRNSPrice Monitoring Extension
27th Sep 20222:00 pmRNSPrice Monitoring Extension
26th Sep 20224:32 pmRNSFinancial Results Half Year Ended 30 June 2022
15th Sep 20222:05 pmRNSSecond Price Monitoring Extn
15th Sep 20222:00 pmRNSPrice Monitoring Extension
13th Sep 20224:41 pmRNSSecond Price Monitoring Extn
13th Sep 20224:35 pmRNSPrice Monitoring Extension
9th Sep 20224:40 pmRNSSecond Price Monitoring Extn
9th Sep 20224:35 pmRNSPrice Monitoring Extension
9th Sep 202212:19 pmRNSRambler Provides a Corporate Update
1st Sep 20227:00 amRNSSignificance of Stope In-fill Drilling Program
23rd Aug 20227:00 amRNSRambler Updates 2022 Diamond Drilling Program

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.