Rift Oil plc
("Rift")
Puk Puk Update
The Directors of Rift are delighted to provide the following update on testing at Puk Puk.Β
Testing commenced on 24 SeptemberΒ 2008. During initial clean-up flow to flare, of the combined Toro and Lower Hedinia pay intervals, a calculatedΒ gasΒ flow rate of 29.2 million cubic feet per day was achievedΒ on a 64/64" choke, at a surface flowing pressure in excess of 1200 psi. A separate flow on theΒ Lower HediniaΒ alone was measured at 20.85 mmcf/d on 48/64" choke, with a surface flowing pressure of 1732 psi.
The forward programme is toΒ isolate and flow each of the Toro and Lower Hedinia through the separator equipment, followed by the clean up and separator flow test of the Upper Hedinia.Β Separator equipment is on site to provide a measure of the liquids yield of the gas, once flow rates have stabilised.
Ian Gowrie-Smith, Chairman, commented:
Β "We are very pleased with these initial flow rates, which are in line withΒ what we expectedΒ from theΒ well developed Toro reservoir. TheΒ Lower HediniaΒ rate from thinner sands is also highly encouraging. We look forward toΒ reporting on the completedΒ testing programme duringΒ October, at which point we will be able to give a fuller analysis."
Peter Mikkelsen FGS, AAPG, as the qualified non-executive Director has reviewed this statement and authorised its release.
Further enquiries:
|
Rift |
|
|
David Lees, Ian Gowrie-Smith |
020 7340 9970 |
|
Buchanan Communications |
|
|
Tim Anderson, Isabel Podda |
020 7466 5000 |
|
RBC Capital Markets |
|
|
Andrew Smith, Sarah Wharry |
020 7653 4804 |
Follow the stocks