Pin to quick picksPremier African Minerals Regulatory News (PREM)

Share Price Information for Premier African Minerals (PREM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.1925
Bid: 0.185
Ask: 0.20
Change: 0.0025 (1.32%)
Spread: 0.015 (8.108%)
Open: 0.19
High: 0.1925
Low: 0.1875
Prev. Close: 0.19
PREM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Zulu Lithium Plant Update

10 Apr 2024 12:00

RNS Number : 0549K
Premier African Minerals Limited
10 April 2024
 

Premier African Minerals Limited / Ticker: PREM / Index: AIM / Sector: Mining

For immediate release

 

10 April 2024

Premier African Minerals Limited

 

 Zulu Lithium Plant Update

 

Premier African Minerals Limited ("Premier" or the "Company") is pleased to provide an update on progress at operations at Zulu Lithium and Tantalum ("Zulu") since the Zulu engineering team took responsibility over the operation and management of the plant in March.

 

Highlights:

 

Ø

Ore grade and contained spodumene in the ore fed to the plant is at grades consistently ranging from 1.1% Li20 to 1.7% Li2O.

 

Ø

Stability in the comminution circuit has now been attained and the new mill and jet sizers are now consistently able to provide the required tonnage of correctly sized material to the thickener.

 

Ø

The OEM for the float plant and thickener is now finally able to properly optimise and fully commission the floatation plant.

 

The Zulu Plant

Preliminary finding from the independent EPCM contractor (as announced on 13 March 2024) has confirmed a number of design issues related to the flow of material between various components of the plant.

This affected the comminution and material sizing plant components. Material flows from mill discharge to thickener feed are now stable.

All efforts are now focussed on the floatation plant. The key issues fall into two categories as set out below together with current remedial actions and anticipated timelines.

Throughput

In original test work, mica content was estimated at 17%. In early processing actual mica content is closer to 27%. This is currently restricting throughput to approximately 26 tons per hour of dry solids and the theoretical SC6 output is 4.5 ton per hour until certain pumps and valves in the mica section are upgraded. The OEM expects these components to be at site over the course of April to enable an increase in throughput to the target rate of approximately 37 tons per hour.

Grade and Recovery

Whilst the plant has demonstrated its capability to produce SC6 to grade, it is not able to do so consistently and achieve the desired and required recoveries at present. The reasons include circulation between float cells, resident time in float cells, and "in cell" slurry density. Our Zulu engineering team in conjunction with the OEM team has identified both the cause and the remedy and is in the process of attending to flow changes between the various floatation cells. This problem is expected to be rectified in the coming weeks.

George Roach, CEO commented, "Premier believes we are now in the home stretch with commissioning the Zulu plant operation.

 

Our team at Zulu and our OEMs should be commended for what has been achieved in the past 5 weeks and Premier looks forward to finally getting this plant over the line. We have greater than 1,000 tons of mixed mica rich and spodumene concentrate (not to grade) and with recent price improvements we are exploring ways to commercially release some value for the product available. SC6 will be held back until we have sufficient at grade material to ship to our prepayment and off-take partner.

 

Premier need to express its deep appreciation to all who have stuck with us through this tortuous journey and to our prepayment and off-take partner for their understanding and support."

 

Market Abuse Regulations

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it forms part of UK Domestic Law by virtue of the European Union (Withdrawal) Act 2018 ("UK MAR").

The person who arranged the release of this announcement on behalf of the Company was George Roach.

A copy of this announcement is available at the Company's website, www.premierafricanminerals.com

Enquiries:

 

George Roach

Premier African Minerals Limited

Tel: +27 (0) 100 201 281

Michael Cornish / Roland Cornish

Beaumont Cornish Limited

(Nominated Adviser)

Tel: +44 (0) 20 7628 3396

Douglas Crippen

CMC Markets UK Plc

Tel: +44 (0) 20 3003 8632

Toby Gibbs/Rachel Goldstein

Shore Capital Stockbrokers Limited

Tel: +44 (0) 20 7408 4090

 

Nominated Adviser Statement Beaumont Cornish Limited ("Beaumont Cornish"), which is authorised and regulated in the United Kingdom by the Financial Conduct Authority, is acting as nominated adviser to the Company in connection with this announcement and will not regard any other person as its client and will not be responsible to anyone else for providing the protections afforded to the clients of Beaumont Cornish or for providing advice in relation to such proposals. Beaumont Cornish has not authorised the contents of, or any part of, this document and no liability whatsoever is accepted by Beaumont Cornish for the accuracy of any information, or opinions contained in this document or for the omission of any information. Beaumont Cornish as nominated adviser to the Company owes certain responsibilities to the London Stock Exchange which are not owed to the Company, the Directors, Shareholders, or any other person.

Forward Looking Statements

Certain statements in this announcement are or may be deemed to be forward looking statements. Forward looking statements are identified by their use of terms and phrases such as ''believe'' ''could'' "should" ''envisage'' ''estimate'' ''intend'' ''may'' ''plan'' ''will'' or the negative of those variations or comparable expressions including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the Company's future growth results of operations performance future capital and other expenditures (including the amount. Nature and sources of funding thereof) competitive advantages business prospects and opportunities. Such forward looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements including risks associated with vulnerability to general economic and business conditions competition environmental and other regulatory changes actions by governmental authorities the availability of capital markets reliance on key personnel uninsured and underinsured losses and other factors many of which are beyond the control of the Company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The Company cannot assure investors that actual results will be consistent with such forward looking statements.

Glossary

"EPCM"

Engineering, Procurement and Construction Management.

"Li2O"

 

Lithium Oxide (Lithia) - an inorganic lithium compound used to assess lithium minerals.

"OEM"

Original Equipment Suppliers.

"SC6"

spodumene concentrate.

 

Notes to Editors:

Premier African Minerals Limited (AIM: PREM) is a multi-commodity mining and natural resource development company focused on Southern Africa with its RHA Tungsten and Zulu Lithium projects in Zimbabwe.

 

The Company has a diverse portfolio of projects, which include tungsten, rare earth elements, lithium and tantalum in Zimbabwe and lithium and gold in Mozambique, encompassing brownfield projects with near-term production potential to grass-roots exploration. The Company has accepted a share offer by Vortex Limited ("Vortex") for the exchange of Premier's entire 4.8% interest in Circum Minerals Limited ("Circum"), the owners of the Danakil Potash Project in Ethiopia, for a 13.1% interest in the enlarged share capital of Vortex. Vortex has an interest of 36.7% in Circum.

 

Ends

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDBGGDSXUBDGSG
Date   Source Headline
12th Apr 20247:00 amRNSAdditional Funding for Zulu
11th Apr 20247:00 amRNSFunding of Zulu Project and Update
10th Apr 202412:00 pmRNSZulu Lithium Plant Update
8th Apr 20244:00 pmRNSResult of AGM
27th Mar 20245:00 pmRNSAGM Link and Shareholder Presentation
20th Mar 20246:00 pmRNSNotice of AGM
13th Mar 202411:00 amRNSZulu Lithium Plant and General Update
29th Feb 20246:00 pmRNSZulu Lithium Plant Update
26th Feb 20241:00 pmRNSZulu Lithium Plant Update
19th Feb 20246:00 pmRNSDirector Loan
15th Feb 20247:00 amRNSFunding of Zulu Project and Update
9th Feb 20247:00 amRNSNew Mineral Resource Statement Zulu
29th Jan 202411:15 amRNSOfftake and Prepayment Agreement
24th Jan 20247:00 amRNSZulu Lithium Update
18th Jan 20249:00 amRNSZulu Lithium Update
9th Jan 20247:00 amRNSZulu Assay Results and Update
11th Dec 202311:20 amRNSFunding of Zulu Project and Update
7th Dec 20233:00 pmRNSZulu Project and Update
20th Nov 20231:20 pmRNSZulu Update
14th Nov 202311:00 amRNSZulu Update
3rd Nov 20232:30 pmRNSZulu and Corporate Update
29th Sep 20237:05 amRNSZulu Lithium Update
29th Sep 20237:00 amRNSInterim Results
21st Sep 20238:00 amRNSZulu Lithium Update
15th Sep 20237:05 amRNSHolding(s) in Company
15th Sep 20237:00 amRNSHolding(s) in Company
11th Sep 20237:00 amRNSApproval of further funding for Zulu Project
1st Sep 20236:00 pmRNSTotal Voting Rights
30th Aug 20237:00 amRNSZulu Lithium Additional Funding
25th Aug 20237:00 amRNSFunding of Zulu Project
23rd Aug 20237:30 amRNSZulu Update
18th Aug 20233:23 pmRNSDirector/PDMR Shareholding
15th Aug 20231:30 pmRNSOfftake and Prepayment Agreement
14th Aug 20237:00 amRNSResult of Meeting
9th Aug 20236:00 pmRNSDirector Loan Update
21st Jul 20237:10 amRNSDirector's Loan
21st Jul 20237:00 amRNSNotice of GM
20th Jul 20237:00 amRNSOfftake and Prepayment Agreement Update
30th Jun 20232:57 pmRNSFinal Results
28th Jun 20234:37 pmRNSOfftake and Prepayment Agreement Update
26th Jun 20235:00 pmRNSResult of AGM
26th Jun 20237:00 amRNSOfftake and Prepayment Agreement Update
9th Jun 20237:00 amRNSNotice of AGM
6th Jun 202311:03 amRNSOfftake and Prepayment Agreement
25th May 20238:30 amRNSZulu Lithium Project Update
19th May 20237:00 amRNSFunding and Appointment of Joint Broker
15th May 20237:00 amRNSFunding of Ongoing Zulu Plant Optimisation
5th May 20235:00 pmRNSCorporate Update
28th Apr 20237:00 amRNSDirector / PDMR shareholding
27th Apr 20231:00 pmRNSZulu Lithium Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.