Cambay-77H Well - 4 ½ inch casing set and cemented

22 Apr 2014 07:01

RNS Number : 1892F
Oilex Ltd
21 April 2014
 

 

22 April 2014

 

 

CAMBAY-77H WELL - 4 ½ inch casing set and cemented

 

· Cambay-77H 4 ½ inch casing set and cemented on 19 April 2014

· Comprehensive set of logs obtained and initial interpretation completed

· Cambay-77H logs confirm a hydrocarbon bearing reservoir comparable to Cambay-76H and Cambay-73, which has produced from the Y zone.

· Essar Land Rig #4 preparing to demobilise from site

 

Oilex Ltd (ASX: OEX, AIM: OEX,) is pleased to announce that the 4 ½ inch production casing has been successfully set and cemented on 19 April 2014. The wellbore is now secured for the fracture stimulation programme. Essar Land Rig #4 is currently preparing to demobilise from the site. This may take up to three weeks, after which a further four weeks may be required to complete mobilisation of the fracture stimulation equipment, material and personnel in addition to the well test equipment and personnel.

As previously reported, the primary reservoir target (Y Zone) has been intersected on prognosis. A comprehensive suite of logs has been acquired and preliminary interpretation confirms the wellbore intersected a significant sequence of hydrocarbon-bearing reservoir similar to Cambay-76H. The Cambay-77H logs also compare favourably to Cambay-73 vertical well, which produced from the Y zone at ~1MMscfd plus condensate and is located approximately 1 km from Cambay-77H.

Cambay-77H is offset 300m from the Cambay-76H horizontal well that underwent a successful multiple staged fracture stimulation programme along its 633m lateral section in 2012. However, it was suspended before testing due to downhole mechanical problems. Prior to suspending the well, gas and condensate flowed to surface during well control operations.

A shorter lateral section (350m) in Cambay-77H coupled with a conventional "plug and perf" method for fracture stimulation is expected to facilitate the primary goal of the well - recording hydrocarbon flow information at surface during a production test.

The drilling operations are complete and Oilex will continue to inform the market about progress during the fracture stimulation work on a milestone basis as indicated below.

ü Setting and cementing of the 13 3/8 inch casing at approximately 590m MD

ü Setting and cementing of the 9 5/8 inch casing at approximately 1,650m MD

ü Completion of drilling operations at well TD, at approximately 2,360m MD

ü Setting and cementing of the 4 1/2 inch production casing

· Completion of mobilisation of the fracture stimulation spread to site

· Completion of the fracture stimulation programme

· Any announcements in relation to flow back and production testing will be dictated by the well response to the stimulation programme

Managing Director of Oilex, Ron Miller, said;

"Drilling operations are now complete after approximately 23 operational days, (excluding rig downtime) compared to 30 days as previously announced. We are encouraged by the amount of hydrocarbon-bearing reservoir penetrated as well as its apparent quality from the logs. We look forward to conducting the fracture stimulation programme and subsequent flow test to realise the full potential of this reservoir."

 

For and on behalf of Oilex Ltd

 

Ron Miller

Managing Director

 

For further information, please contact:

Oilex Ltd

Ron Miller, Managing Director

Email: oilex@oilex.com.au

Tel: +61 8 9485 3200

Australia

RFC Ambrian Limited

Nominated Adviser and AIM Broker

Samantha Harrison

Email: samatha.harrison@rfcambrian.com

Tel: +44 203 440 6800

UK

 

Tavistock Communications

Conrad Harrington

Email: charrington@tavistock.co.uk

Tel: +44 207 920 3150

UK

Qualified Petroleum Reserves and Resources Evaluator statement

 

Pursuant to the requirements of Chapter 5 of the ASX Listing Rules, the information in this report relating to petroleum reserves and resources is based on and fairly represents information and supporting documentation prepared by or under the supervision of Mr. Peter Bekkers, Chief Geoscientist employed by Oilex Ltd. Mr. Bekkers has over 15 years' experience in petroleum geology and is a member of the Society of Petroleum Engineers and AAPG. Mr. Bekkers meets the requirements of a qualified petroleum reserve and resource evaluator under Chapter 5 of the ASX Listing Rules and consents to the inclusion of this information in this report in the form and context in which it appears. Mr. Bekkers also meets the requirements of a qualified person under the AIM Note for Mining, Oil and Gas Companies and consents to the inclusion of this information in this report in the form and context in which it appears.

 

 

Click on, or paste the following link into your web browser, to view the associated PDF document.

http://www.rns-pdf.londonstockexchange.com/rns/1892F_-2014-4-21.pdf

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLEAALFAAFLEAF
Date   Source Headline
27th Jul 202210:54 amRNSCambay C-77H Re-frac Operations Update No5
26th Jul 20227:54 amRNSChange of Company Name
25th Jul 20227:44 amRNSCambay C-77H Re-frac Operations Update No4
25th Jul 20227:40 amRNSJune 2022 Quarterly Report
25th Jul 20227:30 amRNSSuspension - Oilex Ltd
25th Jul 20227:21 amRNSSuspension of trading on AIM
22nd Jul 20229:21 amRNSPlacement - Issue of Securities and TVR
21st Jul 20227:00 amRNSCambay C-77H Re-frac Operations Update No3
19th Jul 20227:55 amRNSChange of Company Name & AIM Suspension
18th Jul 20229:34 amRNSCambay C-77H Re-frac Operations Update No2
13th Jul 202211:18 amRNSResults of General Meeting
30th Jun 20221:57 pmRNSDirector Dealing
23rd Jun 20227:00 amRNSCambay C-77H Re-frac Operations Update
13th Jun 20227:00 amRNSName Change, Director Option Award, Notice of GM
9th Jun 202212:25 pmRNSHolding(s) in Company
8th Jun 20227:00 amRNSHolding(s) in Company
6th Jun 20227:00 amRNSCambay Production and Operations Update
1st Jun 20229:00 amRNSHolding(s) in Company
1st Jun 20227:00 amRNSPlacement - Issue of Securities
27th May 20227:00 amRNSCambay Reserves Re-classification
17th May 20227:00 amRNSChange of Company Secretary
4th May 20227:00 amRNSCambay Production Update and Fund Raise
28th Apr 20227:00 amRNSMarch Quarterly Report 2022
14th Apr 20222:06 pmRNSSecond Price Monitoring Extn
14th Apr 20222:00 pmRNSPrice Monitoring Extension
14th Apr 20227:00 amRNSCambay India Re-frac Update & Revised Gas Contract
8th Apr 20229:38 amRNSCambay India Production and C-77H Re-frac Update
7th Apr 20224:41 pmRNSSecond Price Monitoring Extn
7th Apr 20224:35 pmRNSPrice Monitoring Extension
4th Apr 202211:16 amRNSCambay India Production Further Update
4th Apr 20227:00 amRNSCambay India Production Update
25th Mar 202210:16 amRNSChange in Substantial Holding
22nd Mar 20227:00 amRNSIssue of Securities and Cleansing Notice
16th Mar 20227:00 amRNSCambay India Update
11th Mar 202211:00 amRNSHalf Year Report 2021
28th Feb 20227:00 amRNSMedway Hub CCS Project
18th Feb 20227:00 amRNSResults of General Meeting
15th Feb 20224:41 pmRNSSecond Price Monitoring Extn
15th Feb 20224:36 pmRNSPrice Monitoring Extension
15th Feb 20222:01 pmRNSPrice Monitoring Extension
11th Feb 20224:42 pmRNSSecond Price Monitoring Extn
11th Feb 20224:36 pmRNSPrice Monitoring Extension
10th Feb 202211:06 amRNSSecond Price Monitoring Extn
10th Feb 202211:01 amRNSPrice Monitoring Extension
7th Feb 20224:19 pmRNSGrant of Environmental Clearance for Cambay Field
7th Feb 20227:00 amRNSCambay PSC Participating Interest Assignment
4th Feb 20224:41 pmRNSSecond Price Monitoring Extn
4th Feb 20224:37 pmRNSPrice Monitoring Extension
4th Feb 20222:06 pmRNSSecond Price Monitoring Extn
4th Feb 20222:01 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.