Watch the latest episode of focusIR Fireside Chats: Why Edinburgh Investment Trust Is Backing Turnaround Stocks for 2026 Growth. View here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksNyota Minerals Regulatory News (NYO)

  • There is currently no data for NYO

COMPLETION PRE-SCOPING STUDY TULUKAPI GOLD PROJECT

1 Feb 2010 07:06

RNS Number : 4260G
Nyota Minerals Limited
01 February 2010
 



 

 

Nyota Minerals Limited ('Nyota' or the 'Company')

 

COMPLETION OF PRE-SCOPING STUDY FOR TULU KAPI GOLD PROJECT

 

HIGHLIGHTS

 

·; Preliminary Desktop Scoping Study ("Study") indicates Tulu Kapi project's economic viability

 

·; Most likely mining scenario is open pit, with early indications a "Big Pit" mining scenario may be feasible

 

·; Additional resource drilling planned for completion in 2010 has the potential to further improve the attractiveness of the Tulu Kapi project

 

·; The evidence to date suggests the existence of a much larger goldfield within the greater Tulu Kapi/Ankore licence area

 

 

Melissa Sturgess, Nyota CEO, commented "we are delighted with the results of the Study, which demonstrates that Nyota has ownership of a robust asset which can be expanded and developed with a high level of confidence. Whilst it is not our intention to commence mining until the resource has been significantly increased in size, this Study clearly shows that a mining operation even at the current resource levels could be viable and confirms that the drillout and development of the asset is warranted."

 

Nyota commissioned Venmyn Rand (Pty) Limited ("Venmyn"), to produce a Preliminary Desktop Scoping Study for the Tulu Kapi Project ("the Project" or "Tulu Kapi"). Venmyn is an internationally recognised South African independent mining and minerals advisor specialising in the technical and economic evaluation of mineral projects.

 

With the intention of developing Tulu Kapi into a viable mining operation, the Study was commissioned to establish whether, at this early stage, based on high level estimates of the capital and operating costs typically associated with a resource of this type, the Project is feasible.

 

The Study was prepared as a 'Preliminary Assessment' under the internationally-recognised Canadian mineral resource classification scheme National Instrument 43-101.

 

The Study considered three mining scenarios:

 

·; the merits of establishing an opencast operation based on the currently defined inferred JORC resource of 690,000oz of gold (Base Case Scenario or Scenario 1);

 

·; the potential upside that could be realised should the current resource extension drilling be successful (Scenario 2); and

 

·; the possibility of an underground operation.

 

The Study's key conclusions were:

 

- Tulu Kapi represents a highly prospective gold project within Ethiopia, with the potential for a number of other prospective targets to add to the current Mineral Resource over time;

 

- at sustained gold prices above US$950/oz, allowing for a discount of approximately 15% to the current gold price, Tulu Kapi has the potential to be developed into a viable open-pit mining operation, even based on the current Mineral Resource, which the Company expects to increase significantly with further Project development;

 

- additional resource drilling planned for completion in 2010 has the potential to further improve the Project's size and attractiveness;

 

- investigation of a conceptual resource extension has demonstrated the potential viability of a single Big Pit to mine each of the Project deposits, rather than separate, adjacent smaller pits;

 

- as a result of these encouraging results, Venmyn considers that the immediate exploration focus of the Project should be in the upgrading of the current Mineral Resource model, particularly the up-plunge area of mineralisation, north-east of the most recent drilling programme campaign and in-fill drilling to satisfy the requirements of Indicated and Measured resource categories;

 

- other satellite exploration targets identified on the current exploration licence areas also have the potential to be developed into future open pit and underground mining areas; and

 

- regionally, the evidence to date suggests the existence of a much larger goldfield within the greater Tulu Kapi/Ankore licence area.

 

Further details about the 3 conceptual mine designs considered in the Study are as follows:

 

Scenario 1 (Base Case):

 

This scenario involved the establishment of an opencast operation based on the currently defined Mineral Resource. It considered a single optimised pit design based on Ordinary Kriging Block Model data with a cut-off grade of 0.5g/t Au. Production was planned at a delivery of 100,000 tonnes per month ("tpm") of ROM to the gold processing plant. Project construction is completed in Years 1 to 2. First production occurs during Year 3. Steady state production is achieved in Year 5. Total project life, including the construction period, is planned for 12 years.

 

Scenario 2:

 

Scenario 2 described the probable extension of additional resource potential outside of the current block model boundary, into adjacent exploration areas (currently the focus of a drilling campaign). This scenario investigated the design of an enlarged pit shell and was referred to as the "Big Pit" Scenario. This required the development of a conceptual block model describing probable mineralisation trends into the north-eastern extension of the currently known resource area. A cut-off grade of 0.5g/t Au was used. Similar operational ramp-up parameters to the Base Case Scenario were considered. Based on a production rate of 100,000tpm, the total operational life in this scenario was extended to 20 years.

 

Scenario 3:

 

Scenario 3 considered the possibility of an underground operation at Tulu Kapi, within the current and extended block model areas. The pit optimisation studies from scenarios 1 and 2 indicated that limited ore resources were available for underground mining after the pit designs and that there was no immediate case for an underground operation given the current knowledge of the resources.

 

Venmyn developed two financial models for the Base Case and "Big Pit" Scenarios described above based on information available as well as that attributable to internationally comparable industry projects. The Study is a preliminary exercise commissioned firstly to demonstrate the robustness of the Project (even at the current stage of its development) and secondly to provide Nyota with operating parameters which can be reflected in ongoing and future resource drilling priorities as the Project is developed and the resource base expands. Venmyn has not reported specific NPV or Project values due to the limitations of the assumptions made at this early stage of Project development. However, it did conclude that the financial models demonstrate that at sustained gold prices above US$950/oz, the Project has the potential to be developed into a viable open-pit mining operation. Moreover, the financial assessment demonstrates the potential of the Project to generate cash flows that could result in a payback of capital within 4-5 years from the date of first production.

 

The financial models prepared by Venmyn indicate the following:

 

Scenario

Grade

Cut-off

Production

Tonnes

Contained Au

NPV

IRR

PaybacK

(g/t Au)

(g/t Au)

(Ktpm)

(Mt)

(Moz Au)

(%)

(yrs)

Base Case

1.24

0.5

100

16.5

0.64

+ve

20

4

"Big Pit"

1.24

0.5

100

22.9

0.88

+ve

15

5

 

Capital costs for the Base Case scenario and utilised in the financial models were estimated at approximately US$62 million. Capital cost estimates were completed to a conceptual level of accuracy of +/- 35%. Operating costs utilised in the financial models were also estimated to a conceptual level of accuracy of +/- 35%, benchmarked from recent similar operations in Africa. Indicative unit operating costs of US$530/oz were used in the Base Case scenario financial model.

 

A copy of the Venmyn Pre-Scoping Study can be found on the Nyota Minerals website. This Study will form the basis of future Pre-Feasibility and Definitive Feasibility Studies.

 

TO VIEW THE VENMYN PRE-SCOPING STUDY, PLEASE CLICK ON THE FOLLOWING WEB LINK:

 

http://www.rns-pdf.londonstockexchange.com/rns/4260G_-2010-2-1.pdf

 

For further information please contact:

 

Melissa Sturgess

Nyota Minerals Limited

(+44) (0)78 2555 1397 or melissa.sturgess@nyotaminerals.com

 

Richard Brown/ Richard Greenfield

Ambrian Partners Limited

(+44) (0)20 7634 4700

 

Press enquiries

Charlie Geller or Leesa Peters

Conduit PR

+44 (0)20 7429 6604/ +44 (0)75 2823 3383

 

Or visit: http://www.nyotaminerals.com

 

 

The technical exploration and mining information contained in this Announcement has been reviewed and approved by Mr RN Chapman. Mr Chapman has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity to which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves and as a qualified person under the AIM Note for Mining, Oil and Gas Companies. Mr Chapman is an employee of Mineral Exploration Management Limited, an independent geological consultancy established in 2005 and is a member of the Australasian Institute of Mining and metallurgy (Aus.I.M.M). Mr Chapman consents to the inclusion in this Announcement of such information in the form and context in which it appears. Venmyn has consented to the inclusion in this Announcement of its name in the form and context in which it appears.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUGUUUPUPUUMG
Date   Source Headline
23rd Jun 20109:53 amRNSCHANGE OF DIRECTORS INTEREST
18th Jun 20108:16 amRNSHoldings in Company
17th Jun 20107:00 amRNSPOSITIVE DRILLING PROGRESS AT TULU KAPI
15th Jun 20109:12 amRNSADDITIONAL PROSPECTIVE GROUND IN ETHIOPIA AQUIRED
14th Jun 20107:00 amRNSCOMPLETION OF ?3.44 MILLION SUBSCRIPTION BY IFC
2nd Jun 20107:00 amRNSRESULTS OF GENERAL MEETING
28th May 20107:03 amRNSFINAL AGREEMENTS SIGNED:IFC SUBSCRIPTION ?3.44MILL
24th May 20107:00 amRNSTRANSFER OF INTEREST IN SWAZIGOLD PROJECT
14th May 20107:10 amRNSNYO APPOINTS TERRY TUCKER:CHIEF OPERATING OFFICER
6th May 20107:11 amRNSTULU KAPI RESOURCE INCREASE - 1.38 MILLION OUNCES
4th May 20107:00 amRNSNOTICE OF MEETING OF SHAREHOLDERS
27th Apr 20107:03 amRNSCHANGE OF DIRECTORS INTEREST
26th Apr 20107:00 amRNSQUARTERLY REPORT 31 MARCH 2010
14th Apr 20107:18 amRNSIFC INVESTMENT IN NYOTA
12th Apr 20107:00 amRNSOPTION TO ACQUIRE NEW PROSPECTIVE ETHIOPIAN AREAS
24th Mar 20107:00 amRNSTULU KAPI DRILLING UPDATE
22nd Mar 20107:00 amRNSBOARD CHANGES
16th Mar 20107:00 amRNSHALF YEAR REPORT 31 DECEMBER 2009
4th Mar 20107:00 amRNSNYOTA APPOINTS OCEAN EQUITIES LTD AS JOINT BROKER
23rd Feb 20104:46 pmRNSIssue of Shares and Options
22nd Feb 20107:00 amRNSRESULTS OF GENERAL MEETING
15th Feb 20107:00 amRNSSHAREHOLDER LETTER
4th Feb 20108:04 amRNSSALE OF INTEREST IN PHILIPPINE COAL PROJECT
3rd Feb 20107:40 amRNSTULU KAPI METALLURGICAL TEST RESULTS
1st Feb 20107:06 amRNSCOMPLETION PRE-SCOPING STUDY TULUKAPI GOLD PROJECT
29th Jan 20107:00 amRNSQUARTERLY REPORT 31 DECEMBER 2009
22nd Jan 20107:00 amRNSNOTICE OF MEETING OF SHAREHOLDERS
20th Jan 20107:14 amRNSEXPLORATION RESULTS:TULU KAPI GOLD PROJECT
7th Jan 20109:25 amRNSHolding(s) in Company
23rd Dec 20097:01 amRNSISSUE OF OPTIONS TO EMPLOYEES AND CONSULTANTS
18th Dec 20097:00 amRNSPLACING TO RAISE GBP2.25 MILLION
30th Nov 20097:00 amRNSResults of Annual General Meeting
13th Nov 20097:27 amRNSUPDATED COMPANY PRESENTATION
12th Nov 20097:01 amRNSNEW TARGETS GENERATED AT TULU KAPI GOLD PROJECT
3rd Nov 20097:00 amRNSUpdated Company Presentation
30th Oct 20097:00 amRNSNotice of Annual General Meeting
30th Oct 20097:00 amRNSQuarterly Report 30 September 2009
23rd Oct 20097:09 amRNSNesta - Completion of Compulsory Acquisition 23100
22nd Oct 20098:07 amRNSNyota Minerals Ltd Shareholder letter Oct 09
16th Oct 20097:00 amRNSAppointment of Executive director
6th Oct 20097:26 amRNSIndependent technical review - Tulu Kapi Project
5th Oct 20097:00 amRNSPOSITIVE EXPLORATION RESULTS PRODUCE NEW TARGETS
29th Sep 20097:04 amRNSStatement re: Name Change and new ISIN
25th Sep 20097:03 amRNSNyota Update - Muremera Nickel Project
22nd Sep 20097:00 amRNSChange of Name and Website Address
14th Sep 20097:02 amRNSTulu Kapi Maiden Inferred Resource - 690000oz Gold
10th Sep 20098:56 amRNS2009 Annual Report
10th Sep 20097:24 amRNSHolding(s) in Company
3rd Sep 20097:17 amRNSIssue of Shares and Options
2nd Sep 20097:00 amRNSResults of General Meeting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.